Post on 07-Apr-2018
transcript
8/6/2019 Earned Value Management - The Basics
http://slidepdf.com/reader/full/earned-value-management-the-basics 1/18
Earned Value Management
The Basics
8/6/2019 Earned Value Management - The Basics
http://slidepdf.com/reader/full/earned-value-management-the-basics 2/18
EVA Learning Outcomes
• Describe EVM
• Explain advantages and disadvantages of
EVM• Perform earned value calculation and
interpret earned value data
8/6/2019 Earned Value Management - The Basics
http://slidepdf.com/reader/full/earned-value-management-the-basics 3/18
Earned Value Management
Defined
Earned Value Management (EVM) is a project control process based on a
structured approach to planning, cost collection and performance
measurement. It facilitates the integration of project scope, time and cost
objectives and the establishment of a baseline plan for performance
measurement.
The purpose of measuring earned value is to provide information in order to
determine:
• what has been achieved of the planned work
• what it has cost to achieve the planned work
• whether the work achieved is costing more or less than was planned
• whether the project is ahead of behind the planned schedule
8/6/2019 Earned Value Management - The Basics
http://slidepdf.com/reader/full/earned-value-management-the-basics 4/18
Advantages and Disadvantages of
EVM
Advantages Disadvantages
Variance analysis – shows current status interms of cost and schedule
Time consuming and requires experiencedeffort to measure and analyse performance.
Forecasting – enables predictions of cost atcompletion and completion date
Forecasts depend on reliable measurementsthat can be difficult to achieve for some costtypes
Efficiency – provides performance indicesidentifying areas under of ever performing andrequiring corrective action
Past performance is not necessarily anindication of future performance
Estimating accuracy – provides feedback of actual performance against baseline estimates
Does not take into account risks anduncertainties
Provides triggers for escalating problems andhighlighting successes
Requires a compatible cost collection system
8/6/2019 Earned Value Management - The Basics
http://slidepdf.com/reader/full/earned-value-management-the-basics 5/18
Earned Value Elements• Planned Value (PV) – Value of work planned to be done at a particular point in time.
• Earned Value (EV) – Value (volume) of Work Achieved – Physical Progress• Actual Cost (AC) –Recorded Cost of work performed
By integrating three
measurements - EV, AC &
TIME : Key performanceindicators are produced to
evaluate the health of the
project.
COST
TIME
AC PV
EV
8/6/2019 Earned Value Management - The Basics
http://slidepdf.com/reader/full/earned-value-management-the-basics 6/18
EV Management Terms
• Budget at Completion – Total budget for the work to be carried out
• Original Duration – planned overall duration
• Planned Value – Budgeted Cost of the Work Scheduled (BCWS)
• Data Date – reference point used to measure and evaluate the current status aka Time
Now
• Actual Cost – Cumulative cost incurred at the Data Date. Also called the Actual Costof Work Performed (ACWP)
• Earned Value – Value of planned work done at Data Date. Also called the Budgeted
Cost of Work Performed (BCWP)
• Estimated Cost at Completion (EAC) – The predicted outturn in cost terms
Memorise these – all schedulers must know it!
8/6/2019 Earned Value Management - The Basics
http://slidepdf.com/reader/full/earned-value-management-the-basics 7/18
EV Management Terms
CO
ST
TIMEEV
Actual
Cost
Budget at
Completion
Estimated Cost atCompletion
Forecast Cost
Overrun
Forecast Time
Overrun
PV
Forecast
SVCV
Data
Date
OD Forecast
Duration
8/6/2019 Earned Value Management - The Basics
http://slidepdf.com/reader/full/earned-value-management-the-basics 8/18
8/6/2019 Earned Value Management - The Basics
http://slidepdf.com/reader/full/earned-value-management-the-basics 9/18
Earned Value Principles
The principles of Earned Value Analysis can be illustrated through a simple
example as shown.
The project objectives are to lay a new pipeline. The work has been broken
down into two areas: Ground Works and Pipe Works. Ground works has
been completed. The are tow work packages in Pipe Works. The first, ‘Buy
Pipe’ has been completed and the pipe has been deliver to site. The other work package ‘Lay Pipe’ has been in progress for two weeks.
Key objectives and parameters for the work package are:
Estimated cost for laying pipe = £100 per meter
Length to be laid = 1000 metersThus, Total Budget = £100k
Duration for WP = 8weeks
Quality = no leaks
8/6/2019 Earned Value Management - The Basics
http://slidepdf.com/reader/full/earned-value-management-the-basics 10/18
Earned Value Measurement
After two weeks (Time Now aka Data Date) the work package manager reviews the
progress
The manager is expecting 25% of the work to be completed at Data Date. This is based
on the estimated spend over two weeks. Since the budget for all of the work is
£100k, the value for 25% of the work is £25k assuming a linear rate of spend for
simplicity.
At Data Date the manager also check the account and finds that £30k has been charged
to the work package (actual cost). However, also at Data Date, the manager checks
the surveyor's report which shows that 20% has been achieved.
2 wk 4 wk 6 wk 8 wk
Check points
EV at Data Date
= % Compl x budget
= 20% x £100k
= £20k
Actual Cost (AC) at Data Date = £30k
Planned Value (PV) at Data Date = £25k
8/6/2019 Earned Value Management - The Basics
http://slidepdf.com/reader/full/earned-value-management-the-basics 11/18
Earned Value Analysis
The manager can now complete the analysis.
The first task is to calculate the SV. This will indicate how much the project is off-spec in terms of time.
SV = EV – PV
= £20k - £25k
= -£5k
The next task is to calculate the cost variance. This will show how much the project is off target interms of cost.
CV = EV – AC
= £20k - £30k
= -£10k
From above calculation we can see that the project is behind schedule and overspending. Further
analysis will provide predictions of the time and cost.
Ev
PvAc
Cost Schedule
EV = £20k
PV = £25kAC = £30k
8/6/2019 Earned Value Management - The Basics
http://slidepdf.com/reader/full/earned-value-management-the-basics 12/18
Performance Indicators
The performance indices are calculated as follows:
SPI = EV/PV = 20/25 = 0.8
CPI = EV/AC = 20/30 = 0.67
Thus,
Forecast Duration = OD/SPI = 8/0.8 = 10weeks
EAC = BAC/CPI = 100/0.67 = £150k
Ev
PvAc
Cost Schedule
EV = £20k
PV = £25kAC = £30k
8/6/2019 Earned Value Management - The Basics
http://slidepdf.com/reader/full/earned-value-management-the-basics 13/18
What does this look like graphically?
COST
( 1 0 0 0
’ s )
WeeksEV
Budget at
Completion
Estimated Cost atCompletion
Forecast Cost
Overrun
Forecast Time
Overrun
PV
Forecast
SVCV
2 8 10
20
25
30
150
100
AC
D r a w
i n b y h a
n d
8/6/2019 Earned Value Management - The Basics
http://slidepdf.com/reader/full/earned-value-management-the-basics 14/18
Exercise 1
A project has a budget o £200k and a completion date of 12 months. The progress for the first four months is shown in the table below
All values are in £k
Month 1 Month 2 Month 3 Month 4
PV 40 85 80 110
AC 30 70 95 115
EV 35 55 75 95
1. Calculate the forecast duration and the estimate at completion (EAC) for this project based on this information.
2. Explain how the cost efficiency has changed of the first four months
3. What will the EAC be if the CPI changes to 0.9 for all remaining work?
8/6/2019 Earned Value Management - The Basics
http://slidepdf.com/reader/full/earned-value-management-the-basics 15/18
Exercise 1 – Student Handout
COST
( 1 0 0 0
’ s )
Months
8/6/2019 Earned Value Management - The Basics
http://slidepdf.com/reader/full/earned-value-management-the-basics 16/18
Exercise 1 - Answers
Month CPI
1 1.17
2 0.79
3 0.79
4 0.83
1. At Month 4 (latest Data Date):
SPI = EV/PV = 95/110 = 0.86
Forecast Duration = OD/SPI = 12/0.86 = 13.95 = 14months
CPI = EV/AC = 95/115 = 0.83
EAC = BAC/CPI = 200/0.83 = £241k
2. Cost efficiency can be represented by CPI
1
C
P I
Months
1 32 4
8/6/2019 Earned Value Management - The Basics
http://slidepdf.com/reader/full/earned-value-management-the-basics 17/18
Exercise 1 – Answers (Continued)2. Cost efficiency was excellent for Month 1 because CPI>1
CPI for Month 2 dropped below desired levels with CPI<1
Month 3’s CPI was still poor (CPI<1) with no change from the previous monthMonth 4 shows a slight improvement, however the CPI indicates that th is project will overspend.
3. EAC = BAC/CPI = 200/0.9 = £222k