Project Management - Topics

Schedules And Gantt Charts

Project Milestones

How to Organize Your Team Surgical or Democratic Team?

Drexel University

Schedules And Gantt Charts

3

Drexel University 4

Schedules And Gantt Charts

What is a schedule? A schedule is:

A listing of planned events Properties:

Ordered by time Shows dependencies between tasks Might show assignment of tasks to personnel

Planned events tied to milestones

Drexel University 5

How To Make A Project Schedule Identify the individual component tasks for each

phase or spiral Estimate the size of tasks and amount of time

required Identify dependencies between tasks:

What inputs are required for each task? In what previous task are these inputs created?

Define milestones: High-level milestones Intermediate milestones Low-level milestones (separate personal schedule

document)

Drexel University 6

Gantt Charts A tabular notation to document schedule Rows represent task ids and names (listed in

order). Columns—many variations and many optional

notations: Start-date column, end-date column Task duration column (how long? Hours, days, etc.) Task assignment column (who is doing this?) Task completion: percentage-complete column, or a

line through the task bar

Drexel University 7

Drexel University 8

Gantt Charts Columns—many variations and many optional

notations (continued): Timeline—may be in terms of days, weeks, months,

quarters, etc. In the timeline, a task bar indicates duration of task. Milestones (aka checkpoints) shown like a task and a

task bar, but with a special symbol. Summary “tasks” and bars: higher-level name showing

a collection of related tasks (e.g. requirements analysis, or any “phase” or spiral)

Vertical line showing today's date

Drexel University 9

Comments On Example Chart Two “summary” tasks: requirements analysis

and requirements specification (note the yellow triangles on the ends of the bars)

Timeline: days in a month Duration column: in days, hours Purple-lines in task bars indicate how much is

completed Vertical line shows today's date (task 3 is late!)

Drexel University 10

Comments On Example Chart Milestones: black diamonds, duration of zero “Who” column shows personnel assignments Task dependencies: arrows from one task to

another: First task must be completed before the second

starts Milestones depend on preceding task(s) Tool automatically adjusts chart according to

durations, dependencies

Drexel University 11

Tool Support For Gantt Charts

Microsoft Project: Data file standard: MPX Files (“Ms Project

eXchange”) Visio:

Known As “Project Timeline” Diagram Can Import/export Data In Mpx Format

Drexel University

Project Milestones

12

Drexel University 13

Advice On Milestones For team projects Milestones often tied to sign-off (after review) of major

work-products, such as: Project management plan document Software requirements specification (SRS) document Design document Stage 1 code released (stage 2,...) Final product released

Milestones Must Be Visible To Management, Possibly Customer

Drexel University 14

Milestones

Part of top-down approach Break large project into small problems, each of

which can be estimated and planned A milestone is:

An objectively identifiable point in a project Good checkpoints are:

Clear, unambiguous, crisp, verifiable Binary: done or not done

Drexel University 15

Milestones

“Coding is 90% complete”: In terms of time, or loc? How do you know?

“Program is designed”: What’s this mean? In your head, or on paper? Has it been reviewed, agreed upon?

Drexel University 16

Milestones—Good Examples

Design document reviewed Design document signed-off by management System software successfully passes integration

test data suite Specification document approved by customer All risks determined at last process review

addressed and resolved

Drexel University

How to Organize Your Team

17

Drexel University 18

Group/Team Structure Differences between programmers:

Productivity: 10:1 Program Speed: 5:1

What if we only hire top people?

Efficiency + Conceptual Integrity vs. Large System

Drexel University 19

Group/Team Structure Democratic Team or Surgical Team? A Surgical Team

The Surgeon –-Chief architect, Design and Impl The Copilot ---Impl, Testing, etc The Administrator ---Version control, plan, testing The Program clerk The Editor Two Secretaries The Tool Smith The Tester The language Laywer

Drexel University

Summary How to plan your project using a Gantt Chart

The concept of milestone

Surgical Team vs. Democratic Team

20

Drexel University

Reminder: Reading Homework:

"No Silver Bullet: Essence and Accidents of Software Engineering", by Frederick P. Brooks.

"The Mythical Man Month" by Frederick P. Brooks. Next Tuesday Quiz on papers Term project presentation

21

Drexel University

Term Project Presentation Project description

List all the functions of the project What are the input/output How will the user interact with it Web based? Standalone App? Mobile App?

Team member roles The Surgeon –-Chief architect, Design, Document and Impl The Copilot ---Impl, Testing, Document, etc The Administrator ---Version control, plan, testing The Tester

Project plan in a Gantt Chart with at least 4 milestones

22