Federal AviationAdministrationData Communications
Implementation Team (DCIT)
Data CommunicationsImplementation Team (DCIT)
DCIT #31 PLENARYDCL Trials Update3/13/2014
Matt MakiDCL Trials Lead
Federal AviationAdministration
DTAP Build 7.1 Schedule Update• Build 7.1 Limited Climb Via SID Compliance:
- Interim Build with KEWR focus- UM169 CVS UL when MAINT ALT Set to NONE- National 7110.65 CVS ATC Implementation set for April 3- Trials will seek EWR/MEM CVS DTAP waiver thru May 15- EWR ATC FAT Input Planned
• Build 7.1 Estimated Schedule:- April 14-15: FAT at Thales- April 16: Install at FAATC- April 17-25: Testing at FAATC- April 28 - May1: Install and SAT at MEM and EWR (Parallel
installs)
Federal AviationAdministration
DTAP Build 7.2 Schedule Update
• Build 7.2 Full Climb Via SID Compliance:- Compliance with full 7110.65 CVS Changes- CVS, CVS Except Maintain, Maintain ALT Selections- Longer WJHTC lab testing period expected due to CVS scale
• Build 7.2 Estimated Schedule:- June 11-12: B7.2 FAT at Thales- June 13: Install at FAATC- June 16 - July 3: Testing at FAATC- July 7-10: Install and SAT at MEM and EWR (Parallel
installs)
Federal AviationAdministration
KEWR DCL Trials Status Update
• UAL, FDX MD11/B777 Daily Ops Ongoing:- Open OPR reports diminishing- UAL FRC DCL Filing Error Reductions- Resuming of UAL B767 ops expected next month+
• UPS Starts Daily MD11/B767 Ops March 15:- Approx. 24 Ops/week expected
• AFS-50/400/2P Approval letter to UK CAA pending:- BAW, SAS, DLH CAA Approval letters back to FAA pending- BAW approval expected first
Federal AviationAdministration
KEWR DCL Trials Status Update
• NetJets Trials Participation at KEWR:- NetJets confirmed interest in participating- Kick off Telcon set for March 19 with AOC and Pilot Reps- Bombardier Global Express 5000/6000 aircraft FANS equipped- Bombardier Challenger 350 FANS/VDL2 upgrades expected in
July- 1-2 DCL flights/week from KEWR expected
• March 1-4 ZNY 72 HR ERAM Testing Complete:- Test was successful- Next 72 HR ERAM run expected April 5-8
Federal AviationAdministration
Federal AviationAdministration
KMEM DCL Trials Update• DTAP Running Stable:
- Unplanned Recons minimized – 1 event since last DCIT- Server 1, 2 Re-starts On-going (Tues/Fri)- DTAP Processing 20-40 FDX DCL ops per push- Route Revisions remain minimal/none in #s
• MEM ATC confirms use of CVS phraseology:- Planned CVS waiver will include MEM
Federal AviationAdministration
DCL Ops Advantages During Upcoming SWAP Season