EVM for CNGS. Definitions Pre-requisites Application to CNGS. Definitions. EVM : E arned V alue M anagement -> Measure amount of work performed -> Estimate total costs and duration. PV Planned Value. EV Earned Value. AC Actual Cost. BC Budget at complete. Schedule Variance - PowerPoint PPT Presentation

transcript

CNGS Review15 July 2003

M. Meddahi 1

EVM for CNGS

• Definitions

• Pre-requisites

• Application to CNGS

CNGS Review15 July 2003

M. Meddahi 2

Definitions

EVM: Earned Value Management-> Measure amount of work performed-> Estimate total costs and duration

PVPlanned Value

EVEarned Value

ACActual Cost

Schedule Variance

SV = EV-PV

Cost VarianceCV = EV-AC

BCBudget at complete

CNGS Review15 July 2003

M. Meddahi 3

time

Money

PV

Today

AC

EV

Cost variance

Schedule variance

CNGS Review15 July 2003

M. Meddahi 4

EVM at CERN

- EVM for LHC- Much work done for implementing EVM for LHC- CNGS decided to also apply this management tool- Autumn 2002 started to implement EVM for CNGS

CNGS Review15 July 2003

M. Meddahi 5

Pre-requisites

Work BreakdownStructure

ProjectProgressTracking

Data collectionfrom project

engineers

CNGS Review15 July 2003

M. Meddahi 6

Work Breakdown Structure

CNGS Review15 July 2003

M. Meddahi 7

WBS layers

CNGS Review15 July 2003

M. Meddahi 8

Data collection

CNGS Review15 July 2003

M. Meddahi 9

PPT: Project progress tracking

• EVM project baseline frozen 9 May 2003

• 1st phase of utilisation and learning for the users:Project engineers are getting used to the system and the reporting.Analysing the results obtained from the EVM tools and proposing correcting actions.

CNGS Review15 July 2003

M. Meddahi 10

CNGS Review15 July 2003

M. Meddahi 11

Status of Work Units

CNGS Review15 July 2003

M. Meddahi 12

Work unit reporting

CNGS Review15 July 2003

M. Meddahi 13

Staff plan

CNGS Review15 July 2003

M. Meddahi 14

Planned cash Flow

CNGS Review15 July 2003

M. Meddahi 15

EVM summaries: an example

Proton Beam dump

WindowsShieldingHelium tubes

Target station

ShutterHadron Stop

CNGS Review15 July 2003

M. Meddahi 16

Summary

Organised the CNGS tasks in a Work Breakdown Structure

Defined the Work Units required to complete the project(313 Work Units for CNGS)

EVM CNGS baseline frozen on 9 May 2003

Earned Value Management applied to CNGS- Work is in progress- Monitoring of the project’s progress started (one report per month requested)