Aldermaston and Burghfield

Post on 22-Jan-2016

38 views 0 download

Tags:

description

Aldermaston and Burghfield. 1952 – 1987 Atomic Weapons Research Establishment 1987 – Atomic Weapons Establishment. Research Computers Lasers Core Punch Material Science. Computers. Aldermaston Blue Oak 2002. Blue Gene Lawrence Livermore Most powerful computer in the world. - PowerPoint PPT Presentation

transcript

Aldermaston and Burghfield

1952 – 1987Atomic Weapons Research

Establishment

1987 – Atomic Weapons

Establishment

Research

ComputersLasers

Core PunchMaterial Science

Computers

Aldermaston Blue Oak 2002

Computers

Blue Gene

Lawrence Livermore

Most powerful computer in the world

Computer projection (Teraflops)

US

AWE

0

100

200

300

400

500

600

700

800

900

1000

2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012

Cost of nuclear computing

US AWE

£320 million per year

?

Orion Laser

Orion Laser

US Equivalent – NIF

US NIF

Completion date:

was 2002

now 2009

Cost:

was £500 million,

now £2 billion

AWE Proposed Orion Laser

Completion

date: 2012 ??

Cost: ????

Current AWE Core Punch

Core Punch

Core Punch

Core Punch

Proposed Core Punch Facility

US Equivalent - DARHT

US DARHT

Completion date:

was 2002

now 2008

Cost:

was £32 million,

now £174 million

AWE Proposed Core Punch

Completion

date: 2012 ??

Cost: ????

Material Science

Proposed new facilities atAldermaston and possibly

also at Burghfield.

US Equivalent - CMRR

Chemical & Metallurgical Research Replacement (Los Alamos)

Timescale: started 2002

completion date 2014

Cost: £500 million

AWE Material SciencesFacilities

Completion date: 2012 ??

Cost: ???

Production

Plutonium (primary)Uranium (secondary)Warhead Assembly

Plutonium production – A90

Plutonium production – A90

Built from 1980 to 1997

To be refurbished.

Work of A90

Secondary Primary

A90 makes the plutonium pit at the centre of the Primary

Uranium Production Facility

Site of proposed Uranium Production Facility

US equivalent

Proposed Uranium Production Facility for the Y-12 site

Proposed US Uranium Facility

Start: 2006Completion: 2013Cost: £400 m

Work of Uranium Prodution Facility

Radiation case

Secondary Primary

US and AWE “Uranium Production Facilities” make secondaries and radiation cases.

Warhead assembly - Burghfield

Current facility

New assembly facility - Burghfield

Current facility

Proposed new facility

AWE Management Ltd

BNFL

Lockheed Martin

Serco

The view from Lockheed Martin

AWE Sandia National

Laboratory

Reliable Replacement Warhead

Trident contract

Accuracy Adjunct

TridentMissile

Replacement