Hospital of the FutureConstruction Update as of Dec. 3, 2010

Hospital of the Future

West side of the building.

Hospital of the Future

View of brick work from Springfield Street.

Hospital of the Future

Green Roof (install spring 2011).

Hospital of the Future

Basement boiler started early Nov. to provide temporary heat during construction.

Hospital of the Future

Basement air handler unit started in early Dec. for temporary heat during construction.

Hospital of the Future

Endovascular procedure rooms support steel duct installation ongoing.

Hospital of the Future

Endovascular procedure room coordination complete, released for fabrication.

Endovascular procedure room coordination (each room = 200 hours of configuration).

Hospital of the Future

2nd Floor: CARE area drywall underway.

Hospital of the Future

3rd Floor: Rough-in complete; drywall underway.

2011

Facility Milestones to Come:

•Finished ceilings begin. •Exterior landscaping begins. •Final painting begins.•Phase 1 construction complete.

2012

NEW PATIENT AREAS OPEN!