Post on 28-Mar-2015
transcript
1.0 INTRODUCTION OF COST OVERRUN
The problem of cost overrun, especially in the construction industry, is a worldwide
phenomenon, and its effects are normally a source of friction between owners especially
government owners, project managers, and contractors in terms of project cost variation
subsequent to the owner’s decision to build. Although, in theory, it might be expected that
cost overruns have the same probability of occurring as cost underruns, cost overruns have a
much higher frequency
Project success can be defined as meeting goals and objectives as prescribed in the
project plan. A successful project means that the project has accomplished its technical
performance, maintained its schedule, and remained within budgetary costs. Project
management tools and techniques play an important role in the effective management of a
project. Therefore, a good project management lies in the management tools and techniques
used to manage the project. Project management involves managing the resources—workers,
machines, money, materials and methods used. Some projects are effectively and efficiently
managed while others are mismanaged, incurring much delay and cost overruns
2.0 DEFINITION
2.2.1 COST
According to LONGMAN Dictionary of Contemporary English (2003), cost is
defined as the amount of money that you have to pay in order to buy, do, or produce
something.
2.2.2 COST OVERRUN
Basically, cost overrun is defined as actual budget is more than the planning budget.
More than that, it is an unexpected cost incurred in excess of a budgeted amount due to an
under-estimation of the actual cost during budgeting.
3.0 OBJECTIVE OF THE PROJECT
The main objective of this study is to understand the practices of construction cost
management in various construction projects in Malaysia.
4.0 SUMMARY OF THE PROJECT
In construction works, cost always becomes the ‘X-factor’ in deciding the quality of
the works done. However, eventhough the budget of the work is extremely high, but without
a proper project management, the project won’t succeed too. A construction works normally
consist of various workers and equipments, so it need a well organize team to handle all of
these property as well as to ensure the project achieved the goal set up by the owner.
This project mainly focused on to understand the practices of construction cost
managements in various projects in Malaysia. For this task, our group chose only one site
study but we interviewed two different persons with different construction background.
Firstly we interviewed a senior Quantity Surveyor from UTHM with 27 years old
experienced in construction as our representative from owners and the second one is a sub-
contractor with 30 years old experienced in construction as representative of contractors. We
took UTHM new mosque and as our case study. There are some reasons of choosing that
particular building. One of it due to the delay of the finishing time as well as lead to the cost
overruns. With the budget of almost RM30 million, it is very important to have a good cost
management technique to ensure the project achieved its objective.
5.0 BACKGROUND OF THE PROJECT
Actual works on site
Actual works on site
Actual works on site
Model of the mosque
Model of the mosque
6.0
7.0 RESULT AND DISCUSSION
For this section, we interviewed two different people with different construction
background. The reason for conducted two different interviewed is to get the opinions from
various views. The interviewed was conducted with a senior quantity surveyor and a sub-
contractor. The senior quantity surveyor talked for behalf of owners and contract and the sub-
contractor talked behalf of contractors. There are five scale used in the questionnaire.
Below are the scale used in the questionnaire:-
1. Extremely significant (100%)
2. Very significant (75%)
3. Moderately significant (50%)
4. Slightly significant (25%)
5. Not significant (0%)
1 2 3 4 5
Ordinal Scale One To Five In Ascending Order
Respondent A (Senior quantity surveyor, behalf of client)
From 59 questions, she chose 9 questions as the main factors of cost overrun. They
are as listed below:
i. Poor contract management
ii. Frequent design changes
iii. Poor design and delays in design
iv. Mistakes and error in design
v. Change in scope of the project
vi. Owner interference
vii. Additional works
viii. Inaccurate quantity take-off
ix. Lack of experience of technical consultants
Most of these factors lay in contract management issues. Besides that, she also
mentions that this project which is UTHM mosque trapped in this kind of problems due to
interference of the owner. In general, if too much interference comes from the outsider,
obviously it will bring bad effects to the constructions.
At the same time, she also said that a contractor, once they won the tender, they must
work their best to ensure the project run smoothly. No matter how the won the tender, but the
must important thing is do the job seriously. If the management failed, delayed will followed
and this will lead to cost overrun.
Besides that, she also indicated the important of having a good design. If the design
keep changing, this not only brings difficulties to all parties but surely it will add an extra
cost to the budget.
Respondent B (sub-contractor, behalf of contractor)
8.0 RECOMMENDATIONS AND SUGGESTIONS
In construction, cost always played a great influence. Without a properly cost
management, a construction surely wont be successful. Therefore, there should always be
adequate contingency allowance in order to cover increase in material cost due to inflation.
At the same time, long life learning must also be adapted in both contractors and
workers. They must be familiar with the project management techniques and process. By
doing so, it will lead to effective and efficient performances.
9.0 CONCLUSSION
Cost and construction are always link together. Without a proper cost planning, a
construction will surely get a huge problem. In addition, project planning also played a great
role in deciding the quality of the construction. A good project planning will able to minimize
any unwanted things that might lead to cost overrun .
The most commonly used explanations for cost overruns found in literature are
economical rational behavior, strategic behavior, optimism bias, structure of
the organization, relation between actors and values of actors and their relation to the
environment. The explanations can be grouped in four different categories: technical,
economical, psychological, and political explanations.
10.0 REFERENCES
Surihartati Murni Lestari Sutekno, Senior Quantity Surveyor UTHM, 15 March 2011
Che ku Din bin Che Ku……., Sub-contractor , 19 March 2011
Yaw Frimpong, Jacob Oluwoye, Lynn Crawford (2003),
Causes of delay and cost overruns in construction of groundwater projects in a developing
countries; Ghana as a case study. International Journal of Project Management. 21 : 321–32
Jin-Kyung Lee (2008),
Cost Overrun and Cause in Korean Social Overhead Capital
Projects: Roads, Rails, Airports, And Ports, Journal Of Urban Planning And Development ©
ASCE.pp 59-62
Chantal C. Cantarelli, Bent Flyvbjerg, Bert van Wee, and Eric J. E. Molin
Cost overruns in large-scale transportation infrastructure projects:Which explanations can be
given?
LONGMAN Dictionary of Contemporary English 7th edition (2003).Pearson Education
Limited