Department of Community Planning, Housing & Development
Planning Division Work Program
Arlington County Board &Planning Division Work SessionMarch 8, 2016
PRESENTATION
2016-17 Planning Work Program Report
REPORT CONTENTS
1. Planning Division organization, staffing, functions and 2016 and 2017 budgeted hours
2. Planning Division 2016 – 2017 preliminary work program by section
• Comprehensive Planning Section
• Urban Design and Research Section
• Current Planning Section
3. Summary of 2016 Planning Division Work Program
4. Summary of 2017 (January – June) Planning Division Work program
5. Projects not included as part of the Planning Division’s 2016 – 2017 work program
6. 2016 – 2017 Work Program Projects for Further Discussion
7. Work Program Attachments
8. Planning Division preliminary work program schedules
1
Presentation Overview
» Our Mission» How We Work» Results» Who We Are» 2016-17 Work Program Summary » Comprehensive Planning » Current Planning » Urban Design & Research» Projects not included» Summary of 2016 Projects» Summary of 2016-17 Projects» 2016-17 Work Program Projects for
Further Discussion2
community
communityresilience
building
community sustainability
community design
community engagement
community planning
3
how we work
We work collaboratively to make great places and communities happen in Arlington.
We plan and design for the future of our community.
We value and facilitate civic engagement.
We are a resource for data and knowledge.
4
2015-16JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN
Rosslyn Sector Plan adoption
Western Rosslyn Area Plan adoption Courthouse Sector Plan adoption
672 Flats site plan approval
Clarendon West site plan approval
Lee Highway Visioning CharretteFirst Development Forum
Community Facilities Study Final Report
Ballston Quarter site plan approval
Gilliam Place site plan approval
4000 Fairfax Dr site plan approval
1411 Key Blvd site plan approval
Village Center site plan approval
WRAPs Implementation
DESIGNArlington Awards
Results
5
» 3 Sector/Area Plan Adoptions» Rosslyn Sector Plan» Western Rosslyn Area Plan» Courthouse Sector Plan
» 700+ participants engaged in Lee Highway Visioning» Site Plan Review Process Revisions» Comprehensive Zoning Ordinance Update» 11-month Community Facilities Study & Report» 14 Pubic Facilities Review meetings with APS» 11 DESIGNArlington award winners recognized» Approved new development in 2015, totaling:
» 946,050 square feet of office space (GFA)» 466,132 square feet of retail space (GFA)» 3,747 new residential units» Key transfomational projects such as the $317 million Ballston Quarter
Results
6
» 33 staff members» 3 planning sections» Communications team» Administration team
Who we are
7
Steve Cover, AICPDCPHD Director
Robert J. Duffy, AICPPlanning Director
Jessica Gilmore, Management SpecialistJessica Margarit, Strategic Communications Specialist IIAndrew Pribulka, Digital Communications Specialist I
Administration Current Planning Urban Design & Research Comprehensive PlanningBonnie Strang,
Office Supervisor IITom Miller,
Planning SupervisorKris Krider,
Planning SupervisorClaude Williamson,Planning Supervisor
Administrative Assistant VKaron Henry
Planning Commission & PFRC Coordinator
Michelle Stahlhut, Principal PlannerClerk to the Planning Commission
Gizele JohnsonSite Plan Team
Site Plan CoordinatorSamia Byrd, Principal Planner
Principal PlannersMatthew PfeifferPeter SchultzAaron Shriber
Use Permit TeamPrincipal Planner (Developmental)
Michael CullenAssociate Planners
Nicole BolingSophia FisherMarco RiveroVacant
Urban Design TeamPrincipal Urban Designer
Brett WallaceChief Architect & Urban Designer
Justin Falango, Principal PlannerLandscape Architect
Associate Planner (Vacant)
Research TeamAssociate Planners
Andrew D’HuyvetterElizabeth Hardy
Master Planning TeamPrincipal Planners
Deborah AlbertAnthony FusarelliMatt MattauszekJennifer SmithRichard TuckerElizabeth Weigle
Associate PlannersMatt LaddLeon VignesKellie Brown (.5)Margaret Tulloch Rhodes (.5)
Who we are
8
Planning Division
Communication Administration
Comprehensive Planning Urban Design & Research Current Planning
• Plan Implementation
• Zoning Ordinance Amendments
• Columbia Pike
• Crystal City, Pentagon City and Potomac Yard (22202)
• Comprehensive Plan and General Land Use Plan
• Community Planning
• Ongoing Planning Studies, Facilitation, Coordination and Administration
• Urban Design, Architecture and Landscape Architecture Review
• Research, Demographic and Development Tracking, Projections & Forecasting
• Urban Design & Planning
• Interdivisional, Interdepartmental and Community Urban Design Support
• Community Education and Engagement
• Site Plan - Special Exception, Use Permit and Development Application Review and Reports
• Arlington Public School Facility Site Planning, Design Review and Use Permitting
• Support for Comprehensive Planning and Urban Design and Research
• Planning Commission Coordination and Administration
• Public Facilities Review Committee Coordination and Administration
• Permitting System Conversion and Revisions
Who we are
9
Comprehensive Planning Work Program
» Plan Implementation» Zoning Ordinance Amendments» Columbia Pike » Crystal City, Pentagon City, Potomac Yard
(22202)» General Land Use Plan» Community Planning» Ongoing planning coordination and
administration
» Document and file management
10
» Four Mile Run Valley Initiative
» Columbia Pike Commercial Centers and Neighborhood Areas Plan review and update
» Crystal City Sector Plan review and update
» Affordable Housing Master Plan Implementation - ADU
» Special GLUP studies
» Five Year Review of the Comprehensive Plan
» Pentagon City PDSP Report - Transportation and Community Facilities
2016 2016-17
Preliminary
» Western Rosslyn Area Planning Study Implementation
» Rosslyn Sector Plan Implementation
» Courthouse Square Plan Implementation
» Sign regulations update – case law
» Special sign regulations- regional commercial centers
» Historic Preservation Overlay District Amendments for APS
» Car Rental Zoning Ordinance Amendment
» Columbia Pike – FBC Zoning and Policy Amendments
» Lee Highway Community Visioning
» Lee Highway Pre-Planning (Scope and Process)
Comprehensive Planning Projects
11
Urban Design & Research Work Program
» Urban design, architecture and landscape architecture review
» Research, demographic and development tracking, projections and forecasting
» Urban design support for Comprehensive and Current Planning
» Interdepartmental urban design support
» Community education and engagement
» Document & file management12
2016 2016-17
Preliminary
» Design Arlington Awards
» COG 9.0 Regional Forecast
» Courthouse Square Plan Implementation
» Lee Highway Community Visioning
» Lee Highway Pre-Planning (Scope and Process)
» Policies for redevelopment and adaptive reuse of planned office space
» Four Mile Run Valley Initiative
» Columbia Pike Commercial Centers and Neighborhood Areas Plan review and update
» Crystal City Sector Plan review and update
» Affordable Housing Master Plan Implementation - Affordable by Design
» Special GLUP studies
» Architecture and urban design forum
Urban Design & Research Projects
13
Current Planning Work Program
» Site plan, use permit and development application review
» APS facility review and use permitting» Support for Comprehensive Planning and
Urban Design projects» Planning Commission administration» Public Facilities Review Committee
coordination and administration» Permitting System Conversion
» Document and file management
14
Current Planning Projects
2016 2016-17
Preliminary
» Site Plan, Use Permit and Development Application Review
» Implementation of recommended revisions to site plan review and administration
» Permitting system conversion and revisions
» APS facility review and use permitting – Stratford, Wilson and Thomas Jefferson
» Residential Parking Standards for Metro Station Areas
» Special GLUP studies
15
Summary of 2016 Planning Division ProjectsPlan Implementation» Western Rosslyn Area Planning Study Implementation» Rosslyn Sector Plan Implementation» Courthouse Square Plan Implementation
Site Plan Review» Implementation of Recommended Revisions to Site Plan Review
Process and Administration
Zoning Ordinance Amendments» Sign Regulations Update - Case Law» Special Sign Regulations - Regional Commercial Centers» Historic Preservation Overlay District Amendments for
APS» Car Rental Zoning Ordinance Amendment
16
Summary of 2016 Planning Division Projects(continued)
Columbia Pike» Columbia Pike - FBC Zoning and Policy Amendments
Community Planning» Lee Highway Corridor Visioning
Research» COG Regional Forecast
Community Education and Engagement» DESIGNArlington Awards
17
Comprehensive Plan» Five Year Review of the Comprehensive Plan» Special GLUP Studies
Columbia Pike» Columbia Pike Commercial Centers and Neighborhood Areas Plan
Review and Update
Crystal City, Pentagon City and Potomac Yard (22202)» Crystal City Sector Plan Review and Update» Pentagon City PDSP - Transportation and Community
Facilities
Zoning Ordinance Amendments» Affordable Housing Master Plan Implementation
Summary of 2016-17 Planning Division Projects
18
Community Planning» Lee Highway Pre-Planning (Visioning, Scope and Process)» Four Mile Run Valley Initiative
Research» Policies for Redevelopment and Adaptive Reuse of Planned Office
Space
Community Education and Engagement» Architecture and Urban Design Forum
Current Planning» Permitting System Conversions and Revisions» APS Facility Review and Use Permitting - Stratford,
Wilson and Thomas Jefferson» Residential Parking Standards for Metro
Station Areas
Summary of 2016-17 Planning Division Projects (continued)
19
Planning Projects Not Included as part of the 2016-17 Work Program
2016-17 » Affordable Housing Master Plan - Land Use Tools for Use
Adjacent to Unplanned Transportation Corridors
» Affordable Housing Master Plan - Identification of Existing MARK-Heavy Areas that could be Candidates for Small Area Plans
» Westover Study - Conservation Strategies for Market Rate Housing
» Zoning Ordinance Amendments (see Attachment 1)
» Urban Design Study and Guidelines for Neighborhood Edges
» Analysis and Report - Arlington County Planning for Sustainable Growth
» Arlington County Sector Plans - Report on Future Purpose, Objectives, Scope and Update Schedule
20
2016-17 Work Program Projects for Further Discussion
» Zoning Ordinance Amendments» Implementation of Site Plan Review Process Revisions» Four Mile Run Valley Initiative
» Lee Highway Pre-Planning (Visioning, Scope and Process)
21
Department of Community Planning, Housing & Development
Planning Division Work Program