Post on 08-Jan-2016
description
transcript
CITY OF RAINIER
RAILROAD CROSSINGS
Project # 2 Group
• Matthew DeGeorge
• Josh Crain
• Robert Acevedo
• Chris Penka
• Jim Harvey
• Heather Wenstrand
Group photo or something in this empty area?
Presentation Outline
• Introduction
• Existing Conditions
• Future Conditions
• Intersection Alternative Designs
• Conclusion
Scope
1. To design safe railroad crossings that maximizes the movement of people and goods.
2. Design safe pedestrian crossing across the railroad tracks.
3. To design effective intersection closures that minimizes the impact on traffic and the community.
Background• The City of Rainier is on the south bank of the
Columbia River across from Longview, Washington.
• This project is part of the Rainier Waterfront Urban Renewal Plan.
• The closing of the Trojan nuclear power plant set off a decline in the number of businesses in the city.
• The current population is around 2,000 people.
• Something about the destination, cargo & size of the trains.
Project Overview• Project consists of:
– Design closing for 3 crossings– Redesign 4 crossings
• The City of Rainier has no dedicated engineering staff.– Lars Gare, City Administrator
• ODOT Rail has final design approval– Dave Lanning, Crossing Safety/Compliance
Existing ConditionsRainier, Oregon
Trains Getting More Frequent and Getting LongerA Street all AccessFoss Trucks Backing in on 6th StDowntown Shops 10 Delivery/Week
A Street “” Street
“” Street
“” Street
Traffic Counts
Most Frequently Traveled Intersection Near Post OfficeObvious
No additional studies needed
Future Conditions
• Railroad’s Plans-– The “A” Street Streetscape and Railroad
Safety Project is a commercial street reconstruction project aimed at improving rail functionality and providing safety to the surrounding community.
• Street Improvements include;– Separation of heavy rail from other street
network users. Rail curbs, crossing closures and restricted access to A Street.
• ODOT’s 3/3/1 Offer to City– ODOT Rail has made an agreement with The City of
Rainier Stating that if 3 rail crossing are closed ODOT will pay for 3 to be upgraded. This leaves the fourth additional rail crossing to be upgraded under the responsibility of the City of Rainier to finance.
– Under this agreement The City of Rainier is required to provide all the engineering for the project and ODOT Rail will have final decision making authority on the plans and will be financially responsible for 3 of the crossing upgrades.
• Future Closures– City decided due to usage and location that it would be beneficial to
close the following
• 2nd Street East
• 4th Street East
• 5th Street East
• Future Gated/Controlled– City decided that it would be necessary to allow the following
intersection to remain open however to provide control measures for safety purposes.
• 2nd Street West
• 1st Street
• 3rd Street East
• 6th Street East
Intersection Design Alternatives
Generic Closure – Option 1
• “Right in, right out”• Access from cross streets maintained• Minimal signage
Generic Closure – Option 2
• Permanently close cross streets• Install barricade to dead end street
Closed Intersections – Cost EstimateOption 1 – Right In, Right Out Option 2 – Closed cross streets
3 Sign Installations $900 1 Sign Installation $300
64 Feet Permanent Barricade
$7,680 32 Feet Permanent Barricade $3,840
1 Pavement Arrow $1,620 Asphalt removal $?
Mobilization (10%) $906 Mobilization (10%) $?
Temporary Traffic Control (5%)
$453 Temporary Traffic Control (5%)
$?
Overhead & Profit (15%) $1,359 Overhead & Profit (15%) $?
Contingency (30%) $2,718 Contingency (30%) $?
Total Cost $14,496 Total Cost $?
Generic Crossing – Gated, Signed
• Install two grade crossing controls at bulb outs
3rd St E / 1st St Crossings – Cost EstimateOption 1 – Non-signalized Option 2 – Signalized
10 Sign Installations $3,000 8 Sign Installations $2,400
2 Railroad gates $240,000 2 Railroad gates, 2 RXR Pavement Markings
$241,800
2 RXR Pavement Markings $1,800 Signalize Intersection (4 mast arms)
$160,000
Mobilization (10%) $24,480 Mobilization (10%) $40,420
Temporary Traffic Control (5%)
$12,240 Temporary Traffic Control (5%)
$20,210
Overhead & Profit (15%) $36,720 Overhead & Profit (15%) $60,630
Contingency (30%) $73,440 Contingency (30%) $121,260
Total Cost $391,680 Total Cost $643,840
6th St E – Option 1 • Uncontrolled Crossing • Signing and Striping Only• 150-feet of Open Track
6th St E – Option 2 • Uncontrolled Crossing • Signing and Striping Only• 100-feet of Open Track
6th St E - Uncontrolled Crossing
Advantages Disadvantages
Inexpensive: Signing and striping only
Safety: Not as safe – no warning lights or gates
Trucks: Plenty of room for trucks entering FOSS to turn around and back in.
Trucks: Delivery trucks to FOSS still turn around on tracks
Access Management: All existing driveways at the east end of A Street maintain access
Increased traffic volume: Destinations from south 5th ST E to north 3rd St E must use this crossing
Less Parking: May require modification or removal of on-street parking
6th St E – Cost EstimateOption 1 – 150 feet open track Option 2 – 100 feet open track
9 Sign Installations $2,700 9 Sign Installations $2,700
660 Feet Striping $660 460 Feet Striping $460
3 Pavement Arrows,1 RXR Pavement Marking
$1,620 3 Pavement Arrows,1 RXR Pavement Marking
$1,620
Mobilization (10%) $498 Mobilization (10%) $478
Temporary Traffic Control (5%)
$249 Temporary Traffic Control (5%)
$239
Overhead & Profit (15%) $747 Overhead & Profit (15%) $717
Contingency (30%) $1,494 Contingency (30%) $1,434
Total Cost $7,968 Total Cost $7,648
The Next Phase
• Week 1 - Design 3 intersection closures
• Week 2 & 3 - Design the general railroad crossings. Intersections 1st and 3rd St E
• Week 4 & 5 - Design 2nd St W (Post Office)
• Week 6 & 7 - Design 6th St E (Foss)
• Week 8 - Overall review and finalize designs
• Week 9 & 10 – Presentation preperation