Post on 14-Jan-2016
transcript
1
Efficient Grain Facility Design & OperationBy: Gregg Davidson, Owner
DAVIDSON GRAIN SOLUTIONS (DGS)
PRESENTATION FOR
North DakotaGrain Dealers Association
101st Annual Convention and Industry ShowJanuary 20-22, 2013
Fargo Holiday Inn
2
DAVIDSON GRAIN SOLUTIONS (DGS)
• Troubleshooting• Plant Engineering• Master-Planning• Construction
Management• Start-up & Training
Maddock, ND ● Moorhead, MN ● Plymouth, MN
3
THE GOAL TODAY…
For me: Offer up some new ideas and some proven reminders
to: Change/improve your existing facility successfully Build a new addition or new facility Operate your facility better and safer Maintain your facility better and safer
For you: Look for new ideas that you can incorporate back home Reinforce old ideas that are proven Think of a question or comment Relax and enjoy the presentation followed by questions
4
6 STEPS TO IMPROVE YOUR FACILITY Step 1 - Conceptual Design Step 2 - Front End Engineering Design Step 3 - Detailed Design Step 4 - Construction Step 5 - Start-Up & Warranty Step 6- Safety Devices, Operation, &
Maintenance Bucket Elevator Legs Drag Conveyors Belt Conveyors
5
STEP 1 - CONCEPTUAL DESIGN
Process flow diagram (front gate thru exit gate) Changes to existing flow or developing new flow
Crops handled and annual bushels per crop Total annual bushels handled Operating hours non-harvest and harvest In-bound truck/rail weighing and sampling Out-bound truck/rail weighing and sampling Receiving system(s) truck/rail flow rate Storage type and capacities Grain temperature monitoring Drying system flow rate/moisture reduction
6
CONCEPTUAL DESIGN – PAGE 2
In-house transfer flow rate Rail load-out flow rate and allowed loading time w/0 penalty Truck load out flow rate Equipment by-pass/duplication options Sanitation goals Automation goals Operator control room scheme Special requirements for inspectors and required certifications Other key business goals Other key customer goals
Interference with existing operations Future growth considerations Cadillac or nice Chevrolet ($$$) Potential concerns by neighbors and public
7
CONCEPTUAL DESIGN – PAGE 3
Site plan (outside front gate thru outside exit gate) 3D for aerial perspective 2D for details
Existing structures, roads, and landmarks Off-site improvements (drainage, public roads, traffic
flow) Site grading and drainage Utilities (electrical, gas, water, sewer, fire,
communications)
8
CONCEPTUAL DESIGN – PAGE 4 Roads and parking (traffic flow, customers, employees,
surfaces) Emergency vehicle access Structures Railroad Landscape areas Low maintenance areas Site security (lighting, gates & fence, guard shack, public
locks) Other key business and customer goals Construction staging area
Interference with existing operations Future growth considerations Cadillac or nice Chevrolet ($$$) Potential concerns by neighbors and public
9
STEP 2 – FRONT END ENGINEERING DESIGN
Organizational chart Show owners, designers, contractors, & subs Show overall responsibilities for each Show method of project delivery for each
Design – build Design – bid - build
Consider shared document website for info sharing Project schedule
Weather impact Project budget
Weather impact
10
FRONT END ENGINEERING DESIGN – PAGE 2
Permits City County Watershed district State Federal Railroad Utilities (electrical, gas, water, sewer, fire,
comm.) Determine electrical classification for all areas
11
FRONT END ENGINEERING DESIGN – PAGE 3
Land ownership Clear title Easements
Site survey report Existing topography, buildings, roads, and landmarks
Geotechnical report Locate multiple soil borings directly under key areas Estimated total soil settlement Estimated differential soil settlement Estimated water table during construction & operation Determine geotech’s ability to perform material testing
12
FRONT END ENGINEERING DESIGN – PAGE 4 Operational safety
Explosion prevention and venting Fall protection guarding Running equipment guarding Secondary egress Others specific to the facility
Determine construction management needs Evaluate internal skills, experience, and time
available Consider outside help for:
Conceptual and Front End Engineering Design Bid package development Over-sight of Construction, Start-Up, & Warranty
13
STEP 3 – DETAILED DESIGN Civil package
Site plan Railroad plan
Structures and machinery package Process flow diagram General arrangements Concrete structural Steel structural Miscellaneous Equipment list
Electrical package Controls package
14
STEP 4 - CONSTRUCTION Construction safety
Excavations Fall protection Ladders and scaffolding Crane lifts Electrocution Personal protective equipment Other hazards specific to the project
15
CONSTRUCTION – PAGE 2 Construction contract
Format (design-build, build only) Project schedule Responsibility for final engineering Construction safety Responsibility for material testing and review Insurance and bonding Retainage Liquidated damages Start-up What triggers final payment? Warranty
16
CONSTRUCTION – PAGE 3
Owner mobilization Pre-mobilization meeting (per organizational chart) Construction staking Temporary electrical service Temporary water service (fire protection?) Temporary communications
Contractor mobilization Critical meetings and inspections
Daily, weekly, monthly Progress photos
Final punch list (substantial completion)
17
STEP 5 – START-UP & WARRANTY
Operator training materials Hard copies & electronic version of manuals
Operator training Start-up plan to SAFELY meet phased goals
Process equipment Process safety devices and instrumentation Dust collection balancing Building-related devices and instrumentation Engineered silo/bin loading plan
18
START-UP & WARRANTY – PAGE 2 Final written acceptance by Owner Contractor de-mobilization As-built documentation
Hard copies & electronic version of as-built drawings & specs
Post-project de-briefing meeting Problems and praises Future maintenance and project needs Potential reference and marketing testimony
Issue final payment Warranty period (solve problems together)
19
STEP 6 – BUCKET ELEVATOR LEGS
Recommended safety devices Speed monitor on boot shaft for alarm and
shutdown Belt alignment switch on each side of boot Bearing temperature sensor on each side of boot Belt alignment switch on each side of head Bearing temperature sensor on each side of head Plug switch at leg discharge Guarding over all exposed shafts Explosion panels
20
BUCKET ELEVATOR LEGS – PAGE 2
Operation Install outside if possible Maximum 650 feet per minute (fpm) belt speed =
7mph Wear liner selection based on crops, bushels, & years Spout feeding leg inlet plays huge role in filling cups Height of leg inlet with respect to boot shaft is critical Class II drive with backstop capable of starting leg
under full load Reduced voltage starter (soft start) capable of starting
leg under full load
21
BUCKET ELEVATOR LEGS – PAGE 3
Maintenance Replace head pulley lagging if belt will not track
or crown (1/8” per foot from edge to center of pulley) is gone
Belt replacement guideline based on 1.5% stretch Example: 100 ft tall leg = 200 ft belt x 1.5% = 3 ft = 1.5
ft take up Replace bearings based on frequent
inspection Watch/listen for changes
22
STEP 6 – DRAG CONVEYORS
Recommended safety devices Speed monitor on tail shaft for alarm and
shutdown Slack/tight chain switch on tail Plug switch at conveyor discharge Guarding over all exposed shafts
23
DRAG CONVEYORS – PAGE 2
Operation 150 to 180 feet per minute (fpm) chain speed
= 2 mph Wear liner selection based on crops, bushels, &
years Class II drive capable of starting drag under
full load Reduced voltage starter (soft start) capable of
starting drag under full load
24
DRAG CONVEY0RS – PAGE 3
Maintenance Replace bearings, sprockets, and chain based
on frequent inspection Watch/listen for changes
25
STEP 6 – BELT CONVEYERS
Recommended safety devices Speed monitor on tail shaft for alarm and
shutdown Belt alignment switch on each side of tail Bearing temperature sensor on each side of tail Belt alignment switch on each side of head Bearing temperature sensor on each side of
head Plug switch at conveyor discharge Guarding over all exposed shafts
26
BELT CONVEYERS – PAGE 2
Operation Maximum 700 feet per minute (fpm) belt speed = 7 mph Wear liner selection based on crops, bushels, and years Spout feeding the loader plays huge role in feeding belt Class II drive capable of starting conveyor under full
load Reduced voltage starter (soft start) capable of starting
conveyor under full load Side wall inspection doors recommended
27
BELT CONVEY0RS – PAGE 3
Maintenance Inspect tail section often for grain re-loading Replace head pulley lagging if belt will not
track Belt replacement guideline based on 1.5%
stretch Replace bearings based on frequent
inspection Watch/listen for changes
28
QUESTIONS? COMMENTS?
Thank you and Go Bison!
Efficient Grain Facility Design & OperationBy: Gregg Davidson, Owner
DAVIDSON GRAIN SOLUTIONS (DGS)