Final Project Materials Certification

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

1

Final Project Materials Certification

• The Materials Acceptance and Certification system is designed around the requirements for Final Project Materials Certification

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

2

Final Project Materials Certification

• PA Role–PA role in MAC versus PA’s responsibilities

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

3

Final Project Materials Certification

• PA Role can be assigned to the PA’s delegate

• SCO defines the delegate more stringently than was permitted in LIMS

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

4

Final Project Materials Certification

• VT Technician• DMRO personnel

• Others

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

• Contract Specialist

• Head Inspector• Asphalt VT ONLY and/or RAS

• NO OTHERS

5

Final Project Materials Certification

•Sample Life Cycle–PA role is responsible for comparison packages and triggering Resolution

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

6

Final Project Materials Certification

• Sample Life Cycle–Checklists•Asphalt•Soils•Structural Concrete

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

7

Final Project Materials Certification

• Sample Finalization Checklists

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

8

Final Project Materials Certification

• Basic Contract Concepts–Method of Measurement–Basis of Payment• Final Estimates

–Method of Acceptance• State Materials Office

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

9

Final Project Materials Certification

• Method of acceptance is from the contract documents

• JGS is a guide of the contract requirements

• When there is a contradiction, contract rules

• JGS is just a report

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

10

Final Project Materials Certification

•MAC has two types of JGS–Standard JGS–Non‐standard JGS

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

11

Final Project Materials Certification

•Standard JGS–Let date logic–Project Specific requirements

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

12

Final Project Materials Certification

• Back to Method of Acceptance – only project specific requirements that change the standard method of acceptance

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

13

Final Project Materials Certification

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

14

Final Project Materials Certification

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

15

Final Project Materials Certification

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

16

Final Project Materials Certification

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

17

Final Project Materials Certification

•Non‐Standard JGS–Created by QC data entry for•LS/DB/LAP On‐system

–Reviewed by PA

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

18

Final Project Materials Certification

•Non‐Standard JGS–Let Date Logic–Project Specific Requirements

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

19

Final Project Materials Certification

• JGS–If it’s not on the JGS, you can’t log in a sample!!!

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

20

Final Project Materials Certification

• Samples are being taken and processed• PA is tracking sample status• PA is finalizing samples and building comparison packages as the samples progress

• What does all this have to do with MC Review?

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

21

Final Project Materials Certification

•MAC sends conditions to the MC Review process•These conditions are known as issues

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

22

Final Project Materials Certification

• Automatic finding & Manual Findings (MAR Issues)–MC Reviewer needs to initiate review when project begins–Based on MC Exceptions•What is an MC Exception?

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

23

Final Project Materials Certification

• Exception 1 = Material Acceptance–Failing Test Results–Missing Reports

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

24

Final Project Materials Certification

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

25

Final Project Materials Certification

• Exception 2 = Minimum Frequency–Required tests not performed–Required Comparison not performed

–Required Resolution not performed–Not enough samples

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

26

Final Project Materials Certification

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

27

Final Project Materials Certification

• Exception Category 3 = Qualifications–Technicians–Laboratories–Production Facilities•Manual Findings

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

28

Final Project Materials Certification

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

29

Final Project Materials Certification

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

30

Final Project Materials Certification

• Straightedge Deficiencies• Materials that allow Delineation

– These two automatic findings trigger specific functionality with the MAR process that you will not get when creating a manual finding

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

31

Final Project Materials Certification

• Straightedge Deficiencies– Has a different flow with different roles based on CPAM Chapter 11

– Resident Engineer instead of PA– District Bituminous Engineer instead District Materials and Research Engineer

– Recommendation is Final Resolution

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

32

Final Project Materials Certification

• Materials that allow Delineation– Has the same flow with the same roles as other MARs except for Straightedge

– The difference is the option for No EAR –Delineation will not show up for a manual finding

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

33

Final Project Materials Certification

•MC Review in MAC–Responding to Findings–Initiating MAR

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

34

Final Project Materials Certification

MOA

•Issues with MOA?

•Conditional flags

•Manual findings

Is it an issue?

•MC Reviewer determines if the finding warrants further attention. 

• If yes = submit issue for PA response

•If no = exclude ‐DONE

Submitted issues

•PA responds to issue

•Make a comment about the issue

•Background information on what triggered the flag (condition)

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

35

Final Project Materials Certification

MC Review and PA determine if issue needs more action

• If yes, promoted to MAR

• If no, excluded from MAR ‐ DONE

PA determines the severity of the issue

• Can it be solved by standard methods?

• If yes ‐ DONE

Is material so bad it needs to be removed and replaced?

• First – determine if EAR or No EAR*

• Second – enter final resolution

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

36

Final Project Materials Certification

•What is MAR?•When is it used?

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

37

Final Project Materials Certification

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

38

Final Project Materials Certification

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

39

Final Project Materials Certification

•What is the difference between a recommendation and a resolution?

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

40

Final Project Materials Certification

•There are 7 recommendations•5 are also final resolutions that can be made by the PA

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

41

Final Project Materials Certification

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

42

Final Project Materials Certification

• If EAR or No EAR is selected,  2nd process is needed to determine final resolution–Or No EAR Delineation if the Specification allows resolution by delineation

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

43

Final Project Materials Certification

•Resolution options:

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

44

Final Project Materials Certification

•Resolution options:

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

45

Final Project Materials Certification

•Location Information–PA fills it out–After the resolution

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

46

Final Project Materials Certification

• PA needs to ensure the location information is correct and complete

• For Complete Removal and Replacement & Leave in Place – one set of entries

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

47

Final Project Materials Certification

• PA needs to ensure the location information is correct and complete

• For Partial Removal and Replacement, enter sub‐locations for material that was removed and material that was replaced

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

48

Project Administrators and MAC

• MC Reviewer will notify PA if additional information is needed for location information

• This gets used on the PMCL so it needs to be right

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

49

Final Project Materials Certification

•What about DDM/EAR•We don’t do it that way…–P.S.  Not all MAR issues will result in an exception, but most will

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

50

Final Project Materials Certification

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

51

Final Project Materials Certification

•MC Review•PMCL

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

52

Final Project Materials Certification

•Questions?

Florida Department ofFlorida Department of

TRANSPORTATIONTRANSPORTATION

53

0

20

40

60

80

100

2003 03/04 04/05 05/06 06/07 07/18 08/09 09/10 10/11 11/12 12/13 13/14 14/15 15/16

Day

s

Years

Certification Program PerformanceHistoric

(since delegating process to Districts)

Overall Process Time Response Time

GOOD

16‐Day Goal

54

Reduced Pay per Decision

1%

Reduced Pay per Spec‐

3%

Reduced Pay per Spec+

16%

Full Pay per Spec (100%)

11%

Full Pay per Spec+ (Bonus)

68%

Material Acceptance for Asphaltfrom July 1, 2015 to June 30, 2016

Based on an Estimated 4.7M Tons of Asphalt and 

367 Projects

55