LARSEN & TOUBRO LIMITED
MANAMADURAI - TIRUCHULI - VIRUDHUNAGAR RC PROJECT
ACTION PLAN FOR COMPLETING BALANCE WORKS
As on : 17.04.13
Sl. No. Description of workWork
GroupName of the S/c
Target
Completion
Site
EngineerRemarks
APK Station
1 Septic Tank Work PF Mintu pal 25.04.13 Manikantan Work in progress
2 White washing of Toilet PF Ravi 20.04.13 Manikantan
3 Window fixing for Off duty room PF Dept 25.04.13 Manikantan
4 Tap fixing for toilet , inside toilet of station Building PF Mintu pal 20.04.13 Manikantan
5 Patch Tiles work for all rooms PF Dept 18.04.13 Manikantan
6 Duct slab finishing and pointing inside Station Building PF Mintu pal 30.04.13 ManikantanPVC or rubber sheet to be
ordered
7 Ticket counter window work at booking office PF Dept 25.04.13 Manikantan To be enquired
8 Door for public toilet PF Dept 20.04.13 Manikantan Awaiting approval
9 Roof tiles for public toilet PF Mintu pal Completed Manikantan
10 Broken glass refixing for windows PF Dept 25.04.13 Manikantan
11 Glass fixing for ventilator PF Dept 25.04.13 Manikantan
12 Hand rails for waiting hall ramp & toilet ramp PF Syed 30.04.13 Manikantan
13 Tap fixing for water cubicle PF Dept Manikantan Before CRS14 Tiles broken by local people to be replaced in water cubicle PF Mintu pal Manikantan Before CRS
15Balance slab for cable duct in PF. No.2 to be casted and all slabs to be
pointedPF Ghosh 20.04.13 Manikantan
16 Finishing of flooring in Equipment room PF Mintu pal 20.04.13 Manikantan
17 Finishing of steps in battery room PF Mintu pal 20.04.13 Manikantan
18 Painting of relay room and equipment room PF Ravi 20.04.13 Manikantan
19 Dressing of platform PF Dept 30.04.13 Manikantan
20 Soil filling for ramp at VPT end PF Dept 15.04.13 Manikantan
Page 1 of 21
7/30/2019 Comp Programme Civil 17.04.12 (R1)
2/21
Sl. No. Description of workWork
GroupName of the S/c
Target
Completion
Site
EngineerRemarks
NKK Station
1 Septic tank connection works PF Ghosh 30.04.13 Manikantan
2 Plumbing works inside public toilet(Fitting & fixing) PF Ghosh 18.04.13 Manikantan
3 Rain water down pipe from building top to be provided PF Ghosh 25.04.13 Manikantan
4 Chamber towards VPT end of building for collecting rain water PF Ghosh 25.04.13 Manikantan
5 Indian closet in off duty room toilet to be replaced PF Ghosh 20.04.13 Manikantan During CRS
6 New physically challenged toilet to be constructed PF ManikantanNew proposal given on
10.04.13
7 Broken glass for windows to be replaced PF Ghosh 20.04.13 Manikantan
8 Glass fixing for ventilator PF Ghosh 20.04.14 Manikantan
9 Door for ticket store room PF Ghosh 25.04.13 Manikantan
10 Finishing of slab broken for electrical works in booking office room PF Ghosh 30.04.13 Manikantan
11 Plastering for CC Blocks steps infront of new station bulding PF Ghosh 25.04.13 Manikantan
12 Flooring in rear side and VPT side of toilet PF 30.04.13 Manikantan
13 Pale fencing fixing surrounding toilet in ground floor PF Gopi Manikantan To be discussed with clients
14 Roof shelter provision between new and old station building PF Syed 20.04.13 Manikantan
15 Ticket counter window work at booking office PF Dept 30.04.13 Manikantan
16 Tap fixing for water cubicle PF Dept Manikantan During CRS
17 Paving for water cubicle PF Murugaya 30.04.13 Manikantan18 Pointing of precast slab in PF. No.2 cable duct PF M.Krisnan 25.04.13 Manikantan Item to be confirmed
19 Painting of relay room and equipment room PF Ravi 25.04.13 Manikantan
20 Finishing of flooring in rooms broken for S&T and electrical works PF Ghosh 20.04.13 Manikantan
21 Pointing & finishing of precast slab for cable duct inside station building PF Murugaya 25.04.13 Manikantan
Page 2 of 21
7/30/2019 Comp Programme Civil 17.04.12 (R1)
3/21
Sl. No. Description of workWork
GroupName of the S/c
Target
Completion
Site
EngineerRemarks
TIRUCHULI
Septic Tank Work Building Mintu pal 20.04.13 Damodharan Work in progress
White washing of Toilet Building Ravi 22.04.13 Damodharan
Facia board fixing PF syed 18.04.13 Damodharan
Tap fixing for toilet , inside toilet of station Building Building Mintu pal 20.04.13 Damodharan
Patch Tiles work for all rooms Building Mintu pal 20.04.13 Damodharan
Duct slab finishing and pointing inside Station Building Building Mintu pal Damodharan Before CRS
Ticket counter window work at booking office Building Dept 30.04.13 Damodharan
Door for public toilet Building RAJA 19.04.13 Damodharan
Roof tiles for public toilet Building Mintu pal 18.04.13 Damodharan
Broken glass refixing for windows Building Mintu pal 20.04.13 Damodharan
Glass fixing for ventilator Building Mintu pal 20.04.13 Damodharan
Hand rails for toilet ramp Building Syed 22.04.13 Damodharan
Tap fixing for water cubicle PF Mintu pal Damodharan Before CRS
Facia board fixing PF Syed 20.04.13 Damodharan
Balance slab for cable duct in PF. No.2 to be cast and all slabs to be pointed PF Mintupal 22.04.13 Damodharan WIP
Dressing of platform PF Mintupal 20.04.13 Damodharan WIP
Soil filling for ramp at VPT end PF Mintupal 20.04.13 Damodharan
Pale fencing casting PF Gopi 20.04.13 Damodharan Post - 250/250;Walling- 200/250
Pale fencing erection PF Gopi 30.04.13 Damodharan To commence by 15.04.13
Page 3 of 21
7/30/2019 Comp Programme Civil 17.04.12 (R1)
4/21
LARSEN & TOUBRO LIMITED
TIRUCHULI - VIRUDHUNAGAR RC PROJECT
ACTION PLAN FOR COMPLETING BALANCE WORKS
As on : 17.04.13
SI
No.Description Qty Start Date End Date
Name of the
S/c
Site
Engg.REMARKS
VIRUDHUNAGAR YARD
1Fixing of coping slab for
PF no.: 2,3 & 5Muthupandi Alwin
PF no: 5 after wall
clearance by client side
2
Construction of PF wall
in the portion of exg.
Trolly path
12.04.13 20.04.13 Muthupandi AlwinPF no: 5 after wall
clearence by client side
PCC 6.75 Muthupandi Alwin
CC wall 21.6 Muthupandi Alwin
Carballing 1.69 Muthupandi Alwin
Fixing 120 Muthupandi Alwin
3
Attending PF wall &
coping so as to be keep
distance of 1.67m to
1.68m from c/l of track
to face of coping and
.76m to .84m from top
of rail level to coping
Muthupandi Alwin
Balance 40m alignment
detail to be given by
clients
4
Tiling work for the
proposed toilet @ vpt
and drainage
connection
Muthupandi Alwin
Tiling work completed,
drainage connection not
in our scope
5Water cubical &
benches
5 Nos.
Each17.04.13 24.04.13 Mintupaul Alwin
Since width of platform is
less on Tvnli end , we can
construct only 2nos
immediately balance will
be done after completing
FOB foundation works
6Pale fencing left out in
the proposed PF no:535 Mtr 18.04.13 23.04.13 Gopi Alwin
7 Colour washing of palefencing
20.04.13 Gopi Alwin Work in progress
8Colour washing of toilet
building23.04.13 25.04.13 Ravi Alwin
9Toilet building, pvc
door fixing1 No 18.04.13 19.04.13 Raja Alwin
10 Roof tiles fixing 23.04.13 26.04.13 Mintupaul Alwin
11 Water tap fixing 12.04.13 14.04.13 Mintupaul Alwin Completed
Page 4 of 21
7/30/2019 Comp Programme Civil 17.04.12 (R1)
5/21
SI
No.Description Qty Start Date End Date
Name of the
S/c
Site
Engg.REMARKS
12Physically challenged
portion18.04.13 Mintupaul Alwin Work in progress
13Name board in the PF
no:52 Nos. 18.04.13 25.04.13 Kuppan Alwin
14Connection of leach pit
in lc gate2 Nos. 23.04.13 24.04.13 Murugaiya Alwin Perali, Villipathiry
15 LC gate toilet room 2 Nos. 23.04.13 26.04.13 Department AlwinNagampatti,
Thottiyankulam
Gate lodge building
1
Sanitary connection
and construction of
leach pit
4 Nos. 18.04.13 22.04.13 Murugaiya Alwin Leach Pit Completed
2Paving from gate lodge
to road4 Nos. 23.04.13 03.05.13 Murugaiya Alwin
3Colour washing of
fencing2 Nos. 18.04.13 19.04.13 Gopi Alwin
Irrunchirai , Narikudi
balance
4
Level crossing - filling
the surroundings with
Earth b/w pale fencing
and gate lodgee
2 Nos.
100cum
each
18.04.13 22.04.13 Dept AlwinKeelapasali,
Chinnakannanur.
5 New toilet room 1 No. 13.04.13 23.04.13 Murugaiya Alwin Irrunchirai
Page 5 of 21
7/30/2019 Comp Programme Civil 17.04.12 (R1)
6/21
LARSEN & TOUBRO LIMITED
MANAMADURAI - TIRUCHULI RC PROJECT
ACTION PLAN FOR COMPLETING BALANCE WORKS - VENT WAY CLEARANCE
Date : 17.04.13
Sl. No. Br. No. Location Span Barrel length Width Depth Total (Cum) Completion date
1 199 55613-14 1 x2x 3 RCB 8.000 2 0.30 4.80 Completed
2 200 556/14-15 1x1.2x1.2 RCB
3 201 556/16-17 1x1.2x1.2 RCB
4 202 557/2-3 1x1.2x1.2 RCB 7.650 1.2 0.40 3.67 Completed
5 203 557/5-6 1x1.2x1.2 RCB 7.650 1.2 0.50 4.59 Completed
6 204 557/6-7 1x6x2.3 RCB 6.850 6 0.37 15.07 Completed
7 205 557/9-10 1x1.2x1.2 RCB 7.650 1.2 0.23 2.14 Completed
8 206 557/10-11 1x1.2x1.2 RCB 7.650 1.2 0.33 3.06 Completed
9 207 559/3-4 1x6x3.1 RCB 6.850 6 0.40 16.44 Completed
10 208 559/6-7 1x6x2.4 RCB 6.850 6 0.50 20.55 Completed
11 209 559/8-9 1x4x2.5 RCB 6.850 4 0.57 15.53 Completed
12 210 559/9-10 1x1.2x1.2 RCB 7.650 1.2 0.30 2.75 Completed
13 211 559/11-12 1x1.2x1.2 RCB 7.650 1.2 0.40 3.67 Completed
14 212 559/14-15 1x1.2x1.2 RCB 7.650 1.2 0.57 5.20 Completed
15 212A 559/16-17 1x1.2x1.2 RCB 7.650 1.2 0.10 0.92 Completed
16 213 559/16-560/1 1x1.2x1.2 RCB 7.650 1.2 0.50 4.59 Completed
17 214 560/4-5 1x1.2x1.2 RCB 10.710 1.2 0.53 6.85 Completed
18 215 560/5-6 1x1.2x1.2 RCB 9.180 1.2 0.40 4.41 Completed
19 216 560/10-11 1x1.2x1.2 RCB 7.650 1.2 0.53 4.90 17.04.13
20 217 561/1-2 1x4.5x3 RCB 6.850 4.5 0.77 23.63 18.04.13
21 218 561/3-4 6x12.2 PSC 16.04.13
22 219 561/5-6
23 220 561/11-12 1x1.2x1.2 RCB 9.180 1.2 0.47 5.14 20.04.13
24 221 562/1-2 1x4x2.4 RCB 6.850 4 0.47 12.79 21.04.13
25 222 562/3-4 1x1.2x1.2 RCB 7.650 1.2 0.50 4.59 22.04.13
26 223 562/6-7 1x1.2x1.2 RCB 7.650 1.2 0.27 2.45 22.04.13
27 224 562/8-9 1x1.2x1.2 RCB 7.650 1.2 0.50 4.59 23.04.13
Constructed in MNM-RMM GC Project
Major Bridge
Closed Bridge
Page 6 of 21
7/30/2019 Comp Programme Civil 17.04.12 (R1)
7/21
Sl. No. Br. No. Location Span Barrel length Width Depth Total (Cum) Completion date
28 225 563/7-8 1x6x2.2 RCB 6.850 6 0.50 20.55 Completed
29 226 563/8-9 1x6x3 RCB 6.850 6 0.67 27.40 Completed
30 227 563/10-11 1x4x3 RCB 6.850 4 0.50 13.70 Completed
31 228 564/1-2 2x4x1.7 RCB 7.000 4 0.50 14.00 Completed
32 229 564/15-565/1 1x1.2x1.2 RCB 7.650 1.2 0.60 5.51 25.04.13
33 230 565/7-8 1x4x1.6 RCB 6.85 4 0.53 14.61 25.04.13
34 231 565/8-9 1x4.5x1.8 RCB 6.850 4.5 0.60 18.50 25.04.13
35 232 565/9-10 1x1.2x1.2 RCB 7.650 1.2 0.27 2.45 25.04.13
36 233 565/13-14 1x1.2x1.2 RCB 7.650 1.2 0.50 4.59 25.04.13
37 234 566/1-2 1x1.2x1.2 RCB 7.650 1.2 0.47 4.28 27.04.13
38 235 566/3-4 1x1.2x1.2 RCB 7.650 1.2 0.50 4.59 27.04.13
39 236 566/3-4 1x1.2x1.2 RCB 7.650 1.2 0.60 5.51 27.04.13
40 237 567/4-5 1x4.5x1.8 RCB 6.850 4.5 0.47 14.39 27.04.13
41 238 568/1-2 1 x4x 2 RCB 6.850 4 0.40 10.96 27.04.13
42 239 568/2-3 1x4x2.3 RCB 6.850 4 0.50 13.70 27.04.13
43 240 568/7-8 4x12.2 PSC Completed
44 241 568/8-9 1x4.5x2.6 6.850 4.57 0.27 8.35 30.04.13
45 242 569/3-4 1x1.2x1.2 RCB 9.180 1.2 0.50 5.51 30.04.13
46 243 569/5-6 1x1.2x1.2 RCB 10.710 1.2 0.20 2.57 30.04.13
47 244 569/6-7 1x1.2x1.2 RCB 10.710 1.2 0.27 3.43 30.04.13
48 245 569/7-8 1x2.5x2.6 RCB 6.850 2.5 0.33 5.71 30.04.13
49 246 569/8-9 1x4.5x4.4 RCB 6.850 4.5 0.40 12.33 02.05.13
50 247 569/14-15 1x1.2x1.2 RCB 9.180 1.2 0.27 2.94 02.05.13
51 248 570/14-15 1 x4x 1.9 RCB 6.850 4 0.20 5.48 02.05.13
52 249 572/3-4 1x1.2x1.2 RCB 7.650 1.2 0.17 1.53 02.05.13
53 250 572/13-14 1x 6x 3 RCB 6.850 6 0.10 4.11 02.05.13
54 251 572/14-15 1x6x5.3 RCB 6.850 6 0.37 15.07 05.05.13
55 252 573/3-5 9x12.2 PSC 20.04.13
56 252 A 573/5-6
57 253 573/8-9 1x1.2x1.2 RCB 10.710 1.2 0.23 3.00 Completed
Major Bridge
Closed Bridge
Major Bridge
Page 7 of 21
7/30/2019 Comp Programme Civil 17.04.12 (R1)
8/21
Sl. No. Br. No. Location Span Barrel length Width Depth Total (Cum) Completion date
58 254 573/9-10 1x1.2x1.2 RCB 9.180 1.2 0.10 1.10 Completed
59 255 573/11-12 1x1.2x1.2 RCB 7.650 1.2 0.17 1.53 Completed
60 256 573/14-15 1x1.2x1.2 RCB 7.650 1.2 0.17 1.53 Completed
61 257 574/2-3 1x1.2x1.2 RCB 7.650 1.2 0.38 3.52 03.05.13
62 258 574/4-5 1x1.2x1.2 RCB 7.650 1.2 0.20 1.84 03.05.13
63 259 574/5-6 1x6x2.3 RCB 6.850 6 0.27 10.96 10.05.13
64 260 574/12-13 1x1.2x1.2 RCB 7.650 1.2 0.27 2.45 03.05.13
65 261 575/5-6 1x4.5x3 RCB 6.850 4.5 0.53 16.44 12.05.13
66 262 575/15-576/1 1x1.2x1.2 RCB 7.650 1.2 0.27 2.45 13.05.13
67 263 575/15-576/1
68 264 576/7-8 1x1.2x1.2 RCB 32.130 1.2 0.20 7.71 13.05.13
69 265 576/10-11 1x2x2.3 RCB 32.325 2 0.17 10.78 15.05.13
70 266 577/6-7 1x4.5x3.4 RCB 6.850 4.5 0.17 5.14 13.05.13
71 267 577/9-10 1x1.2x1.2 RCB 10.710 1.2 0.33 4.28 13.05.13
72 268 577/12-13 1x1.2x1.2 RCB 9.180 1.2 0.23 2.57 13.05.13
73 269 577/12-13 1x2.5x2.8 RCB 6.850 2.5 0.30 5.14 15.05.13
74 270 577/14-15 2x4x2.1 RCB 6.850 4 0.17 4.57 15.05.13
75 271 577/16-578/1 1x2x1.2 RCB 6.850 2 0.50 6.85 Completed
76 272 579/7-8 1x3x1.2 RCB 6.850 3 0.40 8.22 Completed
77 273 580/3-4 1x4.5x1.4 RCB 6.850 4.5 0.37 11.30 17.05.13
78 274 580/13-14 1x1.2x1.2 RCB 7.650 1.2 0.20 1.84 17.05.13
79 275 581/2-3 1x1.2x1.2 RCB 7.650 1.2 0.43 3.98 17.05.13
80 276 581/5-6 1x1.2x1.2 RCB 7.650 1.2 0.50 4.59 17.05.13
81 277 581/7-8 1x1.2x1.2 RCB 7.650 1.2 0.43 3.98 17.05.13
82 278 581/13-14 1x1.2x1.2 RCB 7.650 1.2 0.47 4.28 17.05.13
83 279 581/15-582/1 1x4.5x1.6 RCB 6.850 4.5 0.37 11.30 17.05.13
84 280 582/8-9 1x1.2x1.2 RCB 7.650 1.2 0.43 3.98 17.05.13
85 281 582/10-11 1x1.2x1.2 RCB 7.650 1.2 0.40 3.67 17.05.13
86 282 583/11-12 Completed
87 283 583/12-13 1x1.2x1.2 RCB 9.180 1.2 0.38 4.22 20.04.13
Retained
Closed Bridge
Page 8 of 21
7/30/2019 Comp Programme Civil 17.04.12 (R1)
9/21
Sl. No. Br. No. Location Span Barrel length Width Depth Total (Cum) Completion date
88 284 583/12-13 1x1.2x1.2 RCB 9.180 1.2 0.47 5.14 Completed
89 285 583/14-15 1x1.2x1.2 RCB 10.710 1.2 0.50 6.43 Completed
90 286 584/1-2 1x1.2x1.2 RCB 10.710 1.2 0.37 4.71 Completed
91 287 584/4-5 1x6x2.3 RCB 13.760 6 0.24 19.81 Completed
92 288 584/7-8 5X12.2 PSC Completed
93 288A 584/8-9 1x1.2x1.2 RCB 13.000 1.2 0.30 4.68 05.05.13
94 289 585/5-6 1x1.2x1.2 RCB 9.180 1.2 0.17 1.84 05.05.13
95 290 585/6-7 1x4.5x3.1 RCB 6.850 4.5 0.43 13.36 07.05.13
96 291 587/1-2 1x1.2x1.2 RCB 7.650 1.2 0.38 3.52 05.05.13
97 292 588/5-6 1x4.5x3.7 RCB 6.850 4.5 0.67 20.55 Completed
98 293 588/7-9 11 x12.2 PSC Completed
647.33
Major Bridge
Total ASSESSMENT QTY
Major Bridge
Page 9 of 21
7/30/2019 Comp Programme Civil 17.04.12 (R1)
10/21
LARSEN & TOUBRO LIMITED
TIRUCHULI - VIRUDHUNAGAR RC PROJECT
ACTION PLAN FOR COMPLETING BALANCE WORKS - WEARING COAT
Date : 17.04.13
Sl. No. Br. No. Location Wearing Coat (Cum) Completion date
1 294 589/11-12 9.00 20.04.13
2 296 590/14-15 33.00 27.04.13
3 299 591/10-11 3.00 28.04.13
4 300 591/12-13 1.38 29.04.13
5 302 592/15-593/1 4.50 30.04.13
6 308 595/3-4 3.60 2/05,13
7 313 595/12-13 11.00 03.05.13
8 329 608/9-10 5.00 04.05.13
9 330 609/5-6 4.50 06.05.13
10 331 611/12-13 5.00 07.05.13
11 333 612/9-10 12.30 10.05.13
12 338A 613/14-15 6.10 11.05.13
13 340 613/15-614/1 5.00 12.05.13
14 348 618/12-13 12.00 13.05.13
115.38
Page 10 of 21
7/30/2019 Comp Programme Civil 17.04.12 (R1)
11/21
LARSEN & TOUBRO LIMITED
TIRUCHULI - VIRUDHUNAGAR RC PROJECT
ACTION PLAN FOR COMPLETING BALANCE WORKS - WEARING COAT
Date : 17.04.13
Sl. No. Br. No. Location Wearing Coat (Cum) Completion date
1 202 557/2-3 1.38 23.04.13
2 203 557/5-6 1.38 24.04.13
3 205 557/9-10 1.38 25.04.13
4 206 557/10-11 1.38 26.04.13
5 210 559/9-10 1.08 27.04.13
6 230 565/7-8 6.17 30.04.13
7 249 572/3-4 1.38 05.05.13
9 270 577/14-15 8.22 15.05.13
22.35
7/30/2019 Comp Programme Civil 17.04.12 (R1)
12/21
1 199 55613-14 1 x2x 3 RCB 8.000 2 0.30
2 200 556/14-15 1x1.2x1.2 RCB
3 201 556/16-17 1x1.2x1.2 RCB
4 202 557/2-3 1x1.2x1.2 RCB 7.650 1.2 0.40
5 203 557/5-6 1x1.2x1.2 RCB 7.650 1.2 0.50
6 204 557/6-7 1x6x2.3 RCB 6.850 6 0.37
7 205 557/9-10 1x1.2x1.2 RCB 7.650 1.2 0.23
8 206 557/10-11 1x1.2x1.2 RCB 7.650 1.2 0.33
9 207 559/3-4 1x6x3.1 RCB 6.850 6 0.40
10 208 559/6-7 1x6x2.4 RCB 6.850 6 0.50
11 209 559/8-9 1x4x2.5 RCB 6.850 4 0.57
12 210 559/9-10 1x1.2x1.2 RCB 7.650 1.2 0.30
13 211 559/11-12 1x1.2x1.2 RCB 7.650 1.2 0.40
14 212 559/14-15 1x1.2x1.2 RCB 7.650 1.2 0.57
15 212A 559/16-17 1x1.2x1.2 RCB 7.650 1.2 0.10
16 213 559/16-560/1 1x1.2x1.2 RCB 7.650 1.2 0.50
17 214 560/4-5 1x1.2x1.2 RCB 10.710 1.2 0.53
18 215 560/5-6 1x1.2x1.2 RCB 9.180 1.2 0.40
19 216 560/10-11 1x1.2x1.2 RCB 7.650 1.2 0.53
20 217 561/1-2 1x4.5x3 RCB 6.850 4.5 0.50
21 218 561/3-4 6x12.2 PSC
22 219 561/5-6
23 220 561/11-12 1x1.2x1.2 RCB 9.180 1.2 0.47
REACH-I MANAMADURAI-THIRUCHCHULI VENT
Sl. No. BR.No LOCATION PROPOSED SPAN BARREL WRIDTH DEPTH
Major Bridge
7/30/2019 Comp Programme Civil 17.04.12 (R1)
13/21
24 221 562/1-2 1x4x2.4 RCB 6.850 4 0.47
25 222 562/3-4 1x1.2x1.2 RCB 7.650 1.2 0.50
26 223 562/6-7 1x1.2x1.2 RCB 7.650 1.2 0.27
27 224 562/8-9 1x1.2x1.2 RCB 7.650 1.2 0.50
28 225 563/7-8 1x6x2.2 RCB 6.850 6 0.50
29 226 563/8-9 1x6x3 RCB 6.850 6 0.67
30 227 563/10-11 1x4x3 RCB 6.850 4 0.50
31 228 564/1-2 2x4x1.7 RCB 7.000 4 0.50
32 229 564/15-565/1 1x1.2x1.2 RCB 7.650 1.2 0.60
33 230 565/7-8 1x4x1.6 RCB 6.85 4 0.53
34 231 565/8-9 1x4.5x1.8 RCB 6.850 4.5 0.60
35 232 565/9-10 1x1.2x1.2 RCB 7.650 1.2 0.27
36 233 565/13-14 1x1.2x1.2 RCB 7.650 1.2 0.50
37 234 566/1-2 1x1.2x1.2 RCB 7.650 1.2 0.47
38 235 566/3-4 1x1.2x1.2 RCB 7.650 1.2 0.50
39 236 566/3-4 1x1.2x1.2 RCB 7.650 1.2 0.60
40 237 567/4-5 1x4.5x1.8 RCB 6.850 4.5 0.47
41 238 568/1-2 1 x4x 2 RCB 6.850 4 0.40
42 239 568/2-3 1x4x2.3 RCB 6.850 4 0.50
43 240 568/7-8 4x12.2 PSC
44 241 568/8-9 1x4.5x2.6 6.850 4.57 0.27
45 242 569/3-4 1x1.2x1.2 RCB 9.180 1.2 0.50
46 243 569/5-6 1x1.2x1.2 RCB 10.710 1.2 0.20
47 244 569/6-7 1x1.2x1.2 RCB 10.710 1.2 0.27
48 245 569/7-8 1x2.5x2.6 RCB 6.850 2.5 0.33
49 246 569/8-9 1x4.5x4.4 RCB 6.850 4.5 0.40
50 247 569/14-15 1x1.2x1.2 RCB 9.180 1.2 0.27
51 248 570/14-15 1 x4x 1.9 RCB 6.850 4 0.20
Major Bridge
7/30/2019 Comp Programme Civil 17.04.12 (R1)
14/21
52 249 572/3-4 1x1.2x1.2 RCB 7.650 1.2 0.17
53 250 572/13-14 1x 6x 3 RCB 6.850 6 0.10
54 251 572/14-15 1x6x5.3 RCB 6.850 6 0.37
55 252 573/3-5 9x12.2 PSC
56 252 A 573/5-6
57 253 573/8-9 1x1.2x1.2 RCB 10.710 1.2 0.23
58 254 573/9-10 1x1.2x1.2 RCB 9.180 1.2 0.10
59 255 573/11-12 1x1.2x1.2 RCB 7.650 1.2 0.17
60 256 573/14-15 1x1.2x1.2 RCB 7.650 1.2 0.17
61 257 574/2-3 1x1.2x1.2 RCB 7.650 1.2 0.38
62 258 574/4-5 1x1.2x1.2 RCB 7.650 1.2 0.20
63 259 574/5-6 1x6x2.3 RCB 6.850 6 0.27
64 260 574/12-13 1x1.2x1.2 RCB 7.650 1.2 0.27
65 261 575/5-6 1x4.5x3 RCB 6.850 4.5 0.53
66 262 575/15-576/1 1x1.2x1.2 RCB 7.650 1.2 0.27
67 263 575/15-576/1
68 264 576/7-8 1x1.2x1.2 RCB 32.130 1.2 0.20
69 265 576/10-11 1x2x2.3 RCB 32.325 2 0.17
70 266 577/6-7 1x4.5x3.4 RCB 6.850 4.5 0.17
71 267 577/9-10 1x1.2x1.2 RCB 10.710 1.2 0.33
72 268 577/12-13 1x1.2x1.2 RCB 9.180 1.2 0.23
73 269 577/12-13 1x2.5x2.8 RCB 6.850 2.5 0.30
74 270 577/14-15 2x4x2.1 RCB 6.850 4 0.17
75 271 577/16-578/1 1x2x1.2 RCB 6.850 2 0.50
76 272 579/7-8 1x3x1.2 RCB 6.850 3 0.40
77 273 580/3-4 1x4.5x1.4 RCB 6.850 4.5 0.37
78 274 580/13-14 1x1.2x1.2 RCB 7.650 1.2 0.20
79 275 581/2-3 1x1.2x1.2 RCB 7.650 1.2 0.43
Major Bridge
7/30/2019 Comp Programme Civil 17.04.12 (R1)
15/21
80 276 581/5-6 1x1.2x1.2 RCB 7.650 1.2 0.50
81 277 581/7-8 1x1.2x1.2 RCB 7.650 1.2 0.43
82 278 581/13-14 1x1.2x1.2 RCB 7.650 1.2 0.47
83 279 581/15-582/1 1x4.5x1.6 RCB 6.850 4.5 0.37
84 280 582/8-9 1x1.2x1.2 RCB 7.650 1.2 0.43
85 281 582/10-11 1x1.2x1.2 RCB 7.650 1.2 0.40
86 282 583/11-12
87 283 583/12-13 1x1.2x1.2 RCB 9.180 1.2 0.38
88 284 583/12-13 1x1.2x1.2 RCB 9.180 1.2 0.47
89 285 583/14-15 1x1.2x1.2 RCB 10.710 1.2 0.50
90 286 584/1-2 1x1.2x1.2 RCB 10.710 1.2 0.37
91 287 584/4-5 1x6x2.3 RCB 13.760 6 0.24
92 288 584/7-8 5X12.2 PSC
93 288A 584/8-9 1x1.2x1.2 RCB 13.000 1.2 0.30
94 289 585/5-6 1x1.2x1.2 RCB 9.180 1.2 0.17
95 290 585/6-7 1x4.5x3.1 RCB 6.850 4.5 0.43
96 291 587/1-2 1x1.2x1.2 RCB 7.650 1.2 0.38
97 292 588/5-6 1x4.5x3.7 RCB 6.850 4.5 0.67
98 293 588/7-9 11 x12.2 PSC
Total
Retained
Major Bridge
Major Bridge
7/30/2019 Comp Programme Civil 17.04.12 (R1)
16/21
Date of
completion
Required
Labours
JCB hours
required
Date of
completion
4.80 Completed 6 Completed
3.67 Completed 4 Completed
4.59 Completed 5 Completed
15.07 Completed 7 Completed
2.14 Completed 3 Completed
3.06 Completed 5 Completed
16.44 Completed 6
20.55 Completed 4
15.53 Completed 7
2.75 Completed 4
3.67 Completed 5
5.20 Completed 6
0.92 Completed 4
4.59 Completed 5
6.85 Completed 6
4.41 Completed 5
4.90 21.04.13 3 4
15.41 21.04.13 11 7
5.14 21.04.13 4 6
AY DETAILS Date-17-04-13
CUM Status
Inside vent way
cleaning
Outside vent way
Cleaning
onstructed in MNM-RMM GC Project
Pitching
work was
executed by
other
agency
Completed
Closed Bridge
7/30/2019 Comp Programme Civil 17.04.12 (R1)
17/21
12.79 20.04.13 9 7
4.59 20.04.13 3 5
2.45 19.04.13 2 5
4.59 19.04.13 3 5
20.55 Completed 7
27.40 Completed 7.5
13.70 Completed 6
14.00 Completed 7
5.51 29.04.13 4 5
14.61 29.04.13 10 7
18.50 30.04.13 13 7
2.45 30.04.13 2 5
4.59 01.05.13 3 5
4.28 01.05.13 3 5
4.59 02.05.13 3 5
5.51 02.05.13 4 6
14.39 03.05.13 10 6.5
10.96 03.05.13 8 5.5
13.70 04.05.13 10 5.5 04.05.13
8.35 05.05.13 6 5
5.51 05.05.13 4 6
2.57 06.05.13 2 7
3.43 06.05.13 2 8
5.71 07.05.13 4 6
12.33 07.05.13 9 6
2.94 08.05.13 2 6
5.48 08.05.13 4 6
Pitching
work was
executed by
other
agency
Completed
Pitchingwork was
executed by
other
agency
7/30/2019 Comp Programme Civil 17.04.12 (R1)
18/21
1.53 09.05.13 1 5 09.05.13
4.11 09.05.13 3 5 09.05.13
15.07 10.05.13 11 6 10.05.13
3.00 Completed 5
1.10 Completed 5
1.53 Completed 6
1.53 Completed 5
3.52 Completed 5
1.84 Completed 5
10.96 Completed 6
2.45 11.05.13 2 4 11.05.13
16.44 11.05.13 12 7 11.05.13
2.45 12.05.13 2 5 12.05.13
7.71 12.05.13 6 6.5 12.05.13
10.78 12.05.13 8 6 12.05.13
5.14 13.05.13 4 5 13.05.13
4.28 13.05.13 3 5 13.05.13
2.57 13.05.13 2 5 13.05.13
5.14 14.05.13 4 5 14.05.13
4.57 14.05.13 3 5 14.05.13
6.85
8.22
11.30 15.03.13 8 6 15.03.13
1.84 16.05.13 1 6 16.05.13
3.98 16.05.13 3 5 16.05.13
Completed
Closed Bridge
Closed Bridge
Completed
Completed
7/30/2019 Comp Programme Civil 17.04.12 (R1)
19/21
4.59 16.05.13 3 5 16.05.13
3.98 17.05.13 3 5 17.05.13
4.28 17.05.13 3 5 17.05.13
11.30 18.05.13 8 6 18.05.13
3.98 19.05.13 3 6 19.05.13
3.67 19.05.13 3 5 19.05.13
4.22 19.05.13 3 0 19.05.13
5.14
6.43
4.71
19.81
4.68 20.05.13 3 20.05.13
1.84 20.05.13 1 20.05.13
13.36
3.52 20.05.13 3 20.05.13
20.55
634.31 244 416.5
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
7/30/2019 Comp Programme Civil 17.04.12 (R1)
20/21
Date of
completion
Required
Labours
JCB hours
required
Date of
completion
1 293 A, RUB 589/3-4
2 294 589/11-12 1X2.0X1.230 2 0.45 27.00 completed completed 22.04.13
3 296 590/14-15 2X6.0X2.318.350 12.000 0.300 66.06 26.04.13
4 297 590/14-15 1X1.2X1.27.680 1.200 0.20 1.84 27.04.13
5 298 591/5-6 1X1.2X1.29.180 1.200 0.150 1.65 27.04.13
6 299 591/10-11 1X6.0X2.36.850 6.000 0.200 8.22 28.04.13
7 300 591/12-13 1X1.2X1.27.650 1.200 0.300 2.75 28.04.13
8 301 592/2-3 1X4.0X1.8 6.850 4.000 0.250 6.85 29.04.13
9 302 592/15-593/115.000 2.000 0.300 9.00 30.04.13
10 303 593/7-8 1X4.5X3.46.850 4.500 0.300 9.25 02.05.13
11 304 594/2-3 1X1.2X1.29.180 1.200 0.100 1.10 02.05.13
12 305 15-595/1 1X1.2X1.212.240 1.200 0.200 2.94 03.05.13
13 306 595/1-2 1X1.2X1.29.180 1.200 0.300 3.30 03.05.13
14 307 595/2-3 1X1.2X1.26.850 1.200 0.00 Completed
15 308 595/3-4 1X1.2X1.220.000 1.200 0.300 7.20 04.05.13
16 309 595/5-6 1X1.2X1.212.240 1.200 0.300 4.41 04.05.13
17 310 595/8-9 1X1.2X1.220.000 1.200 0.100 2.40 05.05.13
18 311 595/11-12 1X1.2X1.210.710 1.200 0.300 3.86 05.05.13
19 312 595/12-13 1X1.2X1.29.180 1.200 0.300 3.30 06.05.13
20 313 2X4.0X3.36.850 4.000 0.00 Completed
21 31416.000 2.000 0.350 11.20 07.05.13
22 315 596/9-1016.000 2.000 0.350 11.20 07.05.13
23 316 597/1-2 1X1.2X1.2 12.240 1.200 0.350 5.14 08.05.13
24 317 597/4-5 1X1.2X1.212.240 1.200 0.500 7.34 08.05.13
25 318 597/6-7 1X1.2X1.212.240 1.200 0.500 7.34 09.05.13
26 319 598/6-7 1X1.2X1.29.180 1.200 0.300 3.30 09.05.13
27 320 598/14-15 1X2.5X2.06.850 2.500 0.250 4.28 10.05.13
28 321 599/7-8 1X1.2X1.27.650 1.200 0.300 2.75 10.05.13
29 322 600/13-14 1X1.2X1.221.420 1.200 0.350 9.00 11.05.13
30 324 600/15-16 1X4.0X3.06.850 4.000 0.800 21.92 12.05.13
31 325 602/14-15 1X4.0X3.06.850 4.000 0.200 5.48 12.05.13
32 326 604/5-6 1X4.5X2.56.850 4.500 0.850 26.20 13.05.13
33 327 605/2-3 1X4.5X1.66.850 4.500 0.850 26.20 13.05.13
34 328 608/1-2 1X1.2X1.27.650 1.200 0.250 2.30 14.05.13
35 329 608/9-10 1X2.0X2.019.000 2.000 0.250 9.50 14.05.13
36 330 609/5-6 1X1.2X1.219.000 1.200 0.250 5.70 15.05.13
37 331 611/12-13 1X1.2X1.219.000 1.200 0.250 5.70 15.05.13
38 333 612/9-10 2X6.0X3.5 6.850 0.00 Completed
WRIDTH DEPTH CUMLocation
Pitching work
was
executed by
other agency
BARREL
Inside vent way
cleaning
Outside vent way
Cleaning
MINOR BRIDGES DETAILS
REACH - II ( THIRUCHULI - VIRUDHNAGAR )
AS ON : 17.04.13
SI. NO BR. NOPROPOSED
SPAN
7/30/2019 Comp Programme Civil 17.04.12 (R1)
21/21
Date of
completion
Required
Labours
JCB hours
required
Date of
completion
WRIDTH DEPTH CUMLocation BARREL
Inside vent way
cleaning
Outside vent way
CleaningSI. NO BR. NOPROPOSED
SPAN
39 334 612/13-14 1X1.2X1.27.650 1.200 0.300 2.75 16.05.13
40 335 613/6-7 1X2.0X1.7518.000 2.000 0.300 10.80 16.05.13
41 336 613/7-8 1X1.2X1.27.650 1.200 0.350 0.30 17.05.13
42 337 613/10-11 1X1.2X1.27.650 1.200 0.300 2.75 17.05.13
43 338 613/13-14 1X1.2X1.27.650 1.200 0.250 2.30 17.05.13
44 339 613/14-15 1X6.0X2.76.850 6.000 0.00 Completed
45 340 613/15-614/1 1X1.2X1.219.000 1.200 0.450 10.26 18.05.13
46 341 614/8-9 1X2.0X1.519.000 2.000 0.450 17.10 18.05.13
47 342 615/15-616/1 1X4.0X1.3
6.850 4.000 1.000 27.40 19.05.1348 343 617/5-6 1X1.2X1.2
6.850 1.200 0.300 2.47 19.05.13
49 344 618/7-8 1X4.0X1.56.850 4.000 1.000 27.40 20.05.13
50 345 618/8-9 1X4.0X1.510.000 4.000 1.000 40.00 21.05.13
51 346 618/10-11 1X1.2X1.210.000 1.200 1.000 12.00 22.05.13
52 347 618/12-13 1X1.2X1.210.000 1.200 0.100 1.20 22.05.13
53 348 2X4.0X2.59.000 4.000 1.000 36.00 24.05.13
518.43
Pitching work
wasexecuted by
other agency