A Consultant perspective on FoundationTM Fieldbus on FPSO

Arasu ThanigaiBusiness Development Manager

Pepperl+Fuchs pte Ltd

Presented on Behalf of EPC companies

Courtesy – P+F, Technip, JGC, Samsung, Bechtel

2Singapore FPSO Seminar - 21 August 2009

Challenges and advantages

• FPSO Overview

• Difference between FPSO and non-FPSO applications

• Why Foundation Fieldbus System?

• Benefits from using FOUNDATION Fieldbus

• The Design of a Fieldbus application

3Singapore FPSO Seminar - 21 August 2009

FPSO PROJECT ACTIVITY OVERVIEW

4Singapore FPSO Seminar - 21 August 2009

MARKET OVERVIEW

5Singapore FPSO Seminar - 21 August 2009

MARKET OVERVIEW

6Singapore FPSO Seminar - 21 August 2009

MARKET OVERVIEW

7Singapore FPSO Seminar - 21 August 2009

MARKET OVERVIEW

8Singapore FPSO Seminar - 21 August 2009

PROJECT OVERVIEW

9Singapore FPSO Seminar - 21 August 2009

PROJECT OVERVIEW

MARKET SEEING CURRENT RECORD DEMAND

10Singapore FPSO Seminar - 21 August 2009

Difference between FPSO and non-FPSO applications

• No major differences

• Components must be selected accordingly

• Marine certification must be checked for system components such as Power Conditioners, field devices, Control system, and the even the cables

• Components ( especially Fieldbus devices, and other accessories) must be chosen in order not to increase the net weight of the platform

11Singapore FPSO Seminar - 21 August 2009

Marine certifications

• All the system components must be certified for marine applications ( corrosive effects, vibration etc)

• Some examples of the marine certification agencies are – Det Norske Veritas (DnV) – American Bureau of Shipping (ABS)– Bureau Veritas (BV) – Llyod’s Register of Shipping – Germanischer Lloyd (GL)– Registro Italiano Navale Group (RINA)

12Singapore FPSO Seminar - 21 August 2009

Marine certifications

• Example of the marine certificate – system components

13Singapore FPSO Seminar - 21 August 2009

Marine certifications

• Marine certificate – for the cable

• The cable flame resistant and flame retardant cable will withstand very high temperature incase of any flames/fires and the system signals should be still maintained until few 100 degs.

• More info from cable manufacturers

• Similarly Marine certification must be checked for field devices and other system componets.

14Singapore FPSO Seminar - 21 August 2009

Why Foundation Fieldbus System?

• Increased Availability - Real time information of the plant health

• Reduced Capex - Reduced cabling, Easy installation, fast commissioning, Plug and Play, self documentation.

• Reduced Operational and Maintenance expenditure–Imbedded predictive intelligence & diagnostics at all levels.

15Singapore FPSO Seminar - 21 August 2009

Why Foundation Fieldbus System?

• Easy Integration with Business Enterprise–Seamless flow of information information –Open Standards (OPC)

• Utilizing Foundation fieldbus reduces cycle time– Engineering– Start-up & Commissioning

• Reduced Driving exposure and Hostile environment

16Singapore FPSO Seminar - 21 August 2009

Benefits from using FOUNDATION Fieldbus

• Installation completed on time

• Cutover completed ahead of schedule

• ROI was less than 18 months

• Better process control

• Increased productivity

17Singapore FPSO Seminar - 21 August 2009

Benefits from using FOUNDATION Fieldbus

Fieldbus Conventional

191 instruments 191 instruments24,000 feet of wire 1,500,000 feet of wire22 homeruns 191 homeruns

Costs: Costs:Wire - $18,400 Wire - $301,000Wiring blocks – $19,100 Junction Boxes - ?Connectors – $17,400 Marshalling - ?Miscellaneous – $7300 Miscellaneous - ?TOTAL - $62,200 TOTAL - > $301,000

18Singapore FPSO Seminar - 21 August 2009

Benefits from using FOUNDATION Fieldbus

• Less equipment and wiring – more signals• Qty of segments 103• Qty of devices 512• Qty of instrument signals 970*

• Example - LNG Project:• Many signals are multiplexed, using Temperature

and Digital Multiplexers and• Digital Valve Controllers

19Singapore FPSO Seminar - 21 August 2009

Benefits from using FOUNDATION Fieldbus

• 458 multiplexed signals – where are the savings?• (if the same conventional functionality is required)• Wiring• Terminations• Inspection• Loop Check• Instrument Cost• Material Handling• Data sheets• Instrument Index• Loop Diagrams

20Singapore FPSO Seminar - 21 August 2009

Fieldbus Design

• Project Standards

• Develop Project Standards• Collect and integrate the relevant standards• Research Existing Standards (Client’s/Engineer’s)• Research Knowledgebases• Develop Project Standards

• Result : Fieldbus Specification is generated which consists of all the project requirements

21Singapore FPSO Seminar - 21 August 2009

Fieldbus Design

• Project Documents – Deliverables

• P&ID Hookup Drawings• Control Narratives Wiring Diagrams• Instrument Index Alarm Strategy• Function Block Index HMI Graphics• Instrument Specifications SAT Procedures• Instrument Datasheets Purchase Requisitions• Network Drawings Purchase Specifications• Control Strategy Drawings Contrast Specifications• Segment Design• Function Block Datasheets• Location Drawings• FAT Procedures

22Singapore FPSO Seminar - 21 August 2009

Fieldbus Design

• Segment Design Considerations

• Control Loops on same segment– Transmitters– Valves

• Power requirements• Virtual Control Relationships• Risk

23Singapore FPSO Seminar - 21 August 2009

Fieldbus Design

• System Architecture

• The Host• – DCS or PLC or a Combination• Network Considerations

- Regulatory Control (Analog Control)– Control Backbone – Proprietary or Open (HSE)– Discretes– Drives

24Singapore FPSO Seminar - 21 August 2009

Fieldbus Design

• System Architecture

• Control-in-the-Field or Control-in-the-Host– Fast, deterministic, tighter control– No need to access the Host– Single loop integrity– Fewer components and more reliable– More scalable

• Discrete/Hybrid/Batch Processing– PLC– DCS– Flexible Function Blocks

25Singapore FPSO Seminar - 21 August 2009

Fieldbus Design

• Physical Layer – The Foundation

– Power Supplies– Power Conditioners– Terminators– Field Junction Blocks– Surge Suppressors– Spur Short Circuit Protection– IS Considerations– Cables– Connectors– Grounding

26Singapore FPSO Seminar - 21 August 2009

Design Consideration

• Fieldbus Reliability issues– Spur short circuit– Power supply failures– Surges– Others

27Singapore FPSO Seminar - 21 August 2009

Design Consideration

• Spur Shorts– short circuit in one of the device or in its spur

cable disable– the segment– (new instrument installation, service of device,

water logging)– The potential problem can be overcome by using

current– limiter between the trunk cable and spur cable

28Singapore FPSO Seminar - 21 August 2009

Design Consideration

• Trunk Cable protection

• If trunk cables cut, then the power to the field is lost• Trunk cable vulnerability is something that is also a

problem• in traditional DCS systems Trunk cable needs to be• protected in a conduit or sturdy cable tray which must be

according to the international wiring regulation regardless of trunk type.

29Singapore FPSO Seminar - 21 August 2009

Design Consideration

• Lightning Surges

• There is no protection against a direct lightning strike

• The ground potential difference can travel over the cable and break down the electrical isolation of Fieldbus devices

• The general rule is that if the a horizontal distance between devices of greater than 70 to 100m or vertical separation greater than 10 to 30m, lightning surge protection should be used

• Proper Grounding methods should be used for effective surge protection of the platform.

30Singapore FPSO Seminar - 21 August 2009

Zone 1

Zone 0/1

IS applications

Ex e

Ex ia(FISCO + Entity)

FieldBarrier

16..32V

16..32V

230VAC

Fieldbus Power Hub

31Singapore FPSO Seminar - 21 August 2009

Design Consideration

• Increasing availability of the physical layer

• Even after ensuring the DCS redundancy, Power supply redundancy, surge protection, Proper cable installation etc, other man made disturbances could affect the availability of the system.

• E.g. loose wires, water ingress, faulty devices, EMC/RFI interference

• Needs dedicated advanced diagnostics tools to locate and troubleshoot the issues

32Singapore FPSO Seminar - 21 August 2009

Design Consideration

• What are the parameters to be checked

Segment voltage, Segment currentSegment noise (low freq, high freq.)Segment signal levelSegment signal jitterInstrument signal levelInstrument signal jitterIndividual Instrument noiseFieldbus terminationSegment earth fault (imbalance)Device communicationCommunication faultsCable degradation (trending

33Singapore FPSO Seminar - 21 August 2009

Control the physical layer

• Supervision and diagnostics– Measurements, Trending, Alarming

• Part of the Power Hub• Online and in real-time

with remote access– from the control room and – via Internet

• Simple-to-use DTMs– Color-coded status indicators– Built-in oscilloscope forgreatest detail

– Commissioning– Operation– Troubleshooting

34Singapore FPSO Seminar - 21 August 2009

35Singapore FPSO Seminar - 21 August 2009

Save time during commissioning

• Cable checkout– Accurate voltage level– Proper termination– Isolation to ground

• Accelarated field device validation– Signal quality and strength– Jitter

• Automatically generatedocumentation

per device and segment …

36Singapore FPSO Seminar - 21 August 2009

Reliable operation – increased uptime

• Snapshot establishes baseline• Configurable alarming• Longterm trending• Predicts data availability• Enables proactive maintenance

Communication hasn‘t failed yet …

37Singapore FPSO Seminar - 21 August 2009

Targeted Troubleshooting

• Fastest time to repair• Remote access for

– Maintenance planning– Assistance by fieldbus expert

• Oscilloscope function– Various triggers– Visual signal inspection

• Pinpoints trouble spot

38Singapore FPSO Seminar - 21 August 2009

Fieldbus Design

• System Acceptance– Factory Acceptance Tests– Interoperability tests are key

• Engineering Workstation interoperability• Device interoperability – all device types• Network components

– Segment operation – all typical segments– Graphics

– Module Acceptance Tests– Network validation• Noise – Watch out for Frequency Drives• Electrical characteristics• Grounding– System Functional Tests

39Singapore FPSO Seminar - 21 August 2009

Project Example

• SMOE Platform– PETRONAS Cahricali

DCS – Rockwell

Power supply - Pepperl+Fuchs High Power trunk concept

Field Junction Box – GRP (P+F)

Field devices – Rosemount , Flowserve, Yokogawa and ABB

40Singapore FPSO Seminar - 21 August 2009

Project Example

• SMOE Platform– PETRONAS Cahricali

41Singapore FPSO Seminar - 21 August 2009

Project Example

• SMOE Platform– PETRONAS Cahricali– Power conditioner redundant

42Singapore FPSO Seminar - 21 August 2009

Project Example

• SMOE Platform– PETRONAS Cahricali– Rockwell DCS

43Singapore FPSO Seminar - 21 August 2009

Project Example

• SMOE Platform– PETRONAS Cahricali

– Field junction box

44Singapore FPSO Seminar - 21 August 2009

Conclusion

As it is evident compared to other instrumentation techniques, Foundation Fieldbus offers substantial overall cost saving and makes the maintenance simpler, it becomes the de facto standard for any Process Industry particularly on FPSO applications.