BENSON POLYTECHNIC H.S. MPC #8 / JANUARY 5, 2017
AGENDA / 6:00- 6:15 Introductions
5 min MPC and Design Team Introductions 5 min Project Update - Portland Public Schools
+ Tasks since last MPC + Budget
5 min Bassetti Architects + 60-Day Process and beyond
6:15 - 6:30 Guiding Principles
15 min Results from survey and discussion
6:30 - 6:55 Program Studies (Individual Activity)
5 min Overview
20 min CTE Programs and Academic Cluster Diagrams + Observations + Are we covering everything? + Adjacencies
6:55 - 7:10 Preferred Master Plan Schemes
15 min Results from survey and discussion
7:10 - 8:00 Building Studies (Small Group Activity)
5 min Overview
45 min Small group discussion
8:00 - 8:10 Subcommittee Report
8:10 - 8:20 Closing Thoughts & Next Steps
8:20 - 8:30 Public Comment
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
INTRODUCTIONS /
Caroline Lemay, Principal-in-Charge Lorne McConachie, Design Principal Joe Echeverri, Project Manager
Nancy Hamilton, Community Engagement
Cary Dasenbrock, Design Staff
Dianna Montzka, Design Staff
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
INTRODUCTIONS / BASSETTI EXPERIENCEHIGH SCHOOL EXPERIENCE
+ Roosevelt High School (Portland) + Raisbeck Aviation High School + Bishop Blanchet High School + The Center School + Central Kitsap High School + Chief Sealth International High School + Edmonds Woodway High School + Inglemoor High School + Kingston High School + Klahowya Secondary School + Liberty High School + Lincoln High School + Lynnwood High School + Mercer Island High School + Natrona County High School + The Overlake School + Roosevelt High School (Seattle) + Rock Springs Satellite High School + Shorewood High School + Skyline High School + Stadium High School + Stanwood High School + Todd Beamer High School + Vashon High School
www.bassettiarch.com
PROJECT UPDATE / PORTLAND PUBLIC SCHOOLS
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
BUDGET CONSIDERATIONS / DEFINING THE BUDGET
CONSTRUCTION BUDGET
$122 Million
+ Benson Program Requirements (+/- 385,000 SF)
+ Environmental Health and Safety
+ Seismic Upgrades
+ Energy Code Upgrades
+ ADA
+ HVAC
+ Security / Safety
+ Off-Site Improvements Contingency
+ Design & Estimating Contingency
+ GMP Contingency
+ General Conditions
+ Bonds, Insurance, Overhead & Profit
SOFT COSTS (Outside of Construction Budget)
+ Escalation
+ Swing Space / Temp. Facilities / Phased
Construction
+ Fixtures, Furniture and Equipment (FF&E)
+ Design & Permitting
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
SCHEDULE /
EXISTING CONDITIONS
MASTER PLAN COMMITTEE
PROGRAMMING
FOCUS OPTION ED SPEC
2016
PR
E-D
ILIG
EN
CE
PH
AS
E
2017
N DO N DJ F M A A S OM J J
BENSON HIGH SCHOOL PROJECT SCHEDULE
*COST ESTIMATE
MA
Y B
ON
D
NO
W
JAN
17
MPC MEETINGS8 9 10 11
10
9
8 MPC #8 Agenda: January 5, 2017
+ Guiding Principles
+ Preferred Masterplan Schemes
+ Program & Building Studies
MPC #9 Agenda: January 19, 2017
+ Design Refinement
+ Initial Phasing Studies
+ Program Summary
MPC #10 Agenda: January 31, 2017
+ Presentation by Amy Ruiz
+ Bond overview of all school modernization projects
SCHEDULE / MASTER PLAN COMMITTEE MEETINGS
11
Benson Tech Show: February 16, 2017
+ Design Open House
MPC #11 Agenda: February 23, 2017 (To be confirmed)
+ Process update (Design, Phasing, Program, Budget)
+ Focus Option Ed Spec Development
March - September: Continued development of Ed Spec, Design Refinement and Phasing Studies
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
GUIDING PRINCIPLES /
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
“I would lobby for a strong
multidisciplinary design approach that
draws a broad base of design professionals
into the school.”
“Remembering the past is not
denying the future an opportunity to
shine. For without that historic foundation, the future would not have something to
build upon.”
“The most important principle to me, as a
teacher, is the one that states the importance of
providing a flexible space that can and will support
change.”
“My initial comment is to put an increased effort into the second guiding
principle (Engagement with Business, Government, and
Educational partners).”
“All [of the guiding
principles] are relevant.”
“Benson has always been ever changing.”
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
GUIDING PRINCIPLES / SURVEY FEEDBACK
PROGRAM STUDIES / INDIVIDUAL ACTIVITY
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
PROGRAM STUDIES / APPLIED ARTS
GLAZE
KILN
EXISTING: +/- 1,800 SF PROPOSED: +/- 3,100 SF
2D/3DLAB
KILN
SPECIALTY SPACES
TEACHER PLANNING (TP)
FLEX LEARNING
CLASSROOM (CR)
SUPPORT SPACES
CORRIDOR CIRC. INTERIOR CIRC.
OUTDOOR LEARNING
ROLL-UP DOORDAYLIGHT
STOR2D LAB 3D LAB
ied Arts
PRIMARY ADJACENCY SECONDARY ADJACENCY
MANUF.
DIGITALMEDIA
ARCH.
TP
OUTDOOR RAKU FIRING
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
PROGRAM STUDIES / ARCHITECTURERCHITECTURAL DESIGN & MECHANICAL DRAFTING
DRAFT ARCH.
TP
ENG.
CONST.
PROPOSED: +/- 4,800 SF
DRAFTING
ARCH.CR
TP
STOR.
EXISTING: +/- 3,400 SF
SPECIALTY SPACES
TEACHER PLANNING (TP)
FLEX LEARNING
CLASSROOM (CR)
SUPPORT SPACES
CORRIDOR CIRC. INTERIOR CIRC.
OUTDOOR LEARNING
ROLL-UP DOORDAYLIGHT
SPECIALTY SPACES
TEACHER PLANNING (TP)
FLEX LEARNING
CLASSROOM (CR)
SUPPORT SPACES
CORRIDOR CIRC. INTERIOR CIRC.
OUTDOOR LEARNING
ROLL-UP DOORDAYLIGHT
DRAFT
MANUF.
OUTDOOR WORK AREA
PRINT/PLOT/
LAYPIN UP
STOR
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
PROGRAM STUDIES / AUTOMOTIVE & AVIATION
TOOL STOR.
TP
TOOL STOR.
PROPOSED: +/- 20,300 SF with ADDITIONAL 1,500 SF OUTDOOR WORK AREA
EXISTING: +/- 28,100
DIESELAUTO JR./SR.AUTO JR./SR.
FRESH.
AVIATION
SOPH. ENG.
SOPH. SHOP
STOR
STOR STO
R
RR
WASH.LOCK
WASH.LOCK
STOR
STOR
WASH.LOCK
WASH.LOCK
RR RR
STOR STOR
STOR STOR
STOR
STOR
STOR
STOR
STOR
STORWIND
WASH.LOCK
WASH.LOCKRR
OFFICEOFFICE
STOR STOR
STOR STOR
AVIATIONLAB STOR.
TEST LAB
CR CRCR
CR
CR
CR
CR
SECOND FLOOR:
OUTDOOR WORK AREA
TOOL STOR.
CR
DIESEL SHOPJR./SR. SHOP
CR
FRESH. SOPH. SHOP
CR
STOR
STOR
CR
TP
TOOL STOR.
EQUIP. STOR.
EQUIP. STOR.
SOPH. SHOP
OUTDOOR WORK AREA
RR
OUTDOOR WORK AREA
RR
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
PROGRAM STUDIES / COMPUTER ENGINEERING
COMPUTER ENGINEERING/SCIENCE
JR./SR.
STORSTOR TP
SERV.FRESH./SOPH.TP STOR STOR
COMP. ENG.LAB
EXISTING: +/- 3,700 SF PROPOSED: +/- 4,000 SF
MANUF.
ELEC.
ARCH.
COMP LAB
AUTO.
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
PROGRAM STUDIES / MATH TECH & CONSTRUCTION
CR
JR./SR. CONST.
EQUIP.
STOR. MATRL.STOR.
BUILD.CONST.
STORSTOR
TP TP
RR
EXISTING CONSTRUCTION: +/- 8,200 SF
PROPOSED CONSTRUCTION: +/- 9,500 SF with ADDITIONAL 1,000 SF OUTDOOR WORK AREA
CONSTRUCTION
JR./SR. SHOP
LOAD
CR
TOOL STOR
MATRL. STOR.
MATRL. STOR.
TP
TOOL STORSOPH. SHOP
OUTDOOR WORK AREA
OUTDOOR LOAD
ARCH.
CRSOPH. SHOPALG.
FRSH.SHOPGEO.
SOPHSHOP ALG.
MATH TECH
EXISTING MATH TECH: +/- 2,300 SF
MATRL. STOR.
TOOL STOR
ELEC.
MATH TECH
OUTDOOR LOAD
PROPOSED MATH TECH: +/- 4,900 SF with ADDITIONAL 1,000 SF OUTDOOR WORK AREA
PARKINGDirect
street access
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
PROGRAM STUDIES / DIGITAL MEDIA
DIGITAL MEDIA
PHOTO/WEB LAB
VIDEO/ GRAPHICLAB
PHOTO/VIDEO/SOUNDSTUDIO
CR
STOR.
STOR
RR
STOR
PHOTO STUDIO STOR
DARK RM
FRESH./SOPH.
VIDEO/GRAPHIC
LAB
VIDEO STUDIO
SOUNDSTUDIO
STUDIO/PRESENTATION
STOR
STOR
STOR
RADIO
PROPOSED: +/- 7,800 SFEXISTING: +/- 6,700 SF
PRINT/PLOT/
LAY
PHOTO PREP
FRESH./SOPH. TP
FRESH.
DARKRMS
PHOTO/WEB LAB
STOR
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
PROGRAM STUDIES / ELECTRIC
SR.ELEC.
CRSOPH.ELEC
TP TP
STOR STOR
STOR STOR
JR. ELEC SOPH.ELEC
RRRR STOR TP STOR
FRESH.ELEC
SOPH.ELEC
JR RES/COMMELEC
STOR STOR STORTP STOR
CR
EXISTING: +/- 9,800 SF
PROPOSED: +/- 10,500 SF
TRIC
BLDGCONST.
ARCH.
FRESH.ELEC.
COMP.ENG.
TP
CR
CR
SR AUTOMATION
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
PROGRAM STUDIES / ENGINEERING
GINEERING
ENG.W/
PLASTICS
STOR
STOR
DIRTY LABW/ PLASTICS
CLEAN LAB/CR
STOR
TP
CR
EXISTING: +/- 3,000 SF PROPOSED: +/- 4,900 SF
MANUF.
ARCH.
ROBOTICS
ELEC.
CONST.
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
PROGRAM STUDIES / HEALTH OCCUPATIONS
HEALTH OCCUPATIONS
DENTAL CR
DENTAL LAB
NURSE CR
NURSE LAB
STRLZLAB RR
SCIENCE CR
TPSTORTP
MEDICALCR & LAB
1st RESPND& CR
HEALTH OCC CR
1ST FLOOR
TP
EXISTING: +/- 7,800 SF PROPOSED: +/- 11,100 SF
ANAT. LAB
NURSESIMLAB
1st RESPND
MEDCLINIC
DENTAL
STOR
STOR
STOR
LAUND
FLEX
CONF
SCI.
MATH
LASTRLZ
TP
TPTP
FRESH. FRESH.
TP
MEDICAL
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
PROGRAM STUDIES / MANUFACTURING
UFACTURING
SOPH./JR.WELDING & SHT MTLFRESH.
SENIORMACHININGCR
TPTP
COMP LAB
MANUFAC.SENIOR
CR
ARCH. ENG./PLASTICS
MANUFAC.FRESH.
FOUNDRY
PATTERN SHOP
COMPLAB
MANUFAC.MTL.JR.
SOPH.WELD
FIBERGLSCR
TP
STOR
STOR STOR RR TP
RR
STOR
STOR
TP
TP
STOR
STOR
TP
STOR
RR
TP
EXISTING: +/- 20,000 SF
PROPOSED: +/- 21,400 SF
ENG. ARCH. CONST. ELEC.
COMPLAB
FOUNDRY
PATTERN SHOP
COMPLAB
TP
STOR
TP
ROBOTICS
STOR
STOR
TP
CR
STOR STOR
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
PROGRAM STUDIES / RADIO
RADIO
CR CR
RADIOSTUDIOS RR
CONFBREAK
RECEP.
NON-BENSONRADIO
ELEC.
TP
TP RADIORADIO
PROPOSED: +/- 6,100 SFEXISTING: +/- 5,200 SF
CR CR
RADIOSTUDIOS RR
CONFBREAK
RECEP.
RADIO
ELEC.
TP
TP RADIORADIO
CR
TP
DIGITALMEDIA
INDIVIDUAL ACTIVITY / 20 MINUTES
PREFERRED MASTER PLAN SCHEMES /
c Schools is an equal opportunity educator and employer. 2
ntain all of existing building nection between public spaces into heart of school: o Lobby – Student Center - Plaza ary as 2nd floor linkage in Academic wing
MPC 5 meeting):
se of community of student centered experience making buildings transparent, you can showcase the programs
PROS
+ Sense of community of student centered experience
+ By making buildings transparent, you can showcase the programs
+ Easy zoning of public/private
+ Good re-use of building, more cost efficient
+ Preserves more historic integrity
+ Access to light and space
+ Ability to renovate according to need
+ Comfortable and familiar
+ Less future-forward
+ Good flow of spaces
+ Greater access to freight delivery and removal
+ Greater space for outdoor makerspace adjacencies and storage
+ Possibility of lower hard and soft construction costs
+ Simpler construction logistics
+ Less interruption to scholastic and extracurricular proceeding
+ Allows KPBS and some other historic buildings to remain
+ Allows some programs to continue to operate in existing rooms during construction
+ Central Commons
CONS
+ Auto shop not connected and breaks up plan to create this as a focal point
+ Courtyard would seem cramped
+ Less connection between green (field) and building
+ Don’t want distributed science across building
+ Need better access to second floor classrooms in auto building
+ Does not improve access to CTE
+ Interior courtyard too small
+ Inefficient use of plan
+ No overlook from roof
+ Dark, narrow hallway
+ A lot of ADA/seismic costs required
+ No interior connection
+ Not very imaginative
+ Keeps an uninviting feeling to the campus
+ Doesn’t have good flow through the center
+ Too little demo, very few spaces in remaining existing building that are adequate for program needs
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
MASTER PLAN SCHEME A / SURVEY FEEDBACK
PROS
+ Having more new buildings allows designing spaces to serve today’s needs
+ Building greets in all directions
+ Great access to daylight
+ Open but easily secured
+ New space could be designed to higher seismic standard
+ Creating interaction by compactness
+ More flexibility to re-imagine space
+ New constructions offers better flexibility and fewer unknowns
+ Strong interior connections
+ Roof terrace could be used as school spirit space
+ Green space provides for congregation off street
+ Natural flow of students leads to open space
+ More opportunity for service on perimeter edges
+ Better circulation
+ Has the flexibility to use space in different ways and to create spaces that work best for the Benson Community
+ Connection to field
+ Courtyard size and location
CONS
+ Less reuse of (E) assets
+ Higher cost
+ Tunnel feel of N/S pedestrian connection
+ Outdoor space conflicts with N/S axis
+ Limited access to first floor CTE space
+ Center space could be dark
+ Noise and smell from Auto shop to other parts of the building
+ Demolishes KBPS Building
+ Access from NE Irving Street problematic due to heavy traffic
+ Presumably more expensive than the voters will endorse
+ Improved freight delivery and removal access.
+ Larger space for outdoor makerspace adjacencies and storage
+ Needs to reduce possible higher hard and soft construction costs
+ Needs to improve construction logistics
+ Concerns with how interior courtyard would function with needs of loading/maintenance traffic throughout the day
D
ignificant public spaces combine to create the heart of the school: Student Center, Library, za
akes connections to surrounding urban context nnects building and field to create a unified campus ovides greater flexibility for reimagining CTE spaces
m MPC 5 meeting):
stom designing spaces to serve today’s needs ilding greets in all directions eat access to daylight en but easily secured w space could be designed to higher seismic standard
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
MASTER PLAN SCHEME D / SURVEY FEEDBACK
PROS
+ Gives a new feel to the building
+ Increased efficiency of CTE programs.
CONS
+ Concerns with interior courtyard also being a large project area, is there enough space, security, and storage for that to happen?
+ Demoing C and F wings would cause the campus to lose historic significance (if completly demoed, would prefer gutting).
+ Concerned that the interior courtyard prevents the school from being compact and causes it to be divided.
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
D
ignificant public spaces combine to create the heart of the school: Student Center, Library, za
akes connections to surrounding urban context nnects building and field to create a unified campus ovides greater flexibility for reimagining CTE spaces
m MPC 5 meeting):
stom designing spaces to serve today’s needs ilding greets in all directions eat access to daylight en but easily secured w space could be designed to higher seismic standard
MASTER PLAN SCHEME D / SURVEY FEEDBACK
Adaptations should:
1. Focus on flexibility and adaptability.2. Preserve more historic fabric and functional buildings without sacrificing flexibility.3. Resolve service, delivery and loading access. 4. Enhance daylighting and natural ventilation.5. Balance program, budget and phasing.
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
MASTER PLAN SCHEMES / KEY CONSIDERATIONS BASED ON FEEDBACK
BUILDING STUDIES / SMALL GROUP ACTIVITY
CL-03 F1162,592sf
Glaz lab - F113567sf
Kiln - F1006128sf
ComputerLab
F107568 sf
Pattern Shop F102
3,453 sf
StorageF1002307sf
F1010128sf
storage
C1222,404 sf
C112A1,419sf
C112B1,124 sf
C117548sf
Ceramics - F1005183sf
C1272,667sf
C1039838sf
C12465sf
C125115sf
C126115sf
C128701sf
C1037893sf
C1038116sf
C134486sf
C1027164sf
C1026276sf
C1025290sf
C1382,463sf
C1391,474sf
C1411,129sfC145
504sf
C1021180sf
C102078sf
C1019C1012
C1013128sf
C1011139sf
C14799sf
C100980sf
C1492,349sf
C1023,156sf
C106548sf
C1116,076sf
C10790sf
C100387sf
C1004319sf
C108319sf
C10960sf
C114149sf
C1033130sf
C103280sf
C11880sf
C119130sf
C120148sf
D1404,013sf
LavatoryD1020
31sf
D1031355sf
D1305,092sf
D102164sf
D102378sf
D102778sf
D1024128sf
D1029125sf
D103089sf
D102589sf
D1214,411sf
D1014140sf
D1032B140sf
D1032C78sf
D101578sf
D1017223sf
D1018205sf
D103598sf
D103489sf
D1033130sf
D101173sf
D1007101sf
D1008101sf
D101059sf
D1121,954sf
D1152,008sf
D1036159sfD107
2,296sf
D1002106sf
D1039106sf
StorageD105138sf
CustodialD1004
59sf
D1012,149sf
H10191,333sf
H1020113sf
StorageH1018306sf
Storage126C312sf
127427sf
StorageH1023161sf
StorageH1024163sf
Storage125B135sf
StorageH1014101sf
1252,434sf
1241,062sf
StorageH1010165sf
123499sf
StorageH1009193sf
Trans-formerH1008187sf
122984sf
H1002E159sf
H1002D191sf
H1002C174sf
StorageH1002B
94sf
H1002A377sf
120723sf
119914sf
118914sf
117795sf
116605sf
115605sf
114602sf
113605sf
1024523sf
1025130sf
StorageG1002
49sf
G101102sf
G100314,107sf
Men’sG103365sf
G1008219sf
Girl’sG106225sf
StorageG107241sf
G10097,406sf
G1010241sf
Athletics/HealthG109914sf
Athletics/HealthG110914sf
LavatoryG1012
86sf
004D122sf
004C224sf
1016270sf
1011680sf
100183sf
105600sf
106613sf
107711sf
E1021,452sf
E1031,169sf
E1053,045sf
E109615sf
E100562sf
E1006106sf
E100887sf
E101175sf
E1010344sf
E1102,230sf
E111565sf
E1164,364sf
E114113sf
E118113sf
E119100sf
E113100sf
E1019270sf
E121322sf
E122691sf
E126691sf
E130659sf
E1231,697sfE127
1,623sfE131
1,634sf
E12585sfE124
243sfE12994sf
E128253sfE132
140sfE13394sf
E13493sf
E1361,622sf
E135674sf
E1038146sf
E103794sf
E103694sf
E1431,741sf
E142271sf
E14175sf
E148614sf
E1492,396sf
E14688sf
E15191sf
E152137sf
E1043133sf
E144172sf
E153178sf
E14740sf
E15042sf
StorageH1025B
402sf
Teacher’sRoomL1011327sf
SPED L1010
1,009sf
LibraryL10086,172sf
Computer Lab
L1005580sf
Book Rm.L1004
1,102sf
StorageL100166sf
StorageL100254sf
Book RmL1003529sf
StorageL1007140sf
StorageL100684sf
StorageL1009389sf
StorageL1017B
96sf
StorageL1017C
69sf
StorageL1017D
55sf
L1016116sf
L1015146sf
ClassroomL1014261sf
L1013110sf
L10171,225sf
Confer-ence
RoomL1019
K1016115sf
Class-room 25
K1019486sf
Lounge 12
K101772sf
K1015146sf
K1013254sf
K1012165sf
K1010264sf
K1009412sf
K101190sf
RecordLibrary 8
K1008212sfK1007
86sf
K1029225sf
K1001487sf
K1002644sf
K100589sf
K1004179sf
104323sf
1015449sf
004377sf
Storage125C121sf
Practice Room125D171sf
Elec.VaultL101287sf
RoomL101857sf
Confer-ence
RoomL1020
Conference RoomL1021235sf
L102292sf
L102390sf
L102490sf
L102590sf
L102691sf
L102795sf
English
English
English
English
Health Occ
Science
Science
English
Applied Art 2D/3D Art
VirtualScholars
Wrk Rm
English
English
Ath Director
Reception/ Lobby
Principal
Vice Principal 1
In School Suspension
Vice Principal 2
Dean of Students
Wellness Center
Foundry: Sophomore/ Junior
Manufacturing Tech: Freshman
ClassroomClassroomManufacturing Tech: Senior
Computer area
ClassroomManufacturing Tech: Senior
Welding shop:Sophomore
Presentation Rm:Jr/ Sr
Architecture Drafting CR:
Drafting CR:
Manufacturing Plastics Lab
Fiberglass Area
Welding CR Manufacturing Sheet Mtl ShopJR
Classroom
AM Station 18
Production 17
Studio 14
FM Station 13
Production 21
Studio 11
Elec. 9
ConferenceReception
ListeningK1026
62sf
ListeningK1025
63sfK102294sf
Wood Storage
Equipment Storage
Jr./Sr. Construction
Classroom
Building ConstructionDark RoomDark Room
E10447sf
Digital Media
Digital Media
RoboticsRoboticsComputer LabClassroom
ComputerScience
FreshmanElectronic
Storage
Storage
Computer Engineering
Storage
Storage
Electronics
Storage
Storage
Classroom
ElectronicsShop
M
Custodial
Electronics
Storage
Elec. StorageLavatory
E100739sf
Dark Rm
New Gym
Old Gym
MainDiesil
Flammatory Liquid
Storage
Automo-tive Jr./Sr.
Storage
Storage
Storage
Storage
Storage
Custodial
Storage
Automo-tive Jr./Sr.
StorageD101612sf
StorageD1032D
12sf
StorageStorage
Storage Storage
Storage
Aviation
FreshmanClassroom
SophomoreShop
Storage
LavatoryD101333sf
LavatoryD1012
33sf
StorageD102812sf
StorageD1022
12sf
Storage
Storage
LavatoryD100531sf
Storage
Storage
SophomoreBasic
Engineering
LavatoryC1012
33sf
LavatoryC1019B33sf
Electrical
StorageStorage
Storage Storage
Storage
LavatoryC1024
34sf
LavatoryC1029
35sf
LavatoryC101833sf
LavatoryC1005
33sf
Storage
Class-room
LavatoryC1048
36sfStorage Storage
LavatoryC104433sf
LavatoryC1035
33sf
Storage
Storage Storage
Storage
Lavatory35sf
F100447sf
LockersF1001540sf
Women’sF1012109sf
Men’sF1011119sf
CustodialF101355sf
ShowerG1011
26sfCustodial
G101334sf
CustodialG1007
57sf
Conces-sion
Lavatory100430sf
Lavatory100536sf
Storage101233sf
Safe101327sf
Custodial100923sf
Boy’s Lav.1008260sf
Men101956sf
Women1020322sf
Lavatory101743sf
Locker Rm.
101892sf
ListeningK1020
51sf
ListeningK1021
51sf
StorageK1003
13sf
SprinklerK1006
40sf
CustodialK1014
21sf
StorageK1018
36sfClass-
room 26K1023644sf
StorageK1024
15sf
LavatoryK1027
98sf
LavatoryK1028
98sf
StorageH1025146sf
Storage129
205sf
Men’sH1030242sf
Women’sH1029253sf
Women’sH1026
41sf
Men’sH1027
38sfStorageH1031
30sf
Women’sA1002151sf
StorageA1003
60sf
Ticket BoothA1004
78sf
Men’sA1007149sf
StorageA1005
53sf
Ticket BoothA1006
61sf
Audito-riumA01
7,919sf
StageA10081,747sf
StorageA1011731sf
DressingRoomA1009200sf
LavatoryA1010
27sf
MechanicalA1012
44sf
DressingRoomA1013254sf
LavatoryA1014
44sf
CustodialA1015
61sf
Storage
Storage
Storage
After SchoolProgram
1 Floor8
2 Floors4
3 Floors5
10
11 & 12
2 Floors7
2 Floors1
3 Floors3
3 Floors2
1 Floor6
2 Floors13
2 Floors13
9
Light Renovation
New Construction
Demolition Medium Renovation
Heavy Renovation
Legend
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
BUILDING STUDIES / SCHEME E
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
SCHEME E / FIRST FLOOR
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
SCHEME E-H / LOWER LEVEL
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
SCHEME E / SECOND FLOOR
CL-03 F1162,592sf
Glaz lab - F113567sf
Kiln - F1006128sf
ComputerLab
F107568 sf
Pattern Shop F102
3,453 sf
StorageF1002307sf
F1010128sf
storage
C1222,404 sf
C112A1,419sf
C112B1,124 sf
C117548sf
Ceramics - F1005183sf
C1272,667sf
C1039838sf
C12465sf
C125115sf
C126115sf
C128701sf
C1037893sf
C1038116sf
C134486sf
C1027164sf
C1026276sf
C1025290sf
C1382,463sf
C1391,474sf
C1411,129sfC145
504sf
C1021180sf
C102078sf
C1019C1012
C1013128sf
C1011139sf
C14799sf
C100980sf
C1492,349sf
C1023,156sf
C106548sf
C1116,076sf
C10790sf
C100387sf
C1004319sf
C108319sf
C10960sf
C114149sf
C1033130sf
C103280sf
C11880sf
C119130sf
C120148sf
D1404,013sf
LavatoryD1020
31sf
D1031355sf
D1305,092sf
D102164sf
D102378sf
D102778sf
D1024128sf
D1029125sf
D103089sf
D102589sf
D1214,411sf
D1014140sf
D1032B140sf
D1032C78sf
D101578sf
D1017223sf
D1018205sf
D103598sf
D103489sf
D1033130sf
D101173sf
D1007101sf
D1008101sf
D101059sf
D1121,954sf
D1152,008sf
D1036159sfD107
2,296sf
D1002106sf
D1039106sf
StorageD105138sf
CustodialD1004
59sf
D1012,149sf
H10191,333sf
H1020113sf
StorageH1018306sf
Storage126C312sf
127427sf
StorageH1023161sf
StorageH1024163sf
Storage125B135sf
StorageH1014101sf
1252,434sf
1241,062sf
StorageH1010165sf
123499sf
StorageH1009193sf
Trans-formerH1008187sf
122984sf
H1002E159sf
H1002D191sf
H1002C174sf
StorageH1002B
94sf
H1002A377sf
120723sf
119914sf
118914sf
117795sf
116605sf
115605sf
114602sf
113605sf
1024523sf
1025130sf
StorageG1002
49sf
G101102sf
G100314,107sf
Men’sG103365sf
G1008219sf
Girl’sG106225sf
StorageG107241sf
G10097,406sf
G1010241sf
Athletics/HealthG109914sf
Athletics/HealthG110914sf
LavatoryG1012
86sf
004D122sf
004C224sf
1016270sf
1011680sf
100183sf
105600sf
106613sf
107711sf
E1021,452sf
E1031,169sf
E1053,045sf
E109615sf
E100562sf
E1006106sf
E100887sf
E101175sf
E1010344sf
E1102,230sf
E111565sf
E1164,364sf
E114113sf
E118113sf
E119100sf
E113100sf
E1019270sf
E121322sf
E122691sf
E126691sf
E130659sf
E1231,697sfE127
1,623sfE131
1,634sf
E12585sfE124
243sfE12994sf
E128253sfE132
140sfE13394sf
E13493sf
E1361,622sf
E135674sf
E1038146sf
E103794sf
E103694sf
E1431,741sf
E142271sf
E14175sf
E148614sf
E1492,396sf
E14688sf
E15191sf
E152137sf
E1043133sf
E144172sf
E153178sf
E14740sf
E15042sf
StorageH1025B
402sf
Teacher’sRoomL1011327sf
SPED L1010
1,009sf
LibraryL10086,172sf
Computer Lab
L1005580sf
Book Rm.L1004
1,102sf
StorageL100166sf
StorageL100254sf
Book RmL1003529sf
StorageL1007140sf
StorageL100684sf
StorageL1009389sf
StorageL1017B
96sf
StorageL1017C
69sf
StorageL1017D
55sf
L1016116sf
L1015146sf
ClassroomL1014261sf
L1013110sf
L10171,225sf
Confer-ence
RoomL1019
K1016115sf
Class-room 25
K1019486sf
Lounge 12
K101772sf
K1015146sf
K1013254sf
K1012165sf
K1010264sf
K1009412sf
K101190sf
RecordLibrary 8
K1008212sfK1007
86sf
K1029225sf
K1001487sf
K1002644sf
K100589sf
K1004179sf
104323sf
1015449sf
004377sf
Storage125C121sf
Practice Room125D171sf
Elec.VaultL101287sf
RoomL101857sf
Confer-ence
RoomL1020
Conference RoomL1021235sf
L102292sf
L102390sf
L102490sf
L102590sf
L102691sf
L102795sf
English
English
English
English
Health Occ
Science
Science
English
Applied Art 2D/3D Art
VirtualScholars
Wrk Rm
English
English
Ath Director
Reception/ Lobby
Principal
Vice Principal 1
In School Suspension
Vice Principal 2
Dean of Students
Wellness Center
Foundry: Sophomore/ Junior
Manufacturing Tech: Freshman
ClassroomClassroomManufacturing Tech: Senior
Computer area
ClassroomManufacturing Tech: Senior
Welding shop:Sophomore
Presentation Rm:Jr/ Sr
Architecture Drafting CR:
Drafting CR:
Manufacturing Plastics Lab
Fiberglass Area
Welding CR Manufacturing Sheet Mtl ShopJR
Classroom
AM Station 18
Production 17
Studio 14
FM Station 13
Production 21
Studio 11
Elec. 9
ConferenceReception
ListeningK1026
62sf
ListeningK1025
63sfK102294sf
Wood Storage
Equipment Storage
Jr./Sr. Construction
Classroom
Building ConstructionDark RoomDark Room
E10447sf
Digital Media
Digital Media
RoboticsRoboticsComputer LabClassroom
ComputerScience
FreshmanElectronic
Storage
Storage
Computer Engineering
Storage
Storage
Electronics
Storage
Storage
Classroom
ElectronicsShop
M
Custodial
Electronics
Storage
Elec. StorageLavatory
E100739sf
Dark Rm
New Gym
Old Gym
MainDiesil
Flammatory Liquid
Storage
Automo-tive Jr./Sr.
Storage
Storage
Storage
Storage
Storage
Custodial
Storage
Automo-tive Jr./Sr.
StorageD101612sf
StorageD1032D
12sf
StorageStorage
Storage Storage
Storage
Aviation
FreshmanClassroom
SophomoreShop
Storage
LavatoryD101333sf
LavatoryD1012
33sf
StorageD102812sf
StorageD1022
12sf
Storage
Storage
LavatoryD100531sf
Storage
Storage
SophomoreBasic
Engineering
LavatoryC1012
33sf
LavatoryC1019B33sf
Electrical
StorageStorage
Storage Storage
Storage
LavatoryC1024
34sf
LavatoryC1029
35sf
LavatoryC101833sf
LavatoryC1005
33sf
Storage
Class-room
LavatoryC1048
36sfStorage Storage
LavatoryC104433sf
LavatoryC1035
33sf
Storage
Storage Storage
Storage
Lavatory35sf
F100447sf
LockersF1001540sf
Women’sF1012109sf
Men’sF1011119sf
CustodialF101355sf
ShowerG1011
26sfCustodial
G101334sf
CustodialG1007
57sf
Conces-sion
Lavatory100430sf
Lavatory100536sf
Storage101233sf
Safe101327sf
Custodial100923sf
Boy’s Lav.1008260sf
Men101956sf
Women1020322sf
Lavatory101743sf
Locker Rm.
101892sf
ListeningK1020
51sf
ListeningK1021
51sf
StorageK1003
13sf
SprinklerK1006
40sf
CustodialK1014
21sf
StorageK1018
36sfClass-
room 26K1023644sf
StorageK1024
15sf
LavatoryK1027
98sf
LavatoryK1028
98sf
StorageH1025146sf
Storage129
205sf
Men’sH1030242sf
Women’sH1029253sf
Women’sH1026
41sf
Men’sH1027
38sfStorageH1031
30sf
Women’sA1002151sf
StorageA1003
60sf
Ticket BoothA1004
78sf
Men’sA1007149sf
StorageA1005
53sf
Ticket BoothA1006
61sf
Audito-riumA01
7,919sf
StageA10081,747sf
StorageA1011731sf
DressingRoomA1009200sf
LavatoryA1010
27sf
MechanicalA1012
44sf
DressingRoomA1013254sf
LavatoryA1014
44sf
CustodialA1015
61sf
Storage
Storage
Storage
After SchoolProgram
1 Floor8
2 Floors1
3 Floors3
3 Floors2
1 Floor6
2 Floors7
101 Floor
2 Floors4
3 Floors5
2 Floors 9
11 & 12
10
2 Floors13
1 Floor9
13
3 Floors13
Light Renovation
New Construction
Demolition Medium Renovation
Heavy Renovation
Legend
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
BUILDING STUDIES / SCHEME F
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
SCHEME F / FIRST FLOOR
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
SCHEME F / SECOND & THIRD FLOOR
CL-03 F1162,592sf
Glaz lab - F113567sf
Kiln - F1006128sf
ComputerLab
F107568 sf
Pattern Shop F102
3,453 sf
StorageF1002307sf
F1010128sf
storage
C1222,404 sf
C112A1,419sf
C112B1,124 sf
C117548sf
Ceramics - F1005183sf
C1272,667sf
C1039838sf
C12465sf
C125115sf
C126115sf
C128701sf
C1037893sf
C1038116sf
C134486sf
C1027164sf
C1026276sf
C1025290sf
C1382,463sf
C1391,474sf
C1411,129sfC145
504sf
C1021180sf
C102078sf
C1019C1012
C1013128sf
C1011139sf
C14799sf
C100980sf
C1492,349sf
C1023,156sf
C106548sf
C1116,076sf
C10790sf
C100387sf
C1004319sf
C108319sf
C10960sf
C114149sf
C1033130sf
C103280sf
C11880sf
C119130sf
C120148sf
D1404,013sf
LavatoryD1020
31sf
D1031355sf
D1305,092sf
D102164sf
D102378sf
D102778sf
D1024128sf
D1029125sf
D103089sf
D102589sf
D1214,411sf
D1014140sf
D1032B140sf
D1032C78sf
D101578sf
D1017223sf
D1018205sf
D103598sf
D103489sf
D1033130sf
D101173sf
D1007101sf
D1008101sf
D101059sf
D1121,954sf
D1152,008sf
D1036159sfD107
2,296sf
D1002106sf
D1039106sf
StorageD105138sf
CustodialD1004
59sf
D1012,149sf
H10191,333sf
H1020113sf
StorageH1018306sf
Storage126C312sf
127427sf
StorageH1023161sf
StorageH1024163sf
Storage125B135sf
StorageH1014101sf
1252,434sf
1241,062sf
StorageH1010165sf
123499sf
StorageH1009193sf
Trans-formerH1008187sf
122984sf
H1002E159sf
H1002D191sf
H1002C174sf
StorageH1002B
94sf
H1002A377sf
120723sf
119914sf
118914sf
117795sf
116605sf
115605sf
114602sf
113605sf
1024523sf
1025130sf
StorageG1002
49sf
G101102sf
G100314,107sf
Men’sG103365sf
G1008219sf
Girl’sG106225sf
StorageG107241sf
G10097,406sf
G1010241sf
Athletics/HealthG109914sf
Athletics/HealthG110914sf
LavatoryG1012
86sf
004D122sf
004C224sf
1016270sf
1011680sf
100183sf
105600sf
106613sf
107711sf
E1021,452sf
E1031,169sf
E1053,045sf
E109615sf
E100562sf
E1006106sf
E100887sf
E101175sf
E1010344sf
E1102,230sf
E111565sf
E1164,364sf
E114113sf
E118113sf
E119100sf
E113100sf
E1019270sf
E121322sf
E122691sf
E126691sf
E130659sf
E1231,697sfE127
1,623sfE131
1,634sf
E12585sfE124
243sfE12994sf
E128253sfE132
140sfE13394sf
E13493sf
E1361,622sf
E135674sf
E1038146sf
E103794sf
E103694sf
E1431,741sf
E142271sf
E14175sf
E148614sf
E1492,396sf
E14688sf
E15191sf
E152137sf
E1043133sf
E144172sf
E153178sf
E14740sf
E15042sf
StorageH1025B
402sf
Teacher’sRoomL1011327sf
SPED L1010
1,009sf
LibraryL10086,172sf
Computer Lab
L1005580sf
Book Rm.L1004
1,102sf
StorageL100166sf
StorageL100254sf
Book RmL1003529sf
StorageL1007140sf
StorageL100684sf
StorageL1009389sf
StorageL1017B
96sf
StorageL1017C
69sf
StorageL1017D
55sf
L1016116sf
L1015146sf
ClassroomL1014261sf
L1013110sf
L10171,225sf
Confer-ence
RoomL1019
K1016115sf
Class-room 25
K1019486sf
Lounge 12
K101772sf
K1015146sf
K1013254sf
K1012165sf
K1010264sf
K1009412sf
K101190sf
RecordLibrary 8
K1008212sfK1007
86sf
K1029225sf
K1001487sf
K1002644sf
K100589sf
K1004179sf
104323sf
1015449sf
004377sf
Storage125C121sf
Practice Room125D171sf
Elec.VaultL101287sf
RoomL101857sf
Confer-ence
RoomL1020
Conference RoomL1021235sf
L102292sf
L102390sf
L102490sf
L102590sf
L102691sf
L102795sf
English
English
English
English
Health Occ
Science
Science
English
Applied Art 2D/3D Art
VirtualScholars
Wrk Rm
English
English
Ath Director
Reception/ Lobby
Principal
Vice Principal 1
In School Suspension
Vice Principal 2
Dean of Students
Wellness Center
Foundry: Sophomore/ Junior
Manufacturing Tech: Freshman
ClassroomClassroomManufacturing Tech: Senior
Computer area
ClassroomManufacturing Tech: Senior
Welding shop:Sophomore
Presentation Rm:Jr/ Sr
Architecture Drafting CR:
Drafting CR:
Manufacturing Plastics Lab
Fiberglass Area
Welding CR Manufacturing Sheet Mtl ShopJR
Classroom
AM Station 18
Production 17
Studio 14
FM Station 13
Production 21
Studio 11
Elec. 9
ConferenceReception
ListeningK1026
62sf
ListeningK1025
63sfK102294sf
Wood Storage
Equipment Storage
Jr./Sr. Construction
Classroom
Building ConstructionDark RoomDark Room
E10447sf
Digital Media
Digital Media
RoboticsRoboticsComputer LabClassroom
ComputerScience
FreshmanElectronic
Storage
Storage
Computer Engineering
Storage
Storage
Electronics
Storage
Storage
Classroom
ElectronicsShop
M
Custodial
Electronics
Storage
Elec. StorageLavatory
E100739sf
Dark Rm
New Gym
Old Gym
MainDiesil
Flammatory Liquid
Storage
Automo-tive Jr./Sr.
Storage
Storage
Storage
Storage
Storage
Custodial
Storage
Automo-tive Jr./Sr.
StorageD101612sf
StorageD1032D
12sf
StorageStorage
Storage Storage
Storage
Aviation
FreshmanClassroom
SophomoreShop
Storage
LavatoryD101333sf
LavatoryD1012
33sf
StorageD102812sf
StorageD1022
12sf
Storage
Storage
LavatoryD100531sf
Storage
Storage
SophomoreBasic
Engineering
LavatoryC1012
33sf
LavatoryC1019B33sf
Electrical
StorageStorage
Storage Storage
Storage
LavatoryC1024
34sf
LavatoryC1029
35sf
LavatoryC101833sf
LavatoryC1005
33sf
Storage
Class-room
LavatoryC1048
36sfStorage Storage
LavatoryC104433sf
LavatoryC1035
33sf
Storage
Storage Storage
Storage
Lavatory35sf
F100447sf
LockersF1001540sf
Women’sF1012109sf
Men’sF1011119sf
CustodialF101355sf
ShowerG1011
26sfCustodial
G101334sf
CustodialG1007
57sf
Conces-sion
Lavatory100430sf
Lavatory100536sf
Storage101233sf
Safe101327sf
Custodial100923sf
Boy’s Lav.1008260sf
Men101956sf
Women1020322sf
Lavatory101743sf
Locker Rm.
101892sf
ListeningK1020
51sf
ListeningK1021
51sf
StorageK1003
13sf
SprinklerK1006
40sf
CustodialK1014
21sf
StorageK1018
36sfClass-
room 26K1023644sf
StorageK1024
15sf
LavatoryK1027
98sf
LavatoryK1028
98sf
StorageH1025146sf
Storage129
205sf
Men’sH1030242sf
Women’sH1029253sf
Women’sH1026
41sf
Men’sH1027
38sfStorageH1031
30sf
Women’sA1002151sf
StorageA1003
60sf
Ticket BoothA1004
78sf
Men’sA1007149sf
StorageA1005
53sf
Ticket BoothA1006
61sf
Audito-riumA01
7,919sf
StageA10081,747sf
StorageA1011731sf
DressingRoomA1009200sf
LavatoryA1010
27sf
MechanicalA1012
44sf
DressingRoomA1013254sf
LavatoryA1014
44sf
CustodialA1015
61sf
Storage
Storage
Storage
After SchoolProgram
1 Floor8
2 Floors7
2 Floors1
3 Floors3
3 Floors2
1 Floor6
101 Floor
2 Floors4
3 Floors5
9
11 & 12
10
2 Floors13
3 Floors13
Light Renovation
New Construction
Demolition Medium Renovation
Heavy Renovation
Legend
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
BUILDING STUDIES / SCHEME G
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
SCHEME G / FIRST FLOOR
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
SCHEME G / SECOND & THIRD FLOOR
CL-03 F1162,592sf
Glaz lab - F113567sf
Kiln - F1006128sf
ComputerLab
F107568 sf
Pattern Shop F102
3,453 sf
StorageF1002307sf
F1010128sf
storage
C1222,404 sf
C112A1,419sf
C112B1,124 sf
C117548sf
Ceramics - F1005183sf
C1272,667sf
C1039838sf
C12465sf
C125115sf
C126115sf
C128701sf
C1037893sf
C1038116sf
C134486sf
C1027164sf
C1026276sf
C1025290sf
C1382,463sf
C1391,474sf
C1411,129sfC145
504sf
C1021180sf
C102078sf
C1019C1012
C1013128sf
C1011139sf
C14799sf
C100980sf
C1492,349sf
C1023,156sf
C106548sf
C1116,076sf
C10790sf
C100387sf
C1004319sf
C108319sf
C10960sf
C114149sf
C1033130sf
C103280sf
C11880sf
C119130sf
C120148sf
D1404,013sf
LavatoryD1020
31sf
D1031355sf
D1305,092sf
D102164sf
D102378sf
D102778sf
D1024128sf
D1029125sf
D103089sf
D102589sf
D1214,411sf
D1014140sf
D1032B140sf
D1032C78sf
D101578sf
D1017223sf
D1018205sf
D103598sf
D103489sf
D1033130sf
D101173sf
D1007101sf
D1008101sf
D101059sf
D1121,954sf
D1152,008sf
D1036159sfD107
2,296sf
D1002106sf
D1039106sf
StorageD105138sf
CustodialD1004
59sf
D1012,149sf
H10191,333sf
H1020113sf
StorageH1018306sf
Storage126C312sf
127427sf
StorageH1023161sf
StorageH1024163sf
Storage125B135sf
StorageH1014101sf
1252,434sf
1241,062sf
StorageH1010165sf
123499sf
StorageH1009193sf
Trans-formerH1008187sf
122984sf
H1002E159sf
H1002D191sf
H1002C174sf
StorageH1002B
94sf
H1002A377sf
120723sf
119914sf
118914sf
117795sf
116605sf
115605sf
114602sf
113605sf
1024523sf
1025130sf
StorageG1002
49sf
G101102sf
G100314,107sf
Men’sG103365sf
G1008219sf
Girl’sG106225sf
StorageG107241sf
G10097,406sf
G1010241sf
Athletics/HealthG109914sf
Athletics/HealthG110914sf
LavatoryG1012
86sf
004D122sf
004C224sf
1016270sf
1011680sf
100183sf
105600sf
106613sf
107711sf
E1021,452sf
E1031,169sf
E1053,045sf
E109615sf
E100562sf
E1006106sf
E100887sf
E101175sf
E1010344sf
E1102,230sf
E111565sf
E1164,364sf
E114113sf
E118113sf
E119100sf
E113100sf
E1019270sf
E121322sf
E122691sf
E126691sf
E130659sf
E1231,697sfE127
1,623sfE131
1,634sf
E12585sfE124
243sfE12994sf
E128253sfE132
140sfE13394sf
E13493sf
E1361,622sf
E135674sf
E1038146sf
E103794sf
E103694sf
E1431,741sf
E142271sf
E14175sf
E148614sf
E1492,396sf
E14688sf
E15191sf
E152137sf
E1043133sf
E144172sf
E153178sf
E14740sf
E15042sf
StorageH1025B
402sf
Teacher’sRoomL1011327sf
SPED L1010
1,009sf
LibraryL10086,172sf
Computer Lab
L1005580sf
Book Rm.L1004
1,102sf
StorageL100166sf
StorageL100254sf
Book RmL1003529sf
StorageL1007140sf
StorageL100684sf
StorageL1009389sf
StorageL1017B
96sf
StorageL1017C
69sf
StorageL1017D
55sf
L1016116sf
L1015146sf
ClassroomL1014261sf
L1013110sf
L10171,225sf
Confer-ence
RoomL1019
K1016115sf
Class-room 25
K1019486sf
Lounge 12
K101772sf
K1015146sf
K1013254sf
K1012165sf
K1010264sf
K1009412sf
K101190sf
RecordLibrary 8
K1008212sfK1007
86sf
K1029225sf
K1001487sf
K1002644sf
K100589sf
K1004179sf
104323sf
1015449sf
004377sf
Storage125C121sf
Practice Room125D171sf
Elec.VaultL101287sf
RoomL101857sf
Confer-ence
RoomL1020
Conference RoomL1021235sf
L102292sf
L102390sf
L102490sf
L102590sf
L102691sf
L102795sf
English
English
English
English
Health Occ
Science
Science
English
Applied Art 2D/3D Art
VirtualScholars
Wrk Rm
English
English
Ath Director
Reception/ Lobby
Principal
Vice Principal 1
In School Suspension
Vice Principal 2
Dean of Students
Wellness Center
Foundry: Sophomore/ Junior
Manufacturing Tech: Freshman
ClassroomClassroomManufacturing Tech: Senior
Computer area
ClassroomManufacturing Tech: Senior
Welding shop:Sophomore
Presentation Rm:Jr/ Sr
Architecture Drafting CR:
Drafting CR:
Manufacturing Plastics Lab
Fiberglass Area
Welding CR Manufacturing Sheet Mtl ShopJR
Classroom
AM Station 18
Production 17
Studio 14
FM Station 13
Production 21
Studio 11
Elec. 9
ConferenceReception
ListeningK1026
62sf
ListeningK1025
63sfK102294sf
Wood Storage
Equipment Storage
Jr./Sr. Construction
Classroom
Building ConstructionDark RoomDark Room
E10447sf
Digital Media
Digital Media
RoboticsRoboticsComputer LabClassroom
ComputerScience
FreshmanElectronic
Storage
Storage
Computer Engineering
Storage
Storage
Electronics
Storage
Storage
Classroom
ElectronicsShop
M
Custodial
Electronics
Storage
Elec. StorageLavatory
E100739sf
Dark Rm
New Gym
Old Gym
MainDiesil
Flammatory Liquid
Storage
Automo-tive Jr./Sr.
Storage
Storage
Storage
Storage
Storage
Custodial
Storage
Automo-tive Jr./Sr.
StorageD101612sf
StorageD1032D
12sf
StorageStorage
Storage Storage
Storage
Aviation
FreshmanClassroom
SophomoreShop
Storage
LavatoryD101333sf
LavatoryD1012
33sf
StorageD102812sf
StorageD1022
12sf
Storage
Storage
LavatoryD100531sf
Storage
Storage
SophomoreBasic
Engineering
LavatoryC1012
33sf
LavatoryC1019B33sf
Electrical
StorageStorage
Storage Storage
Storage
LavatoryC1024
34sf
LavatoryC1029
35sf
LavatoryC101833sf
LavatoryC1005
33sf
Storage
Class-room
LavatoryC1048
36sfStorage Storage
LavatoryC104433sf
LavatoryC1035
33sf
Storage
Storage Storage
Storage
Lavatory35sf
F100447sf
LockersF1001540sf
Women’sF1012109sf
Men’sF1011119sf
CustodialF101355sf
ShowerG1011
26sfCustodial
G101334sf
CustodialG1007
57sf
Conces-sion
Lavatory100430sf
Lavatory100536sf
Storage101233sf
Safe101327sf
Custodial100923sf
Boy’s Lav.1008260sf
Men101956sf
Women1020322sf
Lavatory101743sf
Locker Rm.
101892sf
ListeningK1020
51sf
ListeningK1021
51sf
StorageK1003
13sf
SprinklerK1006
40sf
CustodialK1014
21sf
StorageK1018
36sfClass-
room 26K1023644sf
StorageK1024
15sf
LavatoryK1027
98sf
LavatoryK1028
98sf
StorageH1025146sf
Storage129
205sf
Men’sH1030242sf
Women’sH1029253sf
Women’sH1026
41sf
Men’sH1027
38sfStorageH1031
30sf
Women’sA1002151sf
StorageA1003
60sf
Ticket BoothA1004
78sf
Men’sA1007149sf
StorageA1005
53sf
Ticket BoothA1006
61sf
Audito-riumA01
7,919sf
StageA10081,747sf
StorageA1011731sf
DressingRoomA1009200sf
LavatoryA1010
27sf
MechanicalA1012
44sf
DressingRoomA1013254sf
LavatoryA1014
44sf
CustodialA1015
61sf
Storage
Storage
Storage
After SchoolProgram
1 Floor8
2 Floors1
3 Floors3
3 Floors2
1 Floor6
2 Floors7
1 Floor9
101 Floor
2 Floors4
3 Floors5
911 & 12
10
2 Floors13
Light Renovation
New Construction
Demolition Medium Renovation
Heavy Renovation
Legend
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
BUILDING STUDIES / SCHEME H
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
SCHEME H / FIRST FLOOR
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
SCHEME H / SECOND FLOOR
SMALL GROUP DISCUSSION / 45 MINUTES
SUBCOMMITTEE REPORT /
CLOSING THOUGHTS & NEXT STEPS /
Master Plan Committee:
+ Continue to review and think about the design
+ Report back to your constituencies and get
feedback
Design Team:
+ Narrow down the scheme options
+ Refine the design based on feedback
+ Continue review of existing conditions and
CTE equipment survey
+ Continue development of Focus Option
Educational Specification
+ Confirm cost estimate
+ Prepare a final report for the board
QUESTIONS?
NEXT STEPS / MASTER PLAN COMMITTEE
BENSON POLYTECHNIC HIGH SCHOOL / MPC #8 (2017.01.05)
PUBLIC COMMENT / 10 MINUTES