Emmaus Coventry and Warwickshire
Vicki UrchDirector
vickiurch@emmauscoventry.org.uk
About Emmaus Coventry and Warwickshire
• Provide accommodation and work to previously homeless adults in a supportive environment
• At time of bid providing 15 rooms in main Community
• Rent a house providing an additional 3 rooms• Provide staff accommodation for two staff
members
The Money•Joint bid with other Emmaus Communities•Bid to provide additional 8 – 10 rooms•Awarded £30,000 to lease and refurbish up to 3 properties providing 7 – 10 rooms•Given very short time frame (completion June 2013)•Had to have ten year lease•Delay in the process meant even shorter time frame
Property search
• Presented at Landlords forum with support from Coventry City Council
• Worked with empty homes officer to identify eligible properties
• Leg work
The problems
The winner
• Landlord contacted us• Viewed with low expectations• 4 storey property with flat on each floor• No major works• Been empty for over 2 years• Survey• Lease negotiations• Donation from Landlord• Lease signed January
Problems
• Managing architects and contractors difficult• Keeping them on site and working to schedule• Understanding the VAT position• The budget far exceeded the original £30,000
grant (£53,000)• Time• Work ability of our residents• Amount of staff time used
Solutions• Able to move an unspent budget from
another Emmaus project into the Coventry budget (£15,000)
• Negotiated with the landlord who donated £8000 towards non structural items
• Negotiated good prices with contactors (floor coverings throughout £2,800)
• Kept contractors on schedule – saying late delivery would prevent access to funds to pay
What have we achieved
Where Are We Now?
• Staff flat occupied• First four residents moved in• Temporary HIMO licence granted• Still some decorating and superficial works to
complete• Despite the short time frame works will
completed on time and on schedule
Highs and lows
• One large property• Relationship with
landlord• Relationship with local
authority• Able to meet our 5 year
expansion plan• Committed staff team• Negotiation skills
• Delay in initial funding decision
• Time to find property• Getting information on
VAT issue• Expectations on what
can be achieved with limited funding
• Time frame, staff have worked tirelessly to complete