Presenters Richard Stark, Project Services Manager, Apache North Sea Paul Williams, Subsea Projects Manager, Apache North Sea
Itinerary
Apache and Apache North Sea 2011 Subsea Campaigns
Lunch
In progress projects Upcoming projects Apache North Sea – The Future Procurement Questions
INTRODUCTION TO APACHE
2
20 mins
20 mins
APACHE – A GLOBAL COMPANY
3
North Sea
Egypt
Australia
Central
Canada
Argentina
Gulf of Mexico Shelf
Julimar – tie back to platform Wheatstone - LNG plant Balnaves – FPSO Conniston – Tie back to FPSO Macedon - Onshore
Kittimat pipeline
Deepwater
FASP
1Q 2012 Results 769 MBOE/D net Up 7% YOY (50% liquids) $1.2 BN adjusted earnings up 4% YOY $2.6 BN cash flow up 18% YOY 3 BN boe in 2011 YE reserves at all‐time high (46% liquids)
2011 Financial Results 748 MBOE/D net +14 % YOY
(50% liquids) $10.2 BN* cash flow +39 % YOY $4.5 BN earnings +50 % YOY
APACHE – A GROWTH COMPANY
APACHE – LARGEST INDEPENDENT
6 % OF PRODUCTION OUTSIDE NORTH AMERICA
2011
PPR
ODU
CTIO
N (M
boe/
d)
0
100
200
300
400
500
600
700
800
900
1,000
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Acquired Mobil North Sea Limited (Beryl) and a non‐operated interest in the Nelson field
Q1 2012 production up 67% YoY, 41% sequentially with plans for continued ramp up
Bacchus well 1 online April 2012 @ ~6,000 Bbls/d gross
Zero to 40 subsea wells 15 to 80+ pipelines 0% to 20% production from subsea
20,000
30,000
40,000
50,000
60,000
70,000
80,000
90,000
100,000
110,000
Oct‐11 Dec‐11 Feb‐12 Apr‐12 Jun‐12 Aug‐12 Oct‐12 Dec‐12
Net
Rat
e (b
oe/d
) Nelson IMSBacchus IMSBeryl IMSForties + Maule IMSTelford BPFScott BPFNelson BPFBeryl BPFForties + Maule BPF
APACHE – LOCAL GROWTH AND ASSETS
NNS – BERYL PLATFORMS
9
Beryl Alpha • Condeep structure • RAT and flare tower • 2 x drilling rigs • Tanker export (oil) • SAGE export pipeline (gas) • Buckland / Skene / Nevis / Ness / Lewis • Gryphon
Beryl Bravo • Steel jacket • Oil and gas export to Beryl Alpha • 1 x drilling rig • Nevis / Ness / Linnhe
CNS – FORTIES PLATFORMS
• 5 x platforms + FASP • Oil export through Forties Charlie via FPS • Limited gas (power)
CNS – SUBSEA FORTIES AREA
• 14 x infield pipelines • 1 (+) x subsea well (Bacchus) • Impressed Current Cathodic Protection (ICCP)
2011 VESSEL CAMPAIGNS ‐ FORTIES
17
Survey and ROV Inspection – 21 Days Subsea Construction (Non Diving) – 22 Days Diving Support Vessel Works (DSV) – 110 Days Pipelay & Trenching – 30 Days
2011 VESSEL CAMPAIGNS ‐ BERYLS
18
Survey and ROV Inspection – 20 Days Subsea Construction (Non Diving) – 0 Days Diving Support Vessel Works (DSV) – 34 Days Pipelay & Trenching – 0 Days
Seven Atlantic Hydrotest of Riser D1. Switch Skene Power B to C. Riser base spool UT 12th Feb to 22nd Feb 10Ernest Shackleton Beryl Survey (UK portion) 1st July to 14th Aug 20
Bibby Topaz N11 riser re-route and leaking N12 grease nipple repair. N12 AMV visual inspection 8th Aug to 20th Aug 12Bibby Topaz Skene IR investigation and S48 greasing 27th Sept to 1st Oct 4Bibby Topaz N13 (N1y) SCM changeout. Nevis IR investigation and repairs. Attempt at skene caisson 15th Oct to 23rd Oct 8
19
19
FORTIES ALPHA SATELITTE MANHOURS ENGINEERING 331,532hrs CONSTRUCTION 1,453,303hrs WEIGHT STRUCTURAL WEIGHT (tons) 16,647 EQUIPMENT WEIGHT 1,550 PIPING LENGTH (Miles) 10.5 No. OF VALVES 2107 ELECTRICAL , INSTRUMENT & TELECOMMS ELEC. CABLE (Miles) 31.9 ELEC. BULKS (Lights etc.) No. 18435 INST. CABLE (Miles) 86.9 INST. BULKS (Gland/Term etc.) No. 21388
This image cannot currently be displayed.
FORTIES CHARLIE SSIV
22
Completion Status Design 100% complete Valves 100% complete
Structures 50% complete Umbilical 100% complete Flange manufacture 80% complete Pipe manufacture 80% complete Conduit 40% complete
3D Visualisation of SSIV Layout (Brae Import) Valve and Actuator Post Testing
Man
FORTIES CHARLIE SSIV
23
3D Model of SSIV & Structure
Base Frame (shows scale)
36” Pipe Weld Qualification Tests
36” Concrete Coated Pipes
Schedule to Completion All manufacturing complete, Sept 2012 Final items into storage, Oct 2012 Site integration tests, Feb 2013
Phase 1 installation, June 2013 Phase 2 installation, Aug 2013
FORTIES D TO C PIPELINE REPLACEMENT
24
Completion Status Design 100% complete Pipelay 100% complete
Trenching 100% complete Riser manufacture 90% complete Clamp manufacture 90% complete
1ST BERYL CAMPAIGN – NEVIS SOUTH REPAIR
26
Well N13 leaking hydraulic fluid
165 Litres per day being discharged Decision taken to mobilise DSV Original schedule was 3 days for Nevis works SCM changed out in 10 hours All Nevis works completed in 1.5 days Well now back online, no leaks reported
Leak at N13 (greenish fluid)
Airbag change out of SCM
Around 500 unsupported pipeline lengths, freespans, have been identified on the SAGE pipeline (lengths 10m‐57m/ gaps 0.1‐2.0m)
5 of these were addressed in detail as the spans fail the pre‐determined criteria
1 freespan was rectified in March 2012 at the Beryl Alpha SSIV (44m) to prevent any potential for further growth and requirement for annual monitoring
4 remaining critical spans will be re‐inspected in 2012
1ST BERYL CAMPAIGN – SAGE FREESPAN
27
2012 Freespan Repair
Freespan Prior to Repair
LORISTON SOUTH WEST
31
Currently based on using an existing and available tree
Use of PL893 2.5km flexible flowline extension required
Flexible flowline is available and under Apache control
Controls & chemicals, new umbilical required
Umbilical chemical hoses to directly tie into the new tree
FEED engineering starting
NESS SOUTH
33
Currently based on using an existing and available tree
Flexible jumper from N7 flowbase to tree
Injection gas also from N7 or other local flowbase
Controls & chemicals, new umbilical required
Jumpers (6” and 8”) are available in the market
New umbilical required Umbilical chemical hoses to
directly tie into the new tree FEED engineering starting
NEVIS CENTRAL LEWIS 4
35
Currently based on using an existing and available tree
New flowline required, longest lead item currently 12 months
Controls & chemicals, new umbilical required, or alternately put enough cores in Loriston South umbilical
Umbilical chemical hoses to directly tie into the new tree
FEED engineering will start in the next quarter
Aviat (WI 100%)
power demand
diesel
Forties gas
2006
2020
Aviat‐1 was drilled in 3Q 2010 and successfully tested A fuel gas resource for Forties Field 26kM from Forties Alpha Two well tie back A final appraisal well currently being planned Project delivery planned for 2014 Engineering works will commence Q3 2012
AVIAT
FORTIES
NELSON
NORTH SEA REGION – EXPLORATION, DRILLING AND APPRAISAL
38
Forties & Nelson
Beryl
◤ FASP ◤ Forties Echo ◤ Isabella 3D Wide
Azimuth Seismic ◤ Tryfan well ◤ Seagull North Well ◤ Seagull Well ◤ 27th License Round
Tryfan
Seagull & Seagull North Isabella
UK Norway
Qualification for work FPAL
Offshore Construction ‐ Currently Petrofac Onshore Engineering / Offshore Construction – Award Pending
Subsea Project Management Flexlife
Subsea Engineering Detailed Design Award Pending
Subsea Construction ITT being prepared
PROCUREMENT
40