Healthcare Testimonial: Blessing Hospital
Jerry Melching and Lee Elledge, Blessing Hospital
Mark Steinmetz, Ameren Illinois Energy Efficiency Program
July 13th, 2016
Blessing Health System Energy Team
2
• Craig Kurk
• Lee Elledge
• Joe Vermiere
• Jerry Melching Left to right in picture
Blessing Hospital
• Quincy Illinois
• 752,000 sq. ft. facility
• 307 bed facility
• Multiple buildings
• Multiple design and energy uses
• Energy intensive facility and daily operation
Getting Started…
4
• Why we decided to participate in the Energy Efficiency
projects……
• Roadblocks….
• “Corporate Approval”…..
• First steps in the program….
Project Summary – Program Years 1 - 9
• Total Ameren Illinois Energy Efficiency Projects - 30
• Standard Lighting Projects – 15
• Standard HVAC Projects – 4
• Standard VFD Projects – 2
• Custom Projects – 4
• Large Facility Retro Commissioning Projects – 1
• Other supportive Projects* - 4
• * = Staffing Grant, Feasibility Study, Metering and Monitoring and SEM participation.
Annual Energy Savings
6
3,783,631 annual kWhs saved
312,314 annual Therms saved
$ 358,000.00 annual energy costs reduced / avoided
Comparison
• Equivalent to annual greenhouse gas emissions from:
• 889 Passenger Vehicles
• 1,015,514 Miles driven per year
• 1,527 Tons of Waste
• 9918 Barrels of Oil Consumed
• Reduction of Metric tons of CO gas emissions
• approximately 4,256
Ameren Illinois Energy Efficiency Program participation has….
• Increased awareness of energy savings opportunities
• i.e. Lighting, HVAC and Variable Frequency Drives and
etc.
• Incentive dollars have assisted to secure corporate support
and approval for projects
• Increased performance, equipment life and lowered
maintenance costs
• Stronger understanding of energy use and ways to manage
that use
• Assisted in a cultural energy development with employees
Large Facility Retro Commissioning participation
• A Registered Service Provider to perform an facility assessment
• Identify several items with 0 -1 year payback that needed
attention, but often overlooked due to daily tasks and staffing
needs.
• Identify and qualified energy efficient large capital projects for
future development
• Increased Energy Star rating from a 38 to 62 compared for
similar buildings based upon energy use per square foot
Going forward
On-Going Efforts…
• Increased energy team participants for broader perspective input
and project identification
• Encourage employee and patient participation
• Encourage and support satellite and affiliate facilities to engage in
energy efficiency projects and savings
• Expand energy efficient cultural change and awareness
throughout the Blessing Health System
• Continue to identify and pursue energy efficiency projects
Ameren Illinois and Blessing Health System
Ameren Illinois Energy Efficiency
and
The Blessing Health System
13
Partnering together to deliver efficient healthcare services to their
customers and the communities that they serve.
Large Facility Retro Commissioning Program
14
• Incentives available to identify energy efficiency opportunities
• 0 -1 year payback opportunities
• 1 – 10 year payback opportunities
• Eligibility
• Ameren Illinois Electric or Gas Customer
• Minimum 100,000 square feet facility
• Existing Energy Management Control System
• 5 years old
• Pre-approval is required
Large Facility Retro-Commissioning Incentives
15
• 70% of Survey Cost for duel energy source customers
• 40% of Survey Cost for single energy source customer
• Customers qualify by implementing 0-1 year payback items to
meet established minimum energy savings goal
• Implementation Incentive
• $0.02 per annual kWh saved
• $0.30 per annual Therm saved
Bonus for submitting custom project application up to 12 months from
completing Retro-Commissioning project.
Large Facility RCx Program
Contact information:
Mark Steinmetz – Large Facility RCx Lead
Email – mark.Steinmetz@gdsassociates.com
Phone – (217) 670-9606
17
Energy Advisors
1. Chad Whitehead 309.620.6333 chad.whitehead@gdsassociates.com
2. Steve Smith 309.212.5831 Steven.L.Smith@leidos.com
3. Rod Rhoads 217.649.8897 rod.rhoads@gdsassociates.com
4. Mark Steinmetz 217.670.9606 mark.steinmetz@gdsassociates.com
5. John Strode 309.370.0062 john.strode@gdsassociates.com
6. Fred Joshu 309.433.4316 Fred.M.Joshu@leidos.com
7. Larry Erwin 309.838.2340 Lawrence.F.Erwin@leidos.com
Resources
Website: ActOnEnergy.com/Business
Phone: 1.866.800.0747
Fax: 1.309.677.7950
Email: ActOnEnergyBusiness@Ameren.com
Contact Information - Blessing Hospital
19
Jerry Melching
Project Specialist
(217) 223-8400 ext. 4468
Jerry.melching@blessinghealthsystem.org
Lee Elledge,
System control specialist
(217) 223-8400 ext. 6708
Lee.elledge@blessinghealthsystem.org
Questions?