MINUTES OF PRE
-BID MEETING HELD ON I5
T
JANUARY, 2014
Package-4: Construction of River Training Protection Works (Consisting of
Guide Banks, Gunda Bunds and Cunette) of Shaheed Benazir Bhutto Bridge
over River Indus Connecting Chachran Sharif with Kot Mithan
01. Pre-Bid Meeting was held in NHA Auditorium, HQ, Islamabad at 1100 hours on 15t
January 2014 to discuss the tender documents issued to bidders and to clarify the points, if any,
raised by them. The following attended the m eeting:
ational Highway uthority
i. Mr. Parvez Iqbal Sulehri
ii. Mr. Asim Amin
iii. Mr. Zulfiqar Ali Janjua
iv.
Mr. Parkash
v.
Mr. Nand Kumar Soofi
vi. Mr. Asad Rahat
General Manager (P&CA)
General Manager (Design)
Director (Design)
Director (P&CA)
Director (QS)
Deputy Director (P&CA)
Design
Consultant M/s EA Consulting)
i.
Mr. Hans Aqil
ii. Mr. Siddiq Sulemani
idders
General Manager (Technical)
Head of Highways
i.
Mr. Sajid M ehmood
ii. Mr. Mudasar Yousaf
iii. Lt. Col. (R) Mohsin
iv.
Mr. Amir Mehmood
v. Mr. Abid Farooqi
vi. Mr. Ghulam Hasan
vii. Mr. Naseer Akh tar Shafai
viii.
Engr. Bilal Hussain
ix.
Mr. Fateh Ali Tipu
x. Mr. Tahammul Abbas
M/s Sachal Engg. Works
M/s Matracon Pakistan
M/s RMC
M/s Mishal Sania
M/s Usmani Associates
M/s Habib Construction Services
M/s FWO
M/s Techno Time Construction Co.
M/s Chaudhry Engineers Associates
M/s Sadaat Enterprises
2.
The said meeting was started with welcome to all participants by General Manager
(P&CA) and General Manager (Design). All the participants were asked to introduce themselves
and their Companies on behalf of which they are attending the meeting
3.
General Manager (Design) explained the Project Package-wise details of Shahed Benazir
Bhutto Bridge i.e the Main Bridge i.e. Package-II is under construction by M/s FWO, and Road
from Zahir Pir to Chachran Sharif i.e. Package-III is under construction by M/s RMC. Bids for
construction of Road from Kot Mithon to N-55 i.e. Package-I were opened on 9 t January 2014
for which the Technical Evaluation is under process and it is expected that the said Package-I will
be awarded in next two months period. Whereas the procurement of remaining packages i.e.
Package-2A Road from Chachran Sharif to left Abutment of Main Bridge and Package-2B Road
from right abutment of Main Bridge to Kot Mithon will be initiated soon. So the timely
completion of subject Package-4 River Training Works (Left and Right Guide Bunds, Cunette and
Gunda Bund) is very important due to nature of work further timely completion of this project is
required to o perationalize the b ridge.
Page of 3
7/24/2019 Addendum No 1 & Minuts of Pre Bid Meeting of Shaheed Benazir Bhutto Bridge
2/4
04.
eneral Manger (Design) further explained the subject project location and requirements
of NHA as following:-
a.
All the bidders are instructed to carefully prepare their bids. Prior to prepare the bid, visit
the site location and as this project is of difficult nature. It involves number of creeks and
hauling distance to project work area is also difficult. Further, the River Indus at the
specific location has its unique dynamics during the flood seasons. Thus all these
conditions has to be taken care during construction therefore the bids have to be
synchronized w ith these and rates must be rationalize and wo rkable.
b.
There is no chance to commence the work on site before this year's flood season. The
activities can be commenced at site after September 2014. NHA requires that the
Contractor during this period prepare their plan, mobilization and stocking / arranging the
materials i.e. stone, as huge quantity of stone shall be required for protection wo rk.
c.
After September, the Contractor is required to achieve raising of river training works upto
high flood level before the next flood season (Year 2015) including rip rap.
The
Contractor is required to complete the remaining works by 2
n working season or before
on set of Year 2016 flood seasons. NHA intends to operationalize the bridge by December
2016. In case of failure of above, N HA will not entertain any claim in this regard.
d.
Due to difficult nature of the project, it was agreed that on 20
t
January 2014 all the
bidders may jointly carryout site visit. Director (Design), Design Consultant and Project
Authorities shall be available at site to assist them.
05.
fter the above discussion, the bidders were asked to come forward with their questions /
queries and the bidders raised certain questions / queries regarding subject works. Questions /
queries alongwith replies / answers of the same are as per following details:
Sr.
No.
Questions / Queries
Replies / Answer
Questions of M/s FW O:
i.
Appendix C in specified material
Not accepted as the quantity of Cement is less than
5% and PEC do not allow it.
ist, Cement may be included.
ii. Right of Way SP
-I (1.1) It may
There is no land issue.
be confirmed that Guide Banks,
Cunette and Gunda Bund are
within the Right of Way.
iii.
Trainee Engineers SS-29 As per
Not accepted.
supplementary specifications, 02
No. Trainee Engineers are to be
provided by the Contractor. This
item may be included in the BoQ .
iv. The condition for experience of
Rs. 1,300 Million is very stringent
and may be reviewed by adding
holding of spec Eqpt / Manpower
and F inancial Health / etc.
Please see addendum N o. 01.
Questions of M/s Mishal Sania
v. In idding
ocuments, EC
requirement for this project is CA,
whereas it JV total requirement of
PEC is the cost of project which is
available in C-1 kindly clarify.
Not accepted.
vi.
In BOQ there is no Engineer's
facility, kindly clarify?
Contractor is not required to provided the Engineer's
facility.
g
-..
_
Page 2 of 3
7/24/2019 Addendum No 1 & Minuts of Pre Bid Meeting of Shaheed Benazir Bhutto Bridge
3/4
vii. Project completed amount is 1300
Million of similar nature. Whereas
in Pakistan no Contract of similar
nature done by any Contractor.
Kindly reduce this criteria and
allow any Contractor who have
experience of this type of project.
Please see addendum No. 01.
viii. Appendix C there is only two
items for change of rate whereas
stone is a very huge quantity in
this project this item should also
include.
Not accepted as NHA requires stocking / arranging of
stones before commencement of works.
ix. This project is on River Indus
which is a very huge river in
Pakistan so extra cost for doing
work of bund should also add in
bid.
Not accepted. It should be included in other items
rates of BOQ.
Que stions of M /s Habib Construction Services:
x. Requirement of Technical Staff is
too high?
Not accepted.
xi.
Requirement
f
tructure
Engineer is it required?
Please see Addendum No. 01.
xii.
The fuel factor for price variation
should be increased.
Not accepted, as PEC Price Adjustment Procedure
has been followed.
xiii. Price variation for stone may be
added.
Not accepted.
06.
n addition to above, Director (P&CA) also clarified the following to the Bidders:
a.
In case of Foreign JV, the proposed staff for the subject works must be present at site
during construction phase and it will be considered as default of the Contractor if the
proposed staff be replaced or not present at site. Furthermore, the condition of JV is very
much clear for bidders.
b. No excuse will be accepted from the Contractor in case of stoppage of work due to
delayed / non payment of IPCs, as the Contractor was qualified for award of subject works
as the firm was evaluated Financially Capable to complete the works.
c.
The bidders must read the Bidding Documents carefully before the submission of bids and
no excuse whatsoever will be accepted from bidders that the period of bid security is less
or the bid security is in Financial Bid Envelope etc. The Technical and Financial Bids
must be submitted as per the Instructions to Bidders of the Bidding Document.
07.
lease note that in case of any further questions / queries required to be clarified after this
meeting, the bidders may forward the same to undersigned in writing. Reply will be responded to
the respective bidders and accordingly it will also be uploaded on NHA website for information of
all the interested bidders.
08.
he meeting con cluded w ith a vote of thanks to al] the participants.
---oo0oo---
Page 3 of 3
7/24/2019 Addendum No 1 & Minuts of Pre Bid Meeting of Shaheed Benazir Bhutto Bridge
4/4
ADDENDUM NO. 01
Package-4: Construction of River Training Protection Works
(Consisting of Guide Banks, Gunda Bunds and Cunette) of Shaheed Benazir
Bhutto Bridge over River Indus Connecting Chachran Sharif with Kot Mithan
The following amendments have been made in the Bid Document under this Addendum, which
shall be read and construed as an integral part of Bid Document and shall take precedence in case
of any conflict / ambiguities in the Bidding Document and other provisions of the Bidding
Document.
1.
Bidding Data:
Refer page-22,
ITB Clauses 3.1a(i),
second and fourth line, constructor's category C-A be
replaced with C-B .
2.
Bidding Data:
Refer page-23,
ITB C lauses 3.1a ii),
the whole para be replaced with the following:
Firm that has completed one or more than one project with accumulated cost not less than
Rs. 1,300/- Million in last five (05) years of similar nature and complexity. In case of more
than one Project, the minimum value of each Contract should not be less than Rs. 500 Million.
Experience of firms against the requirement of similar size and nature project as a sub-
contractor will not be con sidered for evaluation.
3.
Bidding Data:
Refer page-30,
ITB Clauses 11.1(C)
contains heading General and Similar Experience
(Appendix N to bid) of Similar Works, the words 1 Contract at second line be replaced
with words one or more than one Contracts .
4.
Bidding Data:
Refer page-31,
ITB Clauses 11.1(C)
contains heading Qualification of Key S taff (Appendix
to bid) under serial No. b, the words roadway Bridges at the end of lines 3 and 6 be
replaced with River Training / Protection Wo rks .
5.
Bidding Data:
Refer page-35, ITB Clauses 20.1(a) and
23.1, the dates be changed as
13
6 February 2014.
6. Appendix-N to Bid:
Refer page-62, Para-2)
Contracts of Similar Size and Nature, the whole para of requirement
be replaced with the following:
Participation as contractor or management contractor within last five (05) years with
accumulated value of Rs. 1,300 Million or with minimum value of Rs. 500 Million each that
have been successfully or are substantially completed and that are similar to the proposed
works. The similarity shall be based on the physical size, complexity, methods, technology or
other characteristics as indicated in these Bidding Docum ents.
7. Special Provisions:
Refer page-103, second line at paragraph-3 of Clause-1.1 of SP-1, the words for the above
facilities be replaced with for their own facilities .
8.
Other terms and con ditions shall remain same.