Implementation of waste and water infrastructure projects financed by EU in Lithuania
Dainius KazlauskasENVIRONMENTAL PROJECTS MANAGEMENT AGENCYUNDER THE MINISTRY OF ENVIRONMENT OF THE REPUBLIC OF LITHUANIA
1 December 2011, Vilnius
ADMINISTRATION SCHEME OF EU 2007-2013 PERIOD STRUCTURAL FUNDS IN LITHUANIA
Government of the Republic of LithuaniaConfirms legislations, composes monitoring committee
Government of the Republic of LithuaniaConfirms legislations, composes monitoring committee European CommissionEuropean Commission
MINISTRY OF ENVIROONMENT
Preparation of regulations, plans and implements
tools, charts list of environmental projects, financed from Cohesion
fund
MINISTRY OF ENVIROONMENT
Preparation of regulations, plans and implements
tools, charts list of environmental projects, financed from Cohesion
fund
Monitoring Committee for Operational ProgrammsAnalyses progress and submits
proposals
Monitoring Committee for Operational ProgrammsAnalyses progress and submits
proposals
Managing Committee for Operational Programmes
Analyses problems of planning and implementation
Managing Committee for Operational Programmes
Analyses problems of planning and implementation
MINISTRY OF FINANCES Coordinating Institution (coordinate EU
support planning and usage, strategy, implementation of management strategy)
Managing Authority (administrates operational program, response for it’s
implementation) Certifying Authority (confirms and send
expenditure report to EC) Paying Authority (manages finance
accounting)
MINISTRY OF FINANCES Coordinating Institution (coordinate EU
support planning and usage, strategy, implementation of management strategy)
Managing Authority (administrates operational program, response for it’s
implementation) Certifying Authority (confirms and send
expenditure report to EC) Paying Authority (manages finance
accounting)
Audit Authority
State Control
REGIONAL DEVELOPMENT
COUNCILS
REGIONAL DEVELOPMENT
COUNCILSPublic procurement office Public procurement office
Implementing agency
Environmental projects management agency:
• Established in February 2002 by the Ministry of Environment of the Republic of Lithuania;
• Staff – 82 Employees;• Implementing environmental projects, financed by: ISPA fund; Single Programming Document for 2004-2006; Cohesion fund for period 2004-2006; Structural assistance2007-2013 period; LIFE +.
Responsibilities
• Organization of invitation to submit applications for EU finansation;
• Evaluation of applications;
• Signature of administrational and finansation agreement;
• Preservation of public procurement procedures;
• Physical and financial administration of project implementation;
• Un-spot checks;
• Audit after project implementation.
Support from EU in Environment sector
• Instrument for Structural Policies for Pre-Accession (ISPA) (now part of IPA)/Cohesion fund;
Lithuania implements / implemented 11 projects in waste and 16 in water sectors financed by the Cohesion Fund and ISPA.
• EU 2007-2013 Cohesion Promotion Operational Program;
Lithuania implements 29 projects in waste and 143 in water sectors (including sludge management projects) financed by EU 2007-2013 Cohesion fund.
EU 2007-2013 cohesion promotion operational program. Environment and sustainable development
I. Renovation and development of water supply and waste water treatment
Modernization and development of water supply and waste water treatment infrastructure according to EU environmental requirements. Development of sludge treatment infrastructure.
II. Establishment and development of waste treatment system
• No land filling will take place in non-complying landfills after 16 July 2009; • Landfill Directive (1999/31/EC) (for Lithuania) requires phased reduction in the total quantity of biodegradable municipal waste sent to landfills (a reduction to 75% of 2000 levels by 2010, to 50% by 2013, and to 35% by 2020).
7
Wastewater treatment changes in 2000-2009 period,mln of m3 (discharge to surface waters)
0
20
40
60
80
100
120
140
160
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009
in complience with standarts Treated but not in complience with standarts Not treated
8
Water sector investments, mln. EU
2000-2006:-planed financing sources:Cohesion fund - 85 %; LT budget-15 %,
beneficiary-0 %;-real financing sources:Cohesion fund-64,9 %; LT budget-30,1
%, beneficiary-5 %;2007-2013:-planning financing sources:Cohesion fund-85 %; LT budget-10 %,
beneficiary-5 % (plus net income).
0
100
200
300
400
500
600
700
800
EU funds LT budget Beneficiary Total
2000-2006 2007-2013
9
Drinking water supply and waste-water treatment strategy on 2008-2015
Criterion of strategic objective in 2015:
•Availability to get public drinking water and discharge waste water to collecting systems 95 % in 2015.
0 20 40 60 80 100
2007
2015
Waste-water discharge to collecting systems availabilityPublic supplied drinking water availability
10
Financing directions, mln. EU
0
100
200
300
400
500
600
W&WWnetworks
WWT plants WT plants SST plants Total
2000-20062007-2013
11
What we have done or will do?
Period WW networks, km WS networks, km UWWTP Ren./rec.
units
WTP (Ren./rec.
units
SST plants
new Ren./rec. new Ren./rec.
2000-2006 795 89 601 140 47 17 0
2007-2013 871 23 595 25 37 6 23
Total 1666 112 1196 165 84 23 23
211 mln EUR
9 mln EUR37 mln EUR
EU funds
LTU Budget
Beneficiary
Waste sector investments
• Total investment 2000-2006 financing period – 190 mln EUR;
• Total investment 2007-2013 financing period – 257 mln EUR;
Waste management till 2004
• 790 dumpsites;
• 60 municipal landfills;
Waste management 2011• 11 landfills;
• 69 bulky waste sites;
• 13 composting sites;
• 11 MBT plants.
Lithuanian perspective 2013
Regional waste management system
• Geographically waste management systems
covers county area;
• In the year 2002-2004 10 regional waste
management centers (RWMC) were
established;
• RWMC acts on status of JSC or Public
organization;
• The percent of finances part in RWMC is
proportional to municipalities size;
• RWMC is managed by managing board, that consist of representatives from municipalities (1 member from 1 municipality).
2000-2006 2007-2013
Projects grouping
Procurements Centralized (Agency) Decentralized (Beneficiaries ormunicipalities staff, but under
control of Agency)
Financingagreementsigned
European commission-Agency-
Beneficiaries
Agency-Beneficiary
Number of projects
27 172
2000-2004 Project’s timetable
Total – 7 years
Submission of
application to EC
Signature of financing agreement
Design phase
Procurement phase
Execution of works
Finalization
2001 2002 2004 2005 2008
Main challenges in EU 2000-2006 financing periodDesign stage:
•In the very beginning of a project no concrete places for project component was foreseen, long territorial planning, future environmental damage prevention procedures;
•Local designers had no experience in landfill and WWP design procedures, international designers – no experience and understanding in local low and rules;
•Confrontation from local inhabitants;
•Long procurement procedures regarding PRAG requirements;
•Lac of experience in all levels (municipal staff, beneficiaries).
Due to all these reasons design face took more the 3 years, and it was high risk do not fulfill N+2 rule.
Construction stage:
•Long procurement procedures regarding National procurement low requirements;
•Lak of money due to the high construction work costs (period 2006-2007);
•Construction contracts were based on FIDIC rules, that was new for all Contract sides;
•Contracts were sign from 3 sides (Final Beneficieries, Contractor and Contracting Authority). It programmed some disagreements in contract management;
•Lac of experience in technical supervisor and Final Beneficieries staff;
•Mistakes in design project that caused a lot off changes during execution of construction works.
Main challenges in EU 2000-2006 financing period
Finalization stage:
•Bad quality of feasibility studies, applications;
• Too detail specification of physical indicators;
• Implementation of projects indicators (connection rates, increase waste collection level and etc.);
• Mistakes in technical projects;
• Suggested Financial corrections from state control: EU visibility requirements; Variation orders; Public procurement procedures.
•Different interpretation of the same situation, changes of human resources in all levels;
•Preparation and approval of final report.
Main challenges in EU 2000-2006 financing period
Main challenges in EU 2007-2013 financing periodProject preparation stage:
• Late approval of legal acts regarding EU 2007-2013 funds management;
• Low quality of applications;
• Low quality of technical projects;
• In the very beginning of a project implementation, no concrete places for project component was foreseen, long territorial planning, future environmental damage prevention procedures;
• Confrontation from local inhabitants;
• Procurement procedures were not provided till submission of application.
Main challenges in EU 2007-2013 financing periodProject implementation stage:
• Low quality of tender documentation:Agency had prepared the typical tender documentation for works, supplies and services procedures; Recommendations for preparation of tender documentation for MBT facilities;Involvement of international experts;
• Long procurement procedures: Agency is using selection methodology for procurement procedures control;The methodology of adopting financial corrections was approved by Ministry of Environment;
Main challenges in EU 2007-2013 financing periodProject implementation stage:
• To high or to low construction costs:The methodology of additional financing scemes was approved by the Ministry of Environment;
•Court cases regarding public procurement procedures.
•Complicated and slow implementation of projects: Agency is using selection methodology for payment application control;The methodology of adopting financial corrections was approved by the order of the Ministry of Environment;Usage of IT systems for submitting and confirmation of payments applications.
Lessons learned
2004-2006 period planning weakness:
Long time to make decisions in any changes of project;Lack of responsibility of beneficiary and local authority;Large-scale project cause high qualification requirements (less suppliers);Lack of urban planning documents and property deeds;Overloaded design companies;Lack of money to finish projects due to increased mconstruction works cost.
2007-2013 period planning :
Projects managing become more flexible;Shorten project implementation;Direct responsibility for beneficiaries;Grow up the number of qualified suppliers;Unfortunately, grow up litigation on procurement stage;But, the cost of construction works stabilized.
Lessons learned