Post on 16-Apr-2015
description
transcript
1
Integrated Project DeliveryGetting Under the Hood
2
Does Project Delivery Matter?
3
Is Normal Normal?(or Dysfunctional)
4
If You Could Start from a Clean Slate…
5
An IPD Example:SMC Castro Valley
6
Overview @ 70% Completion
• Expected Cost $255 Mill ion• Authorized Cost $225 Million• 30% Schedule Compression (and 6 weeks
ahead)• $5.8 Million Contingency (only $2.2 used)• 26 Owner Originated Changes (<1%)• 333 RFIs (Normal 3,000)• Intense Use of BIM• Full Budgeted Profit• No Compromises to Program
7
Performance Metrics
• Scope Installed EXACTLY as Modeled– Mechanical 99%– Plumbing 99%– Electrical 71%– Framing 79%
• Rework baseline actual
– Mechanical 7% 0.5%– Plumbing 10% 0.5%– Electrical 10% 8.5%– Framing 5% 0.5%
8
Productivity Improvements
Baseline Planned Actual ProjectedMechanical 100% 105% 116% 120%Plumbing 100% 100% 107% 110%Electrical 100% 114% 105% 107%Framing 100% 122% 120% 121%
9
Note: Baseline productivity based on contractors’ own historic productivity on similar projects.
10
IPD Structure
Microstructure
11
Macrostructure
12
13
Multiparty Integrated Agreement
14
15
IPD: A Closer Look
Compensation Goals
• Fair Return for Efforts• Opportunity for Increase Profitability• Align Interests of Parties• Stimulate Creativity and Effort• Reduce Waste• Buffer Cost Overruns• Transparency and Accountability
16
Compensation Principles
• Profit based on Group Outcome– Project– Subgroup
• Profit and Cost Separated– No incentive to increase work– No disincentive to moving work to best capable– Fixed Fee on Variable Costs
• Transparent Costs– Accountable and Auditable
• Profit at Risk Sufficient to Buffer Overruns17
The Art of Compensation
• Amount At-Risk• Metrics for Increasing/Decreasing
– Shared Savings Percentage• Targets
– When Should They Be Set– Benchmarking and Validation
• Cashflow• Buffering
18
19
Compensation Design
20
2 Party Milestone Distributions
21
Multi-variable Risk/Reward
22
Multi-variable Risk/Reward
23
Milestone Distribution Matrix
24
• Percentage of Profit Distributed at Milestones• If Preconditions Met• Distribution Percentages Vary Between Team
Members• Portion of Profit Held to Final Distribution
Other Quantitative Factors
• Schedule• Safety
– Lost days– Reportable Accidents
• Plan Percent Complete• RFI/Change Order Reduction• Energy Performance
25
Qualitative Factors
• Project Quality– Index Projects– 3rd Party Review
• Team Self-Reviews• Owner Satisfaction• Added Value List
26
Changes to Target Cost (HB)
• No Change Orders, Except– Owner Elected Changes (changed scope)– Owner Directives (unilateral changes)– Differing Site Conditions– Changes in Laws and Regulations– Owner’s Suspension or Termination
27
Project Decision Flow(HB/C191)
28
Waiver or Limitation?
• No claim unless exception to waiver
• No insurance for waived claims*
• No litigation for waived claims.
• Claims allowed, but damages limited
• Insurance for claims because not waived
• Litigation to enforce claims likely
29
Waiver of Claims Liability Limitation
* Some waivers have exception forinsured claims. (AIA C-191, some HB)
Liability Waivers (HB)
• Waiver of ALL Liability Among IPD Parties, Except:*– Willful Default– Warranty Claims– Project Performance– Allocation of Third Party Claims– Owner Directives– Non-payment by Owner– Termination or Suspension Costs– Indemnification Obligations– Failure to Procure Required Insurance– Insured Claims?*All projects have custom negotiated provisions that may differ from this description.
30
Insurance Developments
• Most IPD Projects use Traditional Insurance Products– Contractor/Trades should have Contractor’s
Professional Liability• A few multi-insurer integrated programs
– MaineGeneral• Integrated Policies being developed
31
32
IPD Teams
IPD Groups
• Committee– Small– Deciding, not Doing
• Group– Any size– Limited Synergies
• Team– Interactive– Synergistic– Creative
33
Advantages of Teams
• Creativity• Knowledge• Decision Accuracy• Engagement• Alignment and Coordination
34
Teams Can Be Worse!
• Overhead• Communication Complexity• Groupthink• Groupshift• Social Loafing• Bystander (Genovese) effect
35
Team Composition
• Skills– Technical Expertise– Problem Solving/Decision Skills– Interpersonal Skills
• Diversity– Experience & Knowledge– Creative Tension
• Size (5-9)– Small = efficient = 4 or 5– Large = creative <=12– Smallest team necessary
• Personality– Collaboration (1/3 not collaborative)– Command and Control– Firm Culture
36
Team Organization
• Cross-Functional Teams– Interdisciplinary– Systems or Areas
• Discrete Whole– Cost, Scope and ? Responsibility
• Design, Construction, Cost, Schedule, Commissioning
• Duration– R&D Teams 4 year peak– Package work to teams, not teams to work
• Teams within Teams• External or Internal Coordination
37
Team Management
• Bootcamp– Trust– Interpersonal Skills– Management (Lean) Skills
• Physical Proximity (Co-location)– Trust– Velocity of Communication– Quality of Communication– Break from Individual Corporate Cultures
• Visual Management• Decision Making• Coordination• Mentoring
– Scope– Interpersonal Skills/Disputes
• Specific Goals
38
Agile and Scrum
• Cross-functional teams• Self-Organizing teams
– No leader– Daily Scrum– Mentor (scrum master)
• Time-Boxing (sprints)• Face to Face Communication• Simplicity-the Art of Maximizing the Amount of
Work NOT done.• Continuous Attention to Technical Excellence• Regular attention to continuous improvement
39
Motivation is Largely Within
• Pay for Performance may be Detrimental– Pay inequities are detrimental
• Work Structure– Whole and Identifiable Task– Freedom and Autonomy– Adequate Resources– Positive Purpose– Challenge– Imposed or Selected Goals
• Authentic Leadership– Competent, ethical, and compassionate
40
Creativity
• 3 Component Model– Expertise– Creative Thinking Skills– Inherent Interest
• Diversity• Open Communication• Moderate Conflict
– Task and Process, but never Personal• Active Mood• Moderate Challenge
41
42
IPD Projects
43
44
45
46
47
48
49
50
51
54
55
56
57
IPD Resources
58
• IPD: A Working Definition (AIACC, 2007)• IPD: A Guide (AIA/AIACC, 2008)• Negotiating an IPD Agreement (Hanson Bridgett, 2011)• IPD Case Studies (AIA/AIACC, 2010)• IPD Case Studies (AIA 2011)• Managing Integrated Project Delivery (CMAA, 2010)• IPD For Public and Private Owners (NAFSA, COAA,
APPA, AIA, AGC, 2010)• Comparison of IPD Agreements (Hanson Bridgett, 2010)• IFOA Executive Summary (Hanson Bridgett, 2010)• Project Alliancing Practitioner’s Guide (Government of
Victoria , 2006)
www.hansonbridgett.com/practices_industries/IPD_BIM.php
59
www.ipd-ca.net
www.aia.org/ipd
www.consensusdocs.org
www.leanconstruction.org
www.bimforum.org
www.hansonbridgett.com
IPD Resources
60