ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 1-38
BTS 3900 ATP
Site Id and Name:
BTS 3900 ATP Snags Classification
ATP Date
Snag Details
Workmanship
Factor(WM) *
Product Factor (PrF)
Planning
Factor (PF)
Note: *
WF: Means Snags reported due to Workmanship /Human Factor.(Technical Expertise , Skills lacking.
Poor Workmanship etc)
PrF: Means Snags reported due to Product Factor/Issues (Product & Design issues/flaws, High fault
rate etc)
PF: Means Snags reported due to Planning factor/Issues (Poor planning and Management etc).
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 2-38
ATP Summary
S. No. Test Items Total Status
T01 Hardware
Acceptance Items
Pass Fail
T01-01 Cabinet Installation 8
T01-02 Antenna System Installation 6
T01-03 Module Installation 2
T01-04 Trunk Cable & Signal Cable
Installation
13
T01-05 Power Cables & PGND
Cables
5
T02 Power ON Test
T02-01 Power Distribution 8
T02-02 Board Indicators 3
T02-03 Charging & Discharging of
Storage Batteries
17
T01 O&M Function
T01-01
Logging in to the Site Maintenance Terminal
System
15
T01-0701 Site Reset in levels 1
T01-0803 Channel Status Check 5
T01-11 Boards Operations 2
T03 RF Specification
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 3-38
T03-0101
VSWR of the Antenna
System
3
T03-0102 DRFU Antenna Power
29
T02 Service Items
T02-01 Basic Services
T02-02 Switching on an MS
3
T02-01 Voice & Data Calls Test
1
T01-0803 Call Status on DRFU
1
T02-0103 Synchronous Handover 3
T02-0104 BCCH TRU Mutual Aiding 1
T02-0105 Frequency Hopping
Function
4
T03-02 External Alarms 16
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 4-38
Part I: OFF-LINE TEST
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 5-38
T01 Acceptance Items for Hardware Installation
T01-01 Acceptance Items for the Installation of BTS3900 GSM Cabinet
T01-0101 Acceptance Items for BTS3900 GSM Installation
Purpose
Verify that the installation of integrated equipment of BTS3900 indoor cabinet complies with the corresponding engineering specifications.
Prerequisite
The BTS3900 cabinet is already installed.
Test Procedure Expectation Result
1. Check the position of cabinet.
The placement of the BTS3900 cabinet complies with the engineering design.
Pass Fail Not Run Zapped
2. Check the installation position.
When installed against the wall, the back of the cabinet must be 0 mm to 98 mm away from the wall. The cabinet is located near the feeder encapsulation window to minimize the length of the feeder. A height of at least 200 mm is spared for routing the feeder on the top of cabinet. The BTS cabinet can be installed side by side with the cabinet of other equipment.
Pass Fail Not Run Zapped
3. Check all bolts, flat washers, and spring washers.
All bolts are fastened. The spring washer is installed between the bolt and the flat washer. The base (anchor) fits into the expansion bolt holes properly.
Pass Fail Not Run Zapped
4. Check the connection between the cabinet and the base.
The cabinets are securely connected to the bases and are stable.
Pass Fail Not Run Zapped
5. Check the horizontal error and vertical error.
The horizontal error of the cabinets is less than 3 mm and the vertical error is not more than 3 mm.
Pass Fail Not Run Zapped
6. Check the installation of the base.
If no ESD floor is equipped to the equipment room, install the base. If the ESD floor is equipped to the equipment room, install the support and the base. The surface for laying the ESD floor must not be higher than the lower surface of the base; otherwise, the heat dissipation of the base is affected.
Pass Fail Not Run Zapped
7. Check the cleanness and labels.
Clean both inside and outside surface of the cabinet. The surface of cabinet is clean. The paint is intact. The labels are correct, clear, and intact.
Pass Fail Not Run Zapped
8. Check the front door of the cabinet.
The front door of the cabinet opens and closes easily. .
Pass Fail Not Run Zapped
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 6-38
Remarks
None.
T01-0102 Acceptance Items for BTS3900 GSM Antenna Installation
Purpose
Verify that the antenna system installation meets the engineering requirements. The engineering parameters of antenna are as follows:
Prerequisite
The antenna system is already installed
Test Procedure Expectation Result
1. Check the feeders.
Connection Grounding Arrangement label
1) The feeders are correctly connected and arranged in the right sectors. (2) The feeders are arranged orderly and neatly.
(3) The labels are attached in compliance
with the engineering specifications.
Pass Fail Not Run Zapped
2. Check the grounding bar. (1) Grounding
(2) Insulation
The outdoor grounding bar is connected to the underground grounding grid through a dedicated route. The indoor grounding bar is connected to the outdoor grounding bar or is directly grounded nearby. The grounding bar is insulated from the wall. The grounding cable is as short as possible.
Pass Fail Not Run Zapped
3. Check the antenna
installation.
The antenna is installed in compliance with the engineering specifications, such as the position, azimuth, and down tilt.
Pass Fail Not Run Zapped
4. Check the jumpers.
Connector Bending
The connectors of all the outdoor jumpers are waterproofed. Waterproof curves are
made for the jumpers. The bending radius of the jumper should be 20
times larger than its diameter.
Pass Fail Not Run Zapped
5. Check whether
antenna tilt and
orientation mechanical
clamps available
The antenna mechanical clamps are installed properly. Antenna tilt and orientation can be
done.
Pass Fail Not Run Zapped
6. Check RF Antenna type
along with TMA installed as
per RF nominal Plan.
Check whether Antenna type is installed as per RF
Nominal Plan. Mention Antenna make and model
below:
Sector 1:
Sector 2:
Sector 3:
Pass Fail Not Run Zapped
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 7-38
Remarks
None.
T01-0103 Acceptance Items for Module Installation
Purpose
Verify that the installation of the module complies with the corresponding engineering specifications.
Prerequisite
All the modules are installed. The ends of all power cables are coated with protective sleeves.
Test Procedures Expectation Result
1. Check whether the BBU, the GRFU/DRFU modules are correctly installed.
They are correctly installed. Pass Fail Not Run Zapped
2. Check whether the screws for fastening the modules are secured on the cabinet.
The screws for fastening the modules are secured on the cabinet.
Pass Fail Not Run Zapped
Remarks
None
T01-0104 Acceptance Items for Installation of Trunk Cables and Signal Cables
Purpose
Verify that the installation of the trunk cables and signal cables complies with the corresponding engineering specifications.
Prerequisite
The trunk cables and the signal cables are installed.
Test Procedures Expectation Results
1. Check the cabling. The cabling meets the engineering specifications, without cable crossover and damage. The cabling facilitates maintenance and further capacity expansion. The trunk cables and power cables are placed respectively.
Pass Fail Not Run Zapped
2. Checking the trunk cables:
(1) Connector
(2) Bending
(3) The connectors of trunk cables are intact. The connectors of E1 cable are reliable and intact.
(4) The turning radius of coaxial cables is kept no less than 40 mm to prevent the wire core
Pass Fail Not Run Zapped
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 8-38
from being damaged.
3. Checking the cable ties (1) The cables ties face the same direction. The cable ties in the equivalent position must be in a horizontal level.
(2) The extra part of the cable ties is evenly cut off and the cut surface does not have any sharp edges.
(3) No cable tie is wounded up.
(4) In the outdoor environment, each cable tie has a reserved length ranging from 3 mm to 5 mm.
Pass Fail Not Run Zapped
4. Check the cables on the cable rack.
(1) The cables on the cable rack are neatly bound.
(2) The cables are bound neatly and tightly. The cable ties are evenly spaced.
Pass Fail Not Run Zapped
5. Check the cables in the cabling trough.
The cables laid in a cabling trough may be bundled or not. If the cables are laid in a cabling trough, they are laid neatly without crossover and do not overrun the trough. The cables are tied when led into and out of the trough or when converting into another direction.
Pass Fail Not Run Zapped
6. Check the margin of trunk cable.
When trunk cables are laid in overhead and under floor cabling mode, a little margin is left at turns at the bottom of racks.
Pass Fail Not Run Zapped
7. Check the cable labels. Both ends of trunk cables are stuck with standard engineering labels to identify the position of the cables. The labels are clear.
Pass Fail Not Run Zapped
8. Check RF cables:
(1) Installation
(2) Cabling
(3) The connectors of the RF cables are fixed in position to avoid false connection that may cause an abnormal voltage standing wave ratio (VSWR). The RF cables are intact.
(4) The horizontal RF cables are clamped into the cable trough.
Pass Fail Not Run Zapped
9. Check power cables. (1) The cables are neatly connected to the power port of each module.
(2) Cables with an extra length are reserved at the connectors.
Pass Fail Not Run Zapped
10. Check the CPRI cable (1) The two ends of the CPRI cable is neatly connected.
(2) The CPRI cables neatly and tightly bound. The cable ties are evenly spaced and face the
Pass Fail Not Run Zapped
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 9-38
same direction.
(3) Proper surplus length is reserved for the CPRI cables near connectors for easy inserting and pulling of the connectors.
11. Check the ports of modules.
The unused ports are covered with dust-proof covers and matching plugs.
Pass Fail Not Run Zapped
12. Check the installation of indoor jumpers.
(1) The indoor 1/2-inch jumpers are distributed according to the layer and sector.
(2) The indoor 1/2-inch jumpers are kept straight for 300 mm at their joints with the cabinet.
Pass Fail Not Run Zapped
13. Check the environment monitoring cables.
The environment monitoring cables are securely and neatly installed.
Pass Fail Not Run Zapped
Remarks
None.
T01-0105 Acceptance Items for Power Cables and PGND Cables
Purpose
Verify that the power cables and PGND cables are correctly processed and installed.
Prerequisite
None.
Test Procedures Expectation Result
1. Check the specifications of power cables and PGND cables.
(1) The PGND cable is green and yellow.
(2) The –48 V power cable is blue.
(3) The connectors in use on the power cables are capped with protective sleeves.
(4) All the power cables and grounding cables are copper-core cables. The outer diameter of the external power cables and grounding cables is about 11 mm.
Pass Fail Not Run Zapped
2. Check the labels and power cables.
(1) Labels are attached to ends of the power cables and PGND cables.
(2) The power cables or grounding cables are not short-circuited or connected reversely.
(3) The power cables or grounding cables are not damaged or broken.
(4) There are no connectors or
Pass Fail Not Run Zapped
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 10-38
joints on the power cables or grounding cables.
3. Check the connectors and wiring terminals of power cables and PGND cables.
(1) The lugs at both ends of the power cable or the PGND cable are securely soldered or crimped.
(2) The bare wires and lug handles at the wiring terminals are tightly wrapped up with insulation tapes or heat-shrinkable tubes.
(3) Flat washers and spring washers are securely and closely mounted on wiring terminals.
Pass Fail Not Run Zapped
4. Check the layout of power cables and PGND cables.
(1) The power cables and PGND cables are bound separately from other cables. The extra part of cables are trimmed rather than coiled up.
(2) Breaking devices such as switches and fuses are not included in the electric connection of the grounding system.
Pass Fail Not Run Zapped
5. Check system grounding requirements.
(1) The diameter of the positive pole of the primary power supply connected to the earth complies with the engineering specifications.
(2) The working grounding and protection grounding of the BTS and the surge protection grounding of the building share one group of grounding
Pass Fail Not Run Zapped
Remarks
None.
T01-02 Acceptance Items for Power-on Test
T01-0201 Acceptance Items for Power Distribution
Purpose
Verify that the power distribution of the BTS3900 works properly.
Prerequisite
The external –48 V DC power supply system works properly.
Test Procedures Expectation Result
1. Check the -48 V DC power cables of
(1) The -48 V DC power cable (blue) is connected to the
Pass Fail Not Run Zapped
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 11-38
cabinet. NEG(-) terminal on the DCDU-01 power input terminal block.
(2) The PGND cable (black) is connected to the RTN(+) terminal on the DCDU-01 power input terminal block.
2. Check the input voltage.
Measure the input voltage by using a multimeter. The input power complies with the standard.
Pass Fail Not Run Zapped
3. Set the switch to ON to enable the power module.
The power module runs properly. Pass Fail Not Run Zapped
4. Check the DCDU voltage.
The output voltage of the DCDU-01 module ranges from -38.4 V DC to -57 V DC.
Pass Fail Not Run Zapped
5. Check the power-on of modules.
Set the BBU switch on the DCDU-01 module to ON.
The power-on of each module is normal.
Pass Fail Not Run Zapped
6. Power off the BBU and then power on it
The states of the RUN indicators on the GTMU module change from off to on (including the state of blinking). All the modules work properly.
Pass Fail Not Run Zapped
7. Power off the GRFU/DRFU module and then power on it
The LED works properly: the RUN LED blinks, the ALM LED is off steady, the ACT LED is on steady, the VSWR LED is off steady, and the green LED labeled CPRI0 and CPRI1 are on.
Pass Fail Not Run Zapped
8. Power off the FAN and then power on it
The RUN LED on the panel blinks normally to indicate the normal running of the board. The board is in normal operation.
Pass Fail Not Run Zapped
Remarks
Test engineers must wear ESD wrist straps or ESD gloves.
T01-0202 Acceptance Items for Board Indicators
Purpose
Verify that the indicators on each board work properly.
Prerequisite
The BTS is powered on or running.
Test Procedures Expectation Result
1. Check the board indicators.
2. Running
The board indicators display the running status of boards. For example, the generation and clearance of alarms are displayed
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 12-38
3. Status exactly and in time during power-on and loading.
The indicators work properly when the boards run properly.
Pass Fail Not Run Zapped
Remarks
Pay attention to the running status of the indicators on the GTMU, GRFU/DRFU when the BTS is powered on or reset.
T01-0203 Charging & Discharging of Storage Batteries
Purpose
Verify that the storage batteries can be normally charged and discharged after the mains power supply for
the BTS3009 cabinet is switched on.
Prerequisite
The BTS is powered on or running.
Test Procedures Expectation Result
1. Check the current of the
storage battery
Start the Site Maintenance Terminal System. Query the current of the storage battery (1) Select the target module and double-click View Resource. The View Resource dialog box is displayed. (2) Select Current of battery from the Select Resource Type drop-down list box. The current of the battery is a positive value,
indicating that the battery is being charged.
Pass Fail Not Run Zapped
2. Switch off the mains power supply and query the Current of battery again.
The current of the battery is a negative value, indicating that the battery is being discharged.
Pass Fail Not Run Zapped
3. Switch on the mains power supply.
The current of the battery can be queried.
Pass Fail Not Run Zapped
4. Check the inter-connection of battery
The inter-connection of each battery is proper. The three 50AH bank is connected in loading sharing mode. The total capacity is 150AH.
Pass Fail Not Run Zapped
5. Check the labeling of battery cables
The label of battery cables are marked properly.
Pass Fail Not Run Zapped
6. Check the voltage of battery.
The detail will be filled in the table as follows:
Pass Fail Not Run Zapped
7. Battery bank specs & BOQ Check that battery banks specs as provided as per approved BOQ. i.e. (12V/Cell, 150Ah & 155Ah)
Pass Fail Not Run Zapped
8. Quantity of banks Check that battery banks are provided for cabinet site as per approved BOQ
Pass Fail Not Run Zapped
9. Batteries physical condition Check that the batteries condition is good i.e. batteries are not damaged/swollen
Pass Fail Not Run Zapped
10. Capacity & Rating of banks Check that all the battery banks and cells are provided of same capacity rating i.e. (Voltages, Amp Hour)
Pass Fail Not Run Zapped
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 13-38
11 Health check of battery banks
PTML standard battery health check template (attached) is attached with ATP documents for battery testing.
Pass Fail Not Run Zapped
12. Voltage measurement of batteries
Take the complete cell by cell voltage readings before commencing battery test.
Pass Fail Not Run Zapped
13. Battery heath check Shutdown the AC Input supply of Rectifier to take batteries on load
Pass Fail Not Run Zapped
14. Battery heath check Check the batteries feeding power to load after disconnection of AC power
Pass Fail Not Run Zapped
15. Battery heath check Take the complete bank & cell voltage readings after every 30 mins
Pass Fail Not Run Zapped
16. Battery heath check Check that tested battery backup for cabinet is as per designed backup
Pass Fail Not Run Zapped
17. Battery heath check Is tested battery backup is up to/greater than designed backup
Pass Fail Not Run Zapped
REMARKS:
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 14-38
Huawei Representative
Name:_____________________
Signature:__________________
Date:______________________
PTML Representative
Name:_____________________
Signature:__________________
Date:______________________
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 15-38
Part II: ON-LINE TEST
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 16-38
T01 O&M Function Acceptance Items
T01-01 Login
T01-02 Logging In to the Site Maintenance Terminal System
Objective
Verify that you can log in to the Site Maintenance Terminal System and implement O&M operations through the system.
Prerequisites
The BTS operates normally.
The Ethernet cable between the Site Maintenance Terminal System and the BTS is connected properly.
Procedure Expected result Result
Start and log in to the Site Maintenance Terminal System.
(1) Choose User Management > Login to display the Log in
dialog box.
(2) Enter your user name and password and click OK.
You can log in to the Site Maintenance Terminal System and implement O&M operations.
Pass Fail Not Run Zapped
Remarks
None
T01-03 Site Management Right
T01-0301 Site Management Right
Objective
Verify that you can obtain and release site management right through the Site Maintenance Terminal System.
Prerequisites
The Site Maintenance Terminal System and the BTS communicate normally.
You have logged in to the Site Maintenance Terminal System successfully.
Procedure Expected result Result
1. Obtain the site management right.
(1) Click Site and then double-click Site management right in
the right pane.
(2) Click Get in the Site Management Right
1. The site management right is obtained.
(1) The system prompts that the site management right is obtained successfully.
(2) One minute after the serial port cable is removed .the site management right is released.
Pass Fail Not Run Zapped
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 17-38
dialog box.
(3) Remove the Ethernet cable between your PC and the BTS and wait for one minute, and then check whether the site management right is released.
2. Release the site management right.
(1) Click Site and then double-click Site management right in
the right pane.
(2) Click Release in the Site Management Right dialog box.
(3) Check whether the site management right is released.
The system prompts that the site management right is released successfully.
Pass Fail Not Run Zapped
Remarks
After obtaining the site management right, you can perform operations and maintenance on the BTS through the Site Maintenance Terminal System, but you cannot write data to the BTS through the remote Site Maintenance System.
After releasing the site management right, you cannot carry out operations such as resetting of the BTS, but can only read data from the BTS through the Site Maintenance Terminal System.
T01-04 Logout
T01-0401 Normal Logout
Objective
Verify that you can log out of the Site Maintenance Terminal System under normal conditions.
Prerequisites
The BTS operates normally.
The Site Maintenance Terminal System and the BTS communicate normally.
Procedure Expected result Result
1. Choose Maintenance > Quit
to log out of the Site Maintenance Terminal System.
The Site Maintenance Terminal System window is closed.
Pass Fail Not Run Zapped
2. Change the site management state through the remote Site Maintenance System.
You can change the attributes of the operation objects through the remote Site Maintenance System.
Pass Fail Not Run Zapped
Remarks
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 18-38
After you log out of the Site Maintenance Terminal System, the site management right is handed over to the remote Site Maintenance System automatically.
T01-05 Topology Management
T01-0501 Topology Management
Objective
Verify that you can view the Topology Management through the Site Maintenance Terminal System.
Prerequisites
The Site Maintenance Terminal System and the BTS communicate normally.
Procedure Expected result Result
3. Click Board. Double-click Board Management.
The Board Management window is
displayed.
Pass Fail Not Run Zapped
4. In the Board Management window, double-click GTMU.
The Topology Management window
is displayed, ensure the consistency between the hardware installation and the data configuration.
Pass Fail Not Run Zapped
Remarks
None.
T01-06 Resource Viewing
T01-0601 Resource viewing
Objective
Verify that you can view the resources through the Site Maintenance Terminal System.
Prerequisites
The Site Maintenance Terminal System and the BTS communicate normally.
Procedure Expected result Result
5. Click Site and then double-click View Resource in the right pane of the Site Maintenance Terminal System
window.
The View Resource dialog box is
displayed.
Pass Fail Not Run Zapped
6. Choose a resource item in Select Resource Type.
The status of the resource can be refreshed in the View Resource
dialog box in a real time manner.
Pass Fail Not Run Zapped
Remarks
None
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 19-38
T01-07 Equipment Management
T01-0701 Site Reset Hierarchically
Objective
Verify that the site can be reset hierarchically through the Site Maintenance Terminal System.
Prerequisites
The Site Maintenance Terminal System and the BTS communicate normally.
You have obtained the site management right through the Site Maintenance Terminal System.
Procedure Expected result Result
1. Click Site and then double-click Site Reset Hierarchically
in the right pane of the Site Maintenance Terminal System
window.
2. Select Third Level Reset and then click OK.
3. Click Site and then double-click Site Reset Hierarchically
in the right pane of the Site Maintenance Terminal System
window.
4. Select Forth Level Reset and then click OK.
(1) The Site Reset Hierarchically
dialog box is displayed.
(2) The system prompts that the hierarchical reset is successful.
(3) The Site Reset Hierarchically
dialog box is displayed.
(4) The system prompts that the hierarchical reset is successful.
Pass Fail Not Run Zapped
Remarks
After the site is reset, it is re-initialized. During the re-initialization course, no operations on the site can be carried out. When the Site Maintenance Terminal System window is refreshed, it means the
re-initialization is complete.
During the third level reset, only the data is loaded while program is not.
T01-0702 Cell Management State Changes
Objective
Verify that the cell management state can be changed through the Site Maintenance Terminal System.
Prerequisites
1. The Site Maintenance Terminal System and the BTS communicate normally.
You have obtained the site management right through the Site Maintenance Terminal System.
Procedure Expected result Result
1. Block the cell
(1) Click Cell and then double-click Change Cell Management
(1) The Change Cell Management State dialog box
is displayed.
(2) A prompt "Changing state
Pass Fail Not Run Zapped
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 20-38
State in the right pane of the Site Maintenance Terminal System
window.
(2) Choose LOCKED and then click OK.
(3) Obtain the cell attributes and the attributes of the objects under this cell. Check the management state of the objects.
(4) Observe the color of each GRFU/DRFU under this cell and check the board information.
successfully" is displayed on the status bar.
(3) The management state of each object is LOCKED.
(4) The color of each GRFU/DRFU is dark green. The board information shows “Manual block."
2. Unlock the cell
(1) Click Cell and then double-click Change Cell Management State in the right pane of the Site Maintenance Terminal System
window.
(2) Choose UNLOCKED and then click OK.
(3) Obtain the cell attributes and the attributes of the objects under this cell. Check the management state of the objects.
(4) Observe the color of each GRFU/DRFU under this cell and check the board information.
(1) The Change Cell Management State dialog box
is displayed.
(2) A prompt "Changing state successfully" is displayed on the status bar.
(3) The management state of each object is UNLOCKED.
(4) The color of each GRFU/DRFU is dark green. The board information shows “Normal.”
Pass Fail Not Run Zapped
Remarks
When the cell management state is changed to LOCKED, the calls of the subscribers in this cell are interrupted.
Before the cell management state is change to UNLOCKED, the MS in this cell cannot access to the network.
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 21-38
T01-0703 Cell Performance
Objective
Verify that the cell performance test can be carried out through the Site Maintenance Terminal System.
Prerequisites
The Site Maintenance Terminal System and the BTS communicate normally.
You have obtained the site management right through the Site Maintenance Terminal System.
Procedure Expected result Result
3. Click a cell and then double-click Cell Performance Test in
the right pane of the Site Maintenance Terminal System
window.
4. Click Start.
(1) The Cell Test dialog box is
displayed.
(2) The test results of the GRFU/DRFU are displayed.
If the board is normal, the result shows that the test succeeded.
If the board is abnormal, the result shows that the test failed.
Pass Fail Not Run Zapped
Remarks
None.
T01-08 BT Management
T01-0801 BT Management State Change
Objective
Verify that the BT management state can be changed trough the Site Maintenance Terminal System.
Prerequisites
The Site Maintenance Terminal System and the BTS communicate normally.
You have obtained the site management right through the Site Maintenance Terminal System.
The BT management state is UNLOCKED before the BT is locked. The BT management state is LOCKED before the BT is unlocked.
Procedure Expected result Result
1. Lock the BT
(1) Click Cell > BT and
then double-click Change BT Management State in the Site Maintenance Terminal System
window.
(2) Check Current BT and LOCKED, and then click OK.
(3) Obtain the BT attributes and the attributes of the objects under this BT. Check the
(1) The Change BT Management State dialog box is displayed.
(2) The system prompts that the BT management state is changed successfully.
(3) The management state of each object is LOCKED.
(4) The color of each GRFU/DRFU is dark green. The board information shows “Manual block.”
Pass Fail Not Run Zapped
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 22-38
management state of the objects.
(4) Observe the color of each GRFU/DRFU under this BT and check the board information.
2. Unlock the BT
(1) Click Cell > BT and
then double-click Change BT Management State in the Site Maintenance Terminal System
window.
(2) Check Current BT and UNLOCKED, and then click OK.
(3) Obtain the BT attributes and the attributes of the objects under this BT. Check the management state of the objects.
(4) Observe the color of each GRFU/DRFU under this BT and check the board information.
(1) The Change BT Management State dialog box is displayed.
(2) The system prompts that the BT management state is changed successfully.
(3) The management state of each object is UNLOCKED.
(4) The color of each GRFU/DRFU is dark green. The board information shows “Normal.”
Pass Fail Not Run Zapped
Remarks
When the BT management state is changed to LOCKED, the calls of the subscribers in this BT are
interrupted.
Before the BT management state is change to UNLOCKED, the MS in this BT cannot access the network.
T01-0802 BT Re-Initialization
Objective
Verify that the BT can be reinitialized through the Site Maintenance Terminal System.
Prerequisites
The Site Maintenance Terminal System and the BTS communicate normally.
You have obtained the site management right through the Site Maintenance Terminal System.
Procedure Expected result Result
1. Click Cell > BT and then double-click BT Reinitialization.
2. Click OK.
(1) The BT Reinitialization dialog
box is displayed.
(2) The prompt saying "BT reinitialize successfully" is displayed.
Pass Fail Not Run Zapped
Remarks
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 23-38
After the BT is reinitialized, the GRFU/DRFU is out of service for a short time.
T01-0803 Viewing Channel State
Objective
Verify that the channel attribute management function is normal.
Prerequisites
The Site Maintenance Terminal System and the BTS communicate normally.
Procedure Expected result Result
3. Click BT. Double-click View Channel State.
4. Make a call on the GRFU/DRFU. Check the channel state.
(1) The View Channel State
dialog box displayed, showing the channel type and status.
(2) Value I means the channel is idle; Value A means the
channel is occupied.
Pass Fail Not Run Zapped
Remarks
To avoid blocking cells, choose single-GRFU/DRFU cells
T01-09 RC Maintenance
T01-0901 RC Attribute Management
Objective
Verify that the RC attribute management through the Site Maintenance Terminal System is functional.
Prerequisites
The Site Maintenance Terminal System and the BTS communicate normally.
You have obtained the site management right through the Site Maintenance Terminal System.
Procedure Expected result Result
5. Click an RC. Double-click RC Attributes Management.
6. Check that the RC attributes shown in the RC Attributes Management dialog
box is consistent with the BSC data.
7. Change the parameter value. Click Set. Then click OK.
8. Close the RC Attributes Management dialog
box. Then open it again to check the
(1) The RC Attributes Management dialog box is
displayed.
(2) The RC attributes on local end and remote end are consistent.
(3) A prompt "Setting RC attributes successful" is displayed on the status bar.
(4) The parameter value is the set value.
Pass Fail Not Run Zapped
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 24-38
parameters.
Remarks
The change of parameters in RC Attributes Management is only valid in the GTMU. To change the parameters in the GRFU/DRFU, perform RC Opstart.
This test may change the initial RC attributes and interrupt the operations on the BTS; therefore, Huawei recommends that you initialize the BTS after the test.
T01-0902 Changing RC Management State
Objective
Verify that the system can change RC management state through the Site Maintenance Terminal System.
Prerequisites
The Site Maintenance Terminal System and the BTS communicate normally.
You have obtained the site management right through the Site Maintenance Terminal System.
Before locking the RC, ensure that the RC is in UNLOCKED state. Before unlocking the RC, ensure that the RC is in LOCKED state.
Procedure Expected result Result
1. Lock the RC
(1) Click RC. Double-click Change RC Management State.
(2) Select Current RC. Then select LOCKED. Click OK.
(3) Obtain the attributes of RC and each channel on this RC through the Site Maintenance Terminal System. Check the management state.
(4) Check the color of GRFU/DRFU s and the board information.
(1) The Change RC Management State window appears.
(2) Operational result indicates
that changing the RC management state succeeded.
(3) The management state of each object is LOCKED.
(4) The color of each GRFU/DRFU is dark green. The boards are locked.
Pass Fail Not Run Zapped
2. Unlock the RC
(1) Click RC. Double-click Change RC Management State.
(2) Select Current RC.
Then select UNLOCKED. Click OK.
(3) Obtain the attributes of RC and each channel on this RC through the Site Maintenance Terminal System. Check the management state.
(1) The Change RC Management State dialog box is displayed.
(2) Operational result indicates
that changing the RC management state succeeded.
(3) The management state of each object is UNLOCKED.
(4) The color of each GRFU/DRFU is light green. The board information is Normal.
Pass Fail Not Run Zapped
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 25-38
(4) Check the color of GRFU/DRFU s and the board information.
Remarks
When the RC management state is changed to LOCKED, the calls on this BT will be affected.
Before the RC management state is changed to UNLOCKED, the connections and conversations on this BT are disabled.
T01-0903 RC Re-initialization
Objective
Verify that the RC re-initialization through the Site Maintenance Terminal System is normal.
Prerequisites
The Site Maintenance Terminal System and the BTS communicate normally.
You have obtained the site management right through the Site Maintenance Terminal System.
Procedure Expected result Result
1. Click BT. Double-click RC Reinitialization.
2. Click OK.
(1) The RC Reinitialization dialog
box is displayed.
(2) A prompt "RC reinitialize successfully" is displayed in the Operational result list box.
Pass Fail Not Run Zapped
Remarks
After the RC re-initialization, the GRFU/DRFU is out of service for a short time.
T01-10 Channel Management
T01-1001 Channel Attribute Management
Objective
Verify that the channel attributes management through the Site Maintenance Terminal System is normal.
Prerequisites
The Site Maintenance Terminal System and the BTS communicate normally.
You have obtained the site management right through the Site Maintenance Terminal System.
Procedure Expected result Result
3. Click a channel. Double-click Channel Attributes Management.
4. Check whether the parameters are consistent with BSC data.
5. Change the parameter value and channel
(1) The Channel Attributes Management dialog box is
displayed.
(2) The channel attributes at remote end and local end are consistent.
(3) A prompt "Set channel attributes successfully." is displayed on the status bar.
(4) The parameter value is the set
Pass Fail Not Run Zapped
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 26-38
type. Click Set. Then click OK.
6. Close the Channel Attributes Management dialog
box. Then open it again to check the parameters.
value.
Remarks
The change of parameters in Channel Attribute Management is only valid in the GTMU. To change the parameters of the GRFU/DRFU, perform Channel opstart.
This test may change the initial RC attributes and interrupt the normal running of BTS. Therefore, the initialization of BTS after the test is recommended.
T01-11 Board Management
T01-1101 Board Operation
Objective
Verify that the operation of each board through the Site Maintenance Terminal System is functional.
Prerequisites
The BTS operates normally.
The Site Maintenance Terminal System and the BTS communicate normally.
You have obtained the site management right through the Site Maintenance Terminal System.
The test board is configured and functional.
Procedure Expected result Result
1. Board resetting, self-test, and opstart
(1) Click Board. Double-click Board Management.
(2) Right-click the board, Choose Reset, Self-test, or Opstart
(1) The Board Management
dialog box is displayed.
(2) The success information is displayed.
Pass Fail Not Run Zapped
Remarks
Board operation includes board reset, board self-test, and board opstart.
GTMU and GRFU/DRFU support resetting and self-test.
GRFU/DRFU support the opstart
T01-1102 Board Alarm
Objective
Check the functions used to query board alarms through the Site Maintenance Terminal System.
Prerequisites
The BTS operates normally.
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 27-38
The Site Maintenance Terminal System and the BTS communicate normally.
The operated board is configured and running normally.
The sensors operate normally and connect correctly.
Procedure Expected result Result
2. Make the board generate an equipment alarm.
3. Click Board and then double-click Board Management in the Site Maintenance Terminal System
window.
4. Right-click a board and choose Board Alarm on the shortcut
menu
(1) The alarm is generated.
(2) The Board Management
dialog box is displayed.
(3) The Board Alarm Information
dialog box is displayed, showing the alarm information about the current board.
Pass Fail Not Run Zapped
Remarks
None
T02 Service Items
T02-01 Basic Services
T02-0101 Switching On an MS
Objective
Verify that an MS can be switched on and registered normally.
Prerequisites
The BTS operates normally.
An MS is available for a test.
The SIM card in the MS is valid.
The Abis interface messages of indicated cells on the BSC Maintenance System can be traced.
Procedure Expected result Result
5. Switch on the MS. The MS is registered in the network. Pass Fail Not Run Zapped
6. View the Abis interface tracing messages of indicated cells on the BSC Maintenance System.
The "Location Updating Accept" message can be seen in the Abis interface messages. The location updating of the MS is successful.
Pass Fail Not Run Zapped
Remarks
None.
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 28-38
T02-0102 Calls
Objective
Verify that MS communicate normally.
Prerequisites
The BTS operates normally.
Two MS are available for a test.
The SIM card is inserted into the testing MS.
Procedure Expected result Result
Use one MS to call the other. The MS communicate successfully, and the speech quality is good.
Pass Fail Not Run Zapped
Remarks
None.
T02-0103 Synchronous Handover
Objective:
Verify that the system can perform synchronous handovers.
Result:
Pass Fail Not Run Zapped
Comment & Remark:
Synchronous handovers refer to the handovers between cells in one site.
Prerequisites
The BTS has multiple neighboring cells.
The BTS operates normally.
An MS is available for a test.
The SIM card in the test MS is valid, and the MS has logged in to the network.
Procedure Expected result Result
7. Use the MS to set up a call on a
certain frequency in the cell of the
site. Then hand over the call to a
neighboring cell of this site
The handover is successful and the
call is not interrupted. Pass Fail Not Run Zapped
8. Hand over the call back to the The handover is successful and the Pass Fail Not Run Zapped
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 29-38
previous cell and keep calling. call is not interrupted.
9. Repeat steps 1 to 2 with other cells. The same as steps 1 and 2. Pass Fail Not Run Zapped
T02-0104 BCCH TRU Mutual Aiding
Objective
Verify that the BTS can provide the BCCH TRU mutual aiding function.
Prerequisites
The BCCH mutual aiding function is enabled.
At least one cell is configured with more than one GRFU..
The BTS operates normally and the GRFU. Carrying the BCCH also operates normally
The SIM cards inserted in the testing MS are valid and the MS have accessed the network.
Procedure Expected result Result
10. Block the BT that the primary BCCH on the Site Maintenance System.
11. Start the local or remote site maintenance system 15 minutes later. Select BT and double-click View Channel State. Check
whether the GRFU, carrying the BCCH switches to another GRFU of the cell.
12. Use the MS to initiate a call after the state of the new primary BCCH changes to I.
(1) The state of all the channels under the BT carrying the primary BCCH is 0.
(2) The primary BCCH is switched to another BT through a TRU mutual aid.
(3) The call is successful and the speech quality is good.
Pass Fail Not Run Zapped
Remarks
Enable the TRU mutual aid function during the system initialization.
Perform the BCCH TRU mutual aid function 15 minutes after the system initialization.
T02-0105 Frequency Hopping Function
Objective:
Verify that the frequency hopping function of the BTS is normal.
Result:
Pass Fail Not Run Zapped
Comment & Remark:
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 30-38
Prerequisites
The specified cell of the BTS is configured with the RF frequency hopping function.
The BTS operates normally.
An MS is available for test.
The SIM card in the MS is valid.
Procedure Expected result Result
13. Block the TCHs on the DRFU carrying the
non-primary BCCH.
Unblocking success is displayed
on the Site Maintenance
Terminal System.
Pass Fail Not Run Zapped
14. Use the testing MS to initiate a call on the
DRFU carrying the BCCH and maintain
the call. Observe the frequency hopping
mode through the MS.
In RF hopping mode, the DRFU
carrying the primary BCCH uses
non-hopping mode. The speech
quality is good.
Pass Fail Not Run Zapped
15. Unblock the TCHs on the DRFU carrying
the non-primary BCCH. Block the TCHs
on the DRFU carrying the primary BCCH.
Blocking success is displayed on
the Site Maintenance Terminal
System.
Pass Fail Not Run Zapped
16. Use the MS to initiate a call on the DRFU
carrying the non-primary BCCH and
maintain the call. Observe the frequency
hopping mode through the MS.
The DRFU carrying the
non-primary BCCH uses hopping
mode. The speech quality is
good.
Pass Fail Not Run Zapped
T03 RF Specifications Test Items
T03-01 RF Specifications
T03-0101 VSWR of the Antenna System
Objective:
Verify that the voltage standing wave ratio (VSWR) of the antenna system complies with the requirements.
Result:
Pass Fail Not Run Zapped
Comment & Remark:
The VSWR of each feeder must be no more than 1.3 but for the sites which with shorter feeder (less than 20
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 31-38
M) or the site with combiner, the VSWR should no more than 1.4.
It is recommended that the Sitemaster (ANRITSU or Bird) is the instrument for VSWR test.
Prerequisites
The BTS operates normally.
Procedure A Expected result
1. Take the jumper off and test the VSWR with
SiteMaster.
Antenna VSWR Test result:
Cell Feeder VSWR Result
Cell1
Cell1A Pass Fail Not Run Zapped
Cell1B Pass Fail Not Run Zapped
Cell1C Pass Fail Not Run Zapped
Cell1D Pass Fail Not Run Zapped
Cell1E Pass Fail Not Run Zapped
Cell1F Pass Fail Not Run Zapped
Cell2
Cell2A Pass Fail Not Run Zapped
Cell2B Pass Fail Not Run Zapped
Cell2C Pass Fail Not Run Zapped
Cell2D Pass Fail Not Run Zapped
Cell2E Pass Fail Not Run Zapped
Cell2F Pass Fail Not Run Zapped
Cell3
Cell3A Pass Fail Not Run Zapped
Cell3B Pass Fail Not Run Zapped
Cell3C Pass Fail Not Run Zapped
Cell3D Pass Fail Not Run Zapped
Cell3E Pass Fail Not Run Zapped
Cell3F Pass Fail Not Run Zapped
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 32-38
T03-0102 DRFU Transmit Power
Objective:
Verify that the actual transmit power of the DRFUs meets the requirements.
Result:
Pass Fail Not Run Zapped
Prerequisites
The BTS operates normally, and the calls of the DRFUs are normal.
.
Procedure A Expected result
1. Measure the transmit power by Power meter.
The criteria for the RF transmit power :
As per ETSI EN 300 910 V7.4.0 (European Stadard Telecommunication Series) “The tolerance of the
actual maximum output power of the BTS shall be ±2 dB under normal conditions and ±2,5 dB under
extreme conditions”.
DRFU
BAND Carrier
TYPE
Coupling
System
ToC Output
Power(W)
ToC Output
Power(dBm)
Power Output
Range(Normal)
Power Output
Range(Extreme)
± 2.0 dB ± 2.5 dB
900M DRFU No
combining 45W 46.53 44.53 ~ 48.53 44.03 ~ 49.03
900M DRFU Combining 20W 43.01 41.01 ~ 45.01 40.51 ~ 45.51
1800M DRFU No
combining 40W 46.02 44.02 ~ 48.02 43.52 ~ 48.52
1800M DRFU Combining 18W 42.55 40.55 ~ 44.55 40.05 ~ 45.05
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 33-38
TRX No. Measured value Result
0 ( )dBm Pass Fail Not Run Zapped
1 ( )dBm Pass Fail Not Run Zapped
2 ( )dBm Pass Fail Not Run Zapped
3 ( )dBm Pass Fail Not Run Zapped
4 ( )dBm Pass Fail Not Run Zapped
5 ( )dBm Pass Fail Not Run Zapped
6 ( )dBm Pass Fail Not Run Zapped
7 ( )dBm Pass Fail Not Run Zapped
8 ( )dBm Pass Fail Not Run Zapped
9 ( )dBm Pass Fail Not Run Zapped
10 ( )dBm Pass Fail Not Run Zapped
11 ( )dBm Pass Fail Not Run Zapped
24 ( )dBm Pass Fail Not Run Zapped
25 ( )dBm Pass Fail Not Run Zapped
26 ( )dBm Pass Fail Not Run Zapped
27 ( )dBm Pass Fail Not Run Zapped
28 ( )dBm Pass Fail Not Run Zapped
29 ( )dBm Pass Fail Not Run Zapped
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 34-38
Huawei Representative
Name:_____________________
Signature:__________________
Date:______________________
PTML Representative
Name:_____________________
Signature:__________________
Date:______________________
T03-02 External alarm
Objective:
Verify that all external alarms can be reported to OMC normally.
Result:
Pass Fail Not Run Zapped
Comment & Remark:
There are 16 external environment alarms on site. All of alarms are Boolean values. If the alarm appears, the
alarm can be displayed normally on OMC. When the alarm recovers, the corresponding alarm will disappear on
OMC.
Procedure Expected result Result
Check the Intruder alarm Intruder sensor properly installed &
terminated till BTS. Open & close BTS
Room Door to generate & clear the
intruder alarm respectively & verify from
OMCR
Pass Fail Not Run Zapped
Check the Fire Panel
alarm
Fire Panel properly installed & terminated
till BTS.
As a precaution, the “Gas Activation
Switch” is switched off and after the activity
changed back to “ON”. Open the main
equipment room’s “AC Distribution Box”
and turn the MCB for the “Fire Panel
Alarm” to the "OFF" position. After few
seconds an audible alarm should be heard
Pass Fail Not Run Zapped
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 35-38
from the “Fire Alarm Panel”.
Check with OMC-R that they can see this
alarm. In the “AC Distribution Box” switch
ON the “Fire Alarm Panel – MCB”. Check
with the OMC-R that the alarm has gone.
Check the Smoke
Detector alarm
Smoke sensors are properly installed &
terminated till BTS.
As a precaution, the “Gas Activation
Switch” is switched off and after the activity
changed back to “ON”.
Open the “Fire Alarm Control Panel” front
cover. Pull down the fire alarm "Pull Down
Switch" located on the “Equipment Room
Wall”, the “Fire Alarm Bell” should start to
ring. Silence the bell with the "Silence Bell"
soft key located on the “Fire Alarm Control
Panel”.
Check with the OMC-R that they can see
this alarm. Reset the “Fire Alarm Control
Panel” by pressing the "Reset Alarm" soft
key on the “Fire Alarm Control Panel”.
Check with the OMC-R that the alarm has
gone.
Close the “Fire Alarm Control Panel” front
cover.
Pass Fail Not Run Zapped
Check the Over temp
alarm
Over temp sensor properly installed &
terminated till BTS.
On A/C Panel, Set the over temperature
threshold below 28 °C. Over Temperature
alarm will be reported at the OMCR. Verify
from OMCR & set over temperature
threshold back to 28 °C.
Pass Fail Not Run Zapped
Check the Humidity
alarm
Humidity sensor properly installed &
terminated till BTS.
Locate the “Humidity Sensor”, which is
installed on one of the “Equipment Room
Walls”.
Pass Fail Not Run Zapped
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 36-38
Set the humidity upper limit at 20% with
OMCR. After few seconds, Check with
OMC-R that they can see this alarm. Set
the humidity upper limit back to 85%,
Check with the OMC-R that the alarm has
gone.
Check the Water
leakage alarm
Water leakage sensor properly installed &
terminated till BTS.
Locate the “Water Leakage Sensor”,
located on one of the “Equipment Room
Walls” at floor level. Immerse the Water
Leakage Sensor into water. After few
seconds, Check with OMC-R that they can
see this alarm. Take out the Water
Leakage Sensor from the water, Check
with the OMC-R that the alarm has gone.
Pass Fail Not Run Zapped
Check the Gas release
alarm
FSS properly installed & terminated till
BTS.
As a precaution, the “Gas Activation
Switch” is switched off and after the activity
changed back to “ON”.
The Test will be done by using “LOOP Test
Method”.
Remove the [Jumper] cables of “Gas
Released” on EMU, the alarm of “Gas
Released” will be reported to OMCR.
Reconnect the [Jumper] cables; the alarm
should be cleared in OMCR
Pass Fail Not Run Zapped
Check the Generator
Running alarm
Open the “Main Switch DB” in Genset
Room. Disconnect the WAPDA supply
from the Main Switch. Genset will be
started. Generator Running alarm will be
reported at the OMCR. Verify from OMCR
& Switch ON the MCB.
Pass Fail Not Run Zapped
Check the Tower light
alarm
Tower light sensor properly installed &
terminated till BTS.
Cover the sun switch with a cloth. Tower
Pass Fail Not Run Zapped
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 37-38
lights will turn on. Now remove one bulb
from the holder & Tower light failure alarm
will be reported at OMCR. Clear the alarm
once bulb is installed back & verify from
OMCR.
Check Air Conditioner
Failure Alarm
Air Con Panel properly installed &
terminated till BTS. Alarm to be actuated
when both Air Conditioners are operating
Pass Fail Not Run Zapped
Check Mains
Failure Alarm
Alarm to be actuated when Input
Commercial Supply for Rectifier has
suspended / failed
Pass Fail Not Run Zapped
Check Low Battery
Voltage alarm
Alarm to be actuated when Battery Bank
discharge voltage <= 49 volts Pass Fail Not Run Zapped
Check the
Rectifier Major
alarm
No: of Rectifier modules having faults=>1,
Pass Fail Not Run Zapped
Check the Rectifier
Minor Alarm
Condition: Alarm to be actuated when
lightning surge has affected the system Pass Fail Not Run Zapped
Check the Generator
Failure alarm
Open the “Main Switch DB” in Genset
Room. Disconnect the WAPDA supply
from the Main Switch. Genset will be
started. Wait for consistent response of the
Genset, for some time.
Locate the “OutPut Switch” on the Front
Panel of Genset. Change the Output
Switch to “OFF” position. The Output
supply of the Genset will be disconnected.
The alarm of “Generator Failure” (Alarm –
15) will be reported in OMCR. Change the
position of “Output Switch” to “ON”
position. The supply of Genset will be
again commenced. Reconnect the
WAPDA supply by changing position of
Main Switch to “ON” position.
Pass Fail Not Run Zapped
Check the Gen Low Fuel
alarm
Take the fuel float with the cover out of the
tank. Check with OMC-R that they can see Pass Fail Not Run Zapped
ATP Items HUAWEI BTS3900 Ufone/Technical/ANO/DOC/01/01 38-38
this alarm. At the fuel float with cover
inserted to the tank. Check with the
OMC-R that the alarm has gone.
Huawei Representative
Name:_____________________
Signature:__________________
Date:______________________
PTML Representative
Name:_____________________
Signature:__________________
Date:______________________