Compact Aqaba LPGT Presentation-22-1-2015

Post on 22-Jul-2015

47 views 7 download

Tags:

transcript

1

Company / Owner

Marine Contractor

Main Contractors - JV

OUTLINE:

.1Introduction

.2Resources

.3Progress Percentage

◦Construction Status

.4Financial Summary

.5Variation Orders

2

The project consists mainly of the detailed design and construction of LPG Jetty which includes:

•Access Trestle & Loading Platform

•2 No. Berthing Dolphins & 4 No. Mooring Dolphins & Catwalks

•Marine Loading Arms (x2)

•LPG and vapour return lines & Cathodic Protection System

•Fire fighting system & Electrical power supply and lighting

•Contractual project dates:24-Feb-14 24-Oct-14

•Computed Completion Date :21-feb-15

3

4

Manpower 1-Nov-2014 1-Jan-2015

Staff 51 54

Direct Labor 41 64

Equipment Quantity Rented/ Owned

Barge 1 Owned

Flexi float barge 1 Owned

Tug Boat 1 1 Owned

Tug Boat 2 1 Rented

Speed Boat 1 Rented

Vibro Hammer 1 Owned

Diesel Hammer 1 Owned

Crawler Crane 1 Owned

Mobile Crane 3 Rented

Air-Compressor 4 Owned

Welding Machine 20 Owned

Truck Mounted Crane

1 Owned

5

Status Expected Completion Date

Trestle 100% Complete

Platform 100% Complete

Loading Arm 100% Complete

Pile Static Load Test 100% Complete

Pipe Line 80% 31-Jan-15

Mooring Dolphins 80% 25-Jan-15

Berthing Dolphins 75% 31-Jan-15

Catwalks 75% 5-Feb-15

Abutement & Access 50% 28-Jan-15

Electrical 30% 10-Feb-15

Marine Furniture (QRH,BAS,Fenders,..) 20% 12-Feb-15

Commissioning 4-Feb to 18-Feb-15

Construction

6

Front View

10” FF Pipe4” Vapour Pipe6” LPG Pipe

2.5” Water Pipe

U-Channel Pipe Support

Concrete Pipe Support

Pipe 13-Jan-15

FireFighting 80%

Vapour 80%

LPG 80%

Water 80%

7

Invoice No.

Description

Initial Amount (JOD)

Agreed Amount (JOD)

Issue Date Due DateSettlement Date

Overdue Period (days)

Status

001

Advance payment

10%1,723,255.00 1,723,255.00 5-Feb-14 6-Mar-14 8-Jun-14 94 Closed

002 IPC-1 2,356,981.61 1,926,073.33 7-May-14 2-Jul-14 19-Aug-14 48 Closed

003 IPC-2 1,092,297.77 969,456.65 7-Jun-14 2-Aug-14 1-Sep-14 30 Closed

004 IPC-3 1,507,114.54 1,245,493.82 12-Jul-14 6-Sep-14 1-Oct-14 25 Closed

005 IPC-4 1,174,215.32 1,583,941.28 11-Aug-14 6-Oct-14 10-Nov-14 35 Closed

006 IPC-5 1,617,218.84 1,006,200.22 8-Sep-14 3-Nov-14 12-Nov-14 9 Closed

007 IPC-6 2,638,679.75 1,919,859.74 7-Oct-14 2-Dec-14 12-Nov-14 Closed

008 IPC-7 1,571,120.29 1,005,264.70 29-Oct-14 24-Dec-14 30-Nov-14 Closed

009IPC-8

1,864,144.68 993,963.07 2-Dec-14 27-Jan-15 Not Yet Open

010IPC-9

1,366,814.24 1,212,026.19 2-Jan-15 27-Feb-15 Not YetOpen

Issued 14-Jan-2015

.1Steel Water Tank to feed the fire fighting system•Issued on Nov. 17th 2014 (202,425.00) JD, Progress : 30%

.2Firefighting Pumps Room•Issued on 17th 2014 (40,700.0) JD, Progress : 95%

.3LPG and Vapour Return Tie-In to Existing Networks•Issued on 17th 2014 (64,509.61) JD, Progress : 100%

.4Design, Supply and Installation of Main Power cable•Issued on Dec. 24th (18,246.99) JD, Progress : 80%

.5Design, Supply and Installation of a Standby Power Generator•Issued on Dec. 24th (18,198.69) JD, Progress : 80%

8

9

General Layout

General Layout

Trestle Modules

Pipe Lines on Trestle

Mooring Dolphins

13

Firefighting Tank + Pump Room

14

Static Load Test

15

Loading Arm PrecommissioningLoading Arm Construction

16

Firefighting Monitor Towers

17

Abutment

18

Tie in at Loading Arm

19

Tie in Point

20

Cable Trays onshore + Trestle

Q & A21