BOSTON ARTS ACADEMYCOMMUNITY MEETING | OCTOBER 26, 2017

2

Welcome & Introduction

Schedule & MSBA Process

Design Update

New Building

Swing Space

Swing Space Implementation

Closing Remarks

Q&A

AGENDA

3

November 9, 2017 Submit Schematic Design Package to the MSBA

November 15, 2017 Anticipate Introducing Funding Agreement to City Council for Consideration

December 1, 2017 Construction Manager @ Risk Interviews

December 13, 2017 MSBA Board Vote & City Council Vote

January 2018 Funding Agreement is executed

Design Development Begins

Construction Manager @ Risk begins work

April 2018 Early Construction Work begins at Cleveland School

July 2018 BAA begins move out of 174 Ipswich Street

Remaining Construction Work @ Cleveland School Begins

August 2018 Construction Complete @ Cleveland School

BAA Moves Into Swing Space

September 2018 Begin Abatement at 174 Ipswich Street

November 2018 Begin Demolition @ 174 Ipswich Street

BAA SCHEDULE UPDATE

4

SITE PLAN

5

NEW BUILDINGLEVEL 1

6

NEW BUILDINGLEVEL 2

7

NEW BUILDINGCATWALK

8

NEW BUILDINGLEVEL 3

9

NEW BUILDINGLEVEL 4

10

NEW BUILDINGLEVEL 5

11

3D VIEWSVAN NESS STREET

12

3D VIEWSIPSWICH STREET

13

3D VIEWSIPSWICH STREET

14

3D VIEWSFENWAY PARK

15

3D VIEWSINTERIOR

16

3D VIEWSINTERIOR – THEATER LOBBY & ENTRANCE

17

SWING SPACE

18

SWING SPACESITE CONTEXT

T

19

SWING SPACELEVEL 1

20

SWING SPACELEVEL 2

21

SWING SPACELEVEL 3

22

THANK YOU