GTM Marine LNG Terminal -Part 1.pdf

Post on 13-Apr-2015

38 views 3 download

transcript

2

Arhangelsk

Severodvinsk

Indiga

Naryan-Mar

Murmansk

Design area

3

4

Location options

Hydrometeorologicalconditions

Navigational-graphiccondition

Geological conditions

Closeness to large settlements with

developed infrastructure

Closeness to gas field

Total sum of areas

Maximum point possible 50 50 50 10 20 180

Cape Mikulkin area 20 50 25 1 2 98

Cape BolshoyRumyanichny area 35 45 25 8 18 131

Cape Chaichy area 50 40 25 9 19 143

Cape Svyatoy nos area(Cape Zhelezny) 50 15 25 10 20 120

5

Marine LNG Terminal

Site for LNG Plant Location

6

Marine LNG Terminal

Site for LNG Plant Location

7

Marine LNG Terminal

Site for LNG Plant Location

8

Options of terminal location

Length of access

channel

Dredging volume

Length of connecting

dam

Length of breakwater №1

Length of breakwater №2

Volume of rock and

stone filling

Length of cryogenicpipeline

m mln. m3 m m m mln. m3 m

B.Rumyanichnycape area 660 1,845 520

1010 490

2,628 2200

Chaichy cape area 1250 1,762 1750 3,226 3200

Zhelezny cape (Svyatoy noscape) area

12120 24,123 750 2,256 3300

9

10

1

1

6

5 4 7

2

345

6 2

3

4

5

6

7

Construction period Operation period

Fencing facility #1

Inside maneuvering basin

Fencing facility #2

Fencing facility #2

Fencing facility #1

Legend

Complex LNG transshipmentBase for maintenance of SH fleet

Complex transshipment of construction cargo

General port objectsCargo-and-passenger jetty

Explication of Jetty front facilities

Jetty for LNG unloading

Jetty for large-size and heavy-weight cargo

Jetty for multipurpose cargo

Cargo-and-passenger jetty

Jetty for transshipment of OSR aids and SNOAnd temporary icebreaker location

Jetty for SH fleet

Jetty for bunkering tanker