drawing number:
CD 4-1
project number:16010project:Canola Exhibit
drawing: date: 26 OCT 2016
Canola Exhibit – Concept Design
EXHIBIT PLAN
CAFM CANOLA EXHIBITExhibit PlanScale 1:100
drawing number:
CD 4-2
project number:16010project:Canola Exhibit
drawing: date: 26 OCT 2016
Canola Exhibit – Concept Design
3D MODEL STUDY
drawing number:
CD 4-3
project number:16010project:Canola Exhibit
drawing: date: 26 OCT 2016
Canola Exhibit – Concept Design
3D MODEL STUDY
drawing number:
CD 4-4
project number:16010project:Canola Exhibit
drawing: date: 26 OCT 2016
Canola Exhibit – Concept Design
3D MODEL STUDY
drawing number:
CD 4-5
project number:16010project:Canola Exhibit
drawing: date: 26 OCT 2016
Canola Exhibit – Concept Design
3D MODEL STUDY
drawing number:
CD 3-6
project number:16010project:Canola Exhibit
drawing:
Canola Exhibit – Concept Design
date: 19 OCT 2016
• GothamFonts• Friendly,sophisticated,easytoread,accessible• SupportsEnglishandFrench
CANOLA EXHIBIT HEADING
ABCDEFGHIJKLMNOPQRSTVWXYZabcdefghijklmnopqrstuvwxyzàâçéèêëïîôùûü0123456789
Canola exhibit body text
ABCDEFGHIJKLMNOPQRSTVWXYZabcdefghijklmnopqrstuvwxyzàâçéèêëïîôùûü0123456789
TYPOGRAPHY
drawing number:
CD 4-7
project number:16010project:Canola Exhibit
drawing: date: 26 OCT 2016
Canola Exhibit – Concept Design
SCHEDULE
Reich+Petch Exhibits | Canada Agriculture & Food Museum | Canadian Science & Technology Museums Corporation
W - Workshop | M - Meeting | P - Presentation | S - Shop - Site Review
MAR APR MAY JUNE
3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30
Task Description: 20175.0 Production & Fabrication
5.1 Pre-Production
Procurement Planning & Scheduling
AV Development Planning
Shop Drawings/Samples
5.2 Fabrication
Carpentry
CNC Cutting
Specialty Work
Painting
Lighting Integration
AV & Interactive Integration
5.3 Graphic
Printing, Lamination
5.4 AV/Interactives & Mechanicals
Mock-up & Prototypes
Hardware Integration
Testing
6.0 Installation & Commissioning
Packing and Delivery
Exhibit Installation
Electrical Work
Graphic Installation
Artifacts
A/V & Interactive Set-up & Testing
Touch Ups
Cleaning
6.1 Project Turnover
Deficiencies (Reviews & Corrections)
CAFM Staff Training
Maintenance & Operating Manuals
7.0 Opening
8.0 Post-opening (July 17 - June 18)
SEPT OCT NOV DEC JAN FEB MAR APR
2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14Task Description: 2016 2017
1.0 Conceptual Design
Kick-Off Meeting
Tour Gallery Space & Collection
Receive Background Material
Design Workshop WDevelop Concept M M M MUpdate Interpretive Outline
Costing
Present Concept Design PCAFM & Review Approval
2.0 Preliminary Design
Design Workshop W Develop Preliminary Design M M MDevelop Interpretive Plan
Sample Text
Update Costing
Present Preliminary Design PCAFM Review & Approval
3.0 Detailed Design/Final Content
Design Workshop WDevelop Detailed Design M M M M MFinal Text (by CAFM)
Update Project Schedule
Final Project Costing
Develop Exhibit Prototypes
Prototype Testing SPresent Detailed Design & Schedule PCAFM Review & Approval
4.0 Graphic Production Files
Edit Final Text
Graphic Production Files
Project Schedule | Canola: Long Term Exhibition | September 28th, 2016