A Steel, Mines , Cement & Power conglomerate operating in Orissa, Jharkhand, Meghalaya, Maharashtra, Karnataka & West Bengal

Presently a Group having turnover exceeding Rs 5000 Crores

One of the fastest expanding groups in the eastern Region having marketing outlets in India & overseas.

The Group has presence in mining sector at a global level including South Africa, Tanzania, Mozambique, Brazil & Indonesia.

Date Of MoU : 26th Feb, 2004 Location : Kandra ( Dist. Seraikella Kharsawan) Total Land Required : 1584 acres Purchased land : 511 acres ( including CA land) Land acquisition : 265 acres Govt. land : 318.64 acres Coal Linkage : 2,40,000 tons for DRI & CPP

Contd.

Water : Agreement with Water Res Deptt signed in 2005 Water being withdrawn and Cess being paid regularly

Environmental Clearance: Obtained vide letter no. J-11011/899/2007-IA II (I) on 12th March 2009.

Power : 33 kv Power Supply is operational . 132 Kv line completed and awaiting synchronization.

Railway siding : Commissioned and operational. Installed capacity : Phase 1 Completed Investment made : Rs 629 Crores Employment : 2000 persons ( Direct + Indirect)

out of which majority are tribals & local population.

A View of Cooling Tower & SMS

Railway siding View

SMS & New Project site

SMS : Billet dispatch bay

WHRB & ESP of DRI

Kiln 2 of DRI Plant

Railway siding : Another view

Administrative Office Building

30 MW Captive Power Plant

1.2mtpa Pellet Plant

Iron Ore Grinding Building Pelletization Plant

Thickener of Pelletization Plant

Current Status

Phase 1 completed Plant fully operational

– 2 x 350 tpd DRI Units– 30 MW CPP– SMS 2,50,000 tons per annum– Coal washery 500,000 tons per annum– Captive Railway siding – Intake Well for water– 132 KV transmission line – 12, 00000 tons per year Iron Ore Beneficiation & – Pelletisation plant Commissioned

Coal Block Allotted : North Dhadhu

North Dhadhu Coal block was allotted to M/s AAPL, Electrosteel, Jharkhand Ispat & Pawanjay steel & Power through block allotment letter dated 13.01.06.

Geological report was procured from CMPDIL on 29.12.08 Mining Lease application was filed at DMO office, Latehar on 20.06.09.

The same was forwarded by DMO to Director (Mines & Geology) Jharkhand on 26.04.09.

Mining Plan prepared and submitted to MOC. It is in advanced stage of approval.

Plot details of 8 villages within block have been collected from concerned office.

Application for Govt. land (149 Ha) already submitted to DC, Latehar. Socio-economic survey of the villages is being conducted by Nav Bharat

Jagriti Kendra samiti and preliminary report has been submitted.

MILESTONES OF POWER PLANT

ACTIVITY DATES STATUS

ZERO DATE OF PROJECT 19.05.09/31.07.09 19.05.09/31.07.09

BOILER ERECTION START 20.03.10/20.05.10 23.03.10BOILER DRUM LIFTING 30.07.10/30.09.10 27.08.10BOILER HYDRAULIC TEST (NON-DRAINABLE) 30.04.11/30.06.11BOILER LIGHT UP 30.09.11/30.11.11TG BOX UP 24.08.11/24.10.11STEAM BLOWING OPERATION 24.09.11/24.11.11SYNCHRONIZATION (OIL) 24.11.11/24.01.11COAL FIRING 30.11.11/30.01.11COMMERCIAL OPERATION 31.01.12/31.03.12

CLEARANCES OBTAINED ON

CONSTRUCTION POWER 19.08.2008

GANESHPUR COAL BLOCK ALLOCATION 30.06.2009

WATER : ALLOCATION 29.08.09

ENVIRONMENTAL CLEARANCE - UNIT 1 29.08.2009

LONG TERM OPEN ACCESS AGREEMENT WITH PGCIL 03.09.2009

JHARKHAND STATE POLLUTION CONTROL BOARD 10.11.2009

CHIMNEY HEIGHT(275 M) CLEARANCE 23.08.2010

MOEF - TOR CLEARANCE FOR U 2, 3 & 4 29.10.2010

PGCIL CLEARANCE FOR TWO BAYS EXTENSION WITH PGCIL 25.11.2010

RAIL SIDING CLEARANCE 29.11.2010

CLEARANCE STATUS

ESP-1 Erection

PHB - 1

SITE PHYSICAL PROGRESS

Boiler– 1

ESP – 1 :

SITE PHYSICAL PROGRESS

ESP Control Room

SITE PHYSICAL PROGRESS

TG – 1

SITE PHYSICAL PROGRESS

Power House Bldg.#1

SITE PHYSICAL PROGRESS

AHP-Compressor Room

Civil & Structural Work of Main Plant & BoPs (Unit-1):

SITE PHYSICAL PROGRESS

Fly Ash Silo

SITE PHYSICAL PROGRESS

Silo Utility Bldg

SITE PHYSICAL PROGRESS

Chimney

CORPORATE SOCIAL RESPONSIBILITY

“Backbone to corporate sustainability”

Dimensions of CSR

Education

Culture

Health

Infrastructure Utilities

Women Empowerment & Capacity Building

Sports

Infrastructure

Women Empowerment & Capacity Building

Utilities

Health

Education

Sports

Culture