Cincinnati Dayton Rd

Widening

Project Overview

• Widening of Cincinnati Dayton Rd to four lanes - providing a center turn lane and an additional northbound lane

• Realignment of Station Rd

• Widening of bridge on Cincinnati Dayton Rd; Replacement of bridge on Station Rd

• New sidewalk and decorative lighting along corridor

• New closed storm system

• New mid-block crosswalks

• Includes rectangular rapid flashing beacons

• Rectangular rapid

flashing beacon: • Corridor lighting:

Mid-block crosswalks

Cincinnati Dayton Rd Bridge

Mid-block crosswalks

Cincinnati Dayton Rd

Boys & Girls Club

Cincinnati Dayton Rd

Interstate 75 >>> Post Office

Standing at the Intersection of Station Rd and

Cincinnati Dayton Rd – Looking north

Existing Proposed

Standing south of the Cincinnati Dayton Rd bridge

– Looking south

Existing Proposed

Tentative Project Schedule

• Right-of-Way Acquisition Complete – End of 2017

• Utility Relocations – Ongoing

• Contract Sell Date – Spring, 2018

• Construction Start Date – Spring, 2018

• Construction Completion Date – Summer, 2019

General Construction Notes

• Operating hours: • 7:00AM – 9:00PM Monday through Saturday

• 1:00PM – 9:00PM Sunday

• Lane restrictions allowed Monday-Friday during non-peak

hours • Peak hours: (7:00AM – 8:30AM & 4:30PM – 6:30PM)

• Lane restrictions will be allowed on weekends

• Pile driving for the Cincinnati Dayton Rd bridge will be

restricted to the weekday hours of 8:00AM – 4:00PM

Construction Sequence

• 2018:

• Phase 1

• Phase 2

• Phase 3

• 2019:

• Phase 4

• Phase 5

• Phase 6

Phase 1 Construction - 2018

• Phase 1 construction begins in Spring, 2018

• Construct temporary pavement on west side of Cincinnati Dayton Rd between Seminary St and I-75

• Permanently widen east side of Cincinnati Dayton Rd bridge

• Permanently widen east side of Cincinnati Dayton Rd between the Cin Day bridge and I-75 up to the intermediate pavement

Phase 1 Construction - 2018

Phase 1 Construction - 2018

West Chester

Presbyterian Church

Phase 1 Construction - 2018

Lesourd

svill

e

West C

heste

r R

d

Phase 1 Construction - 2018 Seminary St

You are Here

Phase 1 Construction - 2018 Boys & Girls Club

Cresthaven Ave

• Phase 2 construction will close Station Rd from May 14th, 2018 through July 23rd, 2018 (10 weeks).

• Realign Station Rd with the intersection of Cincinnati Dayton Rd and Lesourdsville West Chester Rd.

• Complete construction up to the intermediate pavement and open Station Rd on July 23rd, 2018.

• This schedule was implemented to avoid detours during the St. John’s festival (August 3-5, 2018).

Phase 2 Construction – 2018 (Realignment of Station Rd)

Station Road Official Detour

Station Rd Closed

Official Detour (Trucks)

• Phase 3 construction begins after the completion of Phase 1 (Phase 2 is independent of other phases)

• Shift traffic to completed east side of Cincinnati Dayton Rd

• Permanently widen west side of Cincinnati Dayton Rd between the Cin Day bridge and I-75 up to the intermediate pavement

• All roadway widening north of the Cincinnati Dayton Rd bridge will be complete up to the intermediate pavement by Winter, 2018

Phase 3 Construction - 2018

Phase 3 Construction - 2018

West Chester

Presbyterian Church

Phase 3 Construction - 2018

Lesourd

svill

e

West

Cheste

r R

d

Phase 3 Construction - 2018 Seminary St

You are Here

Phase 3 Construction - 2018 Boys & Girls Club Cresthaven Ave

• Phase 4 construction begins in Spring, 2019

• Permanently widen the west side of the bridge on Cincinnati Dayton Rd

• Permanently widen the west side of Cincinnati Dayton Rd up to the intermediate pavement between West Chester Rd and the Cin Day bridge

Phase 4 Construction – 2019 (South of Cin Day Bridge)

Phase 4 Construction - 2019

Locust S

t

Phase 4 Construction - 2019

St. John Entrance

• Phase 5 construction will begin after the completion of phase 4

• Permanently widen the east side of Cincinnati Dayton Rd up to the intermediate pavement between West Chester Rd and the Cincinnati Dayton Rd bridge

• This is the final phase of widening construction. Will be completed by Summer, 2019.

Phase 5 Construction – 2019 (South of Cin Day Bridge)

Phase 5 Construction - 2019

Locust S

t

Phase 5 Construction - 2019

St. John Entrance

• Phase 6 construction will begin once all widening

phases are complete

• Pave the final asphalt surface course through the

entire project

• Apply all final pavement markings

• Final completion date: Summer, 2019

Phase 6 (Final) Construction - 2019

West C

heste

r R

d

Cincinnati Dayton Rd

Boys & Girls Club

Cincinnati Dayton Rd

Post Office

Questions?