Caythorpe Gas Storage ProjectLiaison Committee Meeting28th September 2009

Caythorpe Liaison Committee 28th September 20092

Agenda

• Project Status Report – September 2009

• Archaeological site investigation

• Bridge design

• Seismic survey

• Traffic management plan

• Ongoing community liaison

• Environmental support fund

• Activities on site within coming weeks / months

• Questions

Caythorpe Liaison Committee 28th September 20093

Health, Safety & Environment

• No on or off site complaints (to date)

• No on or off environmental impacts (to date)

• No accidents, incidents or near misses to report (to date)

• Project working under the “Construction Design & Management

Regulations” regulated by the Health & Safety Executive

• Site visit by HSE Construction Division 27th August. No issues of

concern raised

• Baseline noise survey completed August 2009 and issued to ERYC

• Noise, Vibration, Dust Management and Monitoring Scheme submitted

to ERYC (in accordance with planning conditions)

Caythorpe Liaison Committee 28th September 20094

Current Status

• Demolition of existing equipment completed in June

• Archaeological site investigation ongoing

• Geotechnical site investigations

Caythorpe Liaison Committee 28th September 20095

Archaeological Site Investigation

• Located on the margins of a settlement occupied in the late Iron Age,

Roman and early Anglo-Saxon periods (about 200BC to AD700)

Caythorpe Liaison Committee 28th September 20096

Archaeological Site Investigation

Caythorpe Liaison Committee 28th September 20097

Archaeological Site Investigation

Caythorpe Liaison Committee 28th September 20098

Invitation to an Archaeological Site Visit

• Liaison Committee Saturday 10th October

• Boynton School w/c 12th October

Caythorpe Liaison Committee 28th September 20099

Bridge Crossing of Gypsey Race

• Would like to install October/November 2009 but may delay until Spring

2010

• Design approved by the Environment Agency

• Ecological surveys on river ongoing

Caythorpe Liaison Committee 28th September 200910

Bridge Crossing of Gypsey Race – Existing View

Caythorpe Liaison Committee 28th September 200911

Bridge Crossing of Gypsey Race – Proposed View

Caythorpe Liaison Committee 28th September 200912

Water Voles

• Water Vole is a protected species and

present on the Gypsey Race including

location of bridge crossing

• Ongoing daily surveys on the river

• Habitat management to encourage

voles to move along the river

• Fallback option is to move the voles

under licence from Natural England

• Ecological Mitigation & Monitoring

Strategy submitted to ERYC (in

accordance with planning condition)

Caythorpe Liaison Committee 28th September 200913

Seismic Survey

• Seismic survey underway, due to

complete mid November

• 7 day/week operation.

• Mitigation measures in place to avoid

damage to land and protect

archaeology and ecology

• Vibration monitoring at residential

properties

Caythorpe Liaison Committee 28th September 200914

Seismic Survey – Notification to Residents

Caythorpe Liaison Committee 28th September 200915

Seismic Survey – Notification to Residents

Caythorpe Liaison Committee 28th September 200916

Construction Traffic Management Plan

Caythorpe Liaison Committee 28th September 200917

Construction Traffic Management Plan

Caythorpe Liaison Committee 28th September 200918

Environmental Support Fund

The Fund will be structured into two elements:

• An initial one-off sum of £150,000 which is available up until the completion of construction of the project (2012); and

• An ongoing annual budget of £5,000 as per the Warwick Energy agreement with ERYC (over the 24 year lifespan of the planning permission this equates to £120,000)

• The allocation of monies will be subject to applications to the Liaison Committee in accordance with published guidelines

Caythorpe Liaison Committee 28th September 200919

Future Activity October-December 2009

• Completion of seismic survey by mid November

• Completion of archaeological site works for this season (with remainder of work to be done in spring)

• Moving of water voles if habitat management unsuccessful

• Construction of bridge and access road (although may be delayed until spring)

Caythorpe Liaison Committee 28th September 200920

Point of contact for seismic survey

IMC Geophysics International Ltd

c/o Garland Total Vehicle SolutionsLancaster RoadCarnaby Industrial EstateCarnabyBridlingtonYO15 3QY

Tel: 07810 855318

Caythorpe Liaison Committee 28th September 200921

Points of contact for project

Paul Dacombe

Consents & Licencing Manager

Caythorpe Gas Storage Project

Centrica plc

Millstream West

Maidenhead Road

Windsor

Berkshire

SL4 5GD

Mobile 07789 570416

paul.dacombe@centrica.com

Justin Kenyon

Site HSE Manager

Caythorpe Gas Storage Limited

Caythorpe Well Site

Rudston

Driffield

YO25 4JD

Site Office 01262 420177

Mobile 07904200995

justin.kenyon@centrica.com

• Project Website

Caythorpe Liaison Committee 28th September 200922

Questions?