400 Army Navy DriveFinal Site Plan Amendment (SP #2)
SPRC #3
Aaron Shriber
DCPHD—Planning Division
April 24, 2014
Existing Conditions
2
PenPlace
MetPark
Teardrop
Crystal City Sector Plan
3
Columbia Pike Transit Initiative
July 23, 2012 County Board Meeting
County Board Actions:
1) Accepted the Alternatives Analysis and Environmental Assessment, Volumes I & II and Preliminary Plans for the Columbia Pike Transit Initiative dated May 2012;
2) Adopted the streetcar alternative and alignment, as described in the Locally Preferred Alternative Report, as the Locally Preferred Alternative; and
3) Authorized the County Manager, in cooperation with Fairfax County, to submit an application as the project sponsor for project development approval within the New Starts/Small Starts program of the Federal Transit Administration.
4
Locally Preferred Alternative Report
5
Locally Preferred Alternative Report
6
7
Locally Preferred Alternative Report
8
Locally Preferred Alternative Report
Alternative Site Under Evaluation
9
Army Navy Drive Cycle Track
10
Streetscape Treatments
11
Applicant Proposed Plan Staff Proposed Plan
Applicant Proposed Section Staff Proposed Section
Section View from PenPlace to Site Plan
12
Next Steps
Focus on Ongoing Community Engagement and Facility Planning, Engineering and Design that will be Responsive to the Fabric of the Community
• Staff to Focus on Dual Pronged Approach to the Siting of the Streetcar O & M Facility (In-Progress)
• County to Retain Architectural and Engineering Consultant(s) to Advance Preliminary O & M Facility (Fall/Winter 2014; 15-18 month duration)
• Public Process to Address Site Planning, Design and Construction (Spring 2015)
• Public Facility Review Committee to be Convened as Part of Public Engagement Process
13
14
400 Army Navy Drive Existing Conditions
15
Initial Site Layout Proposal
16
Initial Site Plan Perspective from the Northwest
17
Initial Site Plan Proposal Perspective from Old Eads St.
18
Staff Suggested Site Plan Revisions
• Redesign building and layout to be considerate of existing and proposed institutional uses on adjacent parcels to the west and south
• Pursue vacation of Old Eads Street– Provide 20’ wide alley on west side of property– Alley may be incorporated into streetscape design to provide a buffer
between uses• Relocate residential lobbies to Army Navy Drive
– Eliminate individual residential entries from west and south facades– Secondary lobby entries may be appropriate on west and south facades
• Short term loading and drop-off layby may be provided along 11th Street South
19
Revised Site Plan Layout
20
Revised Site Plan Layout Section
21
Building Elevation Looking East
22
Streetscape Treatments
23
Applicant Proposed Plan Staff Proposed Plan
Applicant Proposed Section Staff Proposed Section