Post on 25-Jan-2017
transcript
Industry information day 21.05.2015
1
INDUSTRY INFORMATION DAYAssembly & Installation
Laurent SchmiederBuildings Infrastructure and Power Supplies
Project Leader21st May 2015
Industry information day 21.05.2015
2
1. What is the BIPS scope and organization
2. Procurement status
3. Schedule
4. Status of the works
5. Status of the works in 2017
Summary
Industry information day 21.05.2015
Overview of the scope for Buildings
Reinforced Concrete Buildings 250 000 m3 of concrete (including 190 000 m3 for Nuclear buildings) 21 000 m2 footprint 750 000 m3 building volumeSteel Frame Buildings 29 000 m2 footprintPower supplies (HV, MV, and LV distribution) Detailed design, installation and commissioning Procurement of the emergency generators, the cables, and 25% of the SSEN
equipment Current arrangement: the remainder of the equipment are procured by other
Domestic agencies (China and US)Site infrastructures (Galleries, trenches, roads, bridges fences)
•ITER : 180 ha with 39 buildings and areas on the 40 ha platform
3
Buildings program is 1.5 Billions of Investments
Industry information day 21.05.2015
4
Overview of the ITER Buildings
Industry information day 21.05.2015 5
Organization – Buildings contracts management
BIPS PTIO/F4E
Support to the OwnerEnerghia / Tiresia
Internal and ExternalExperts
Health and Safety Coordination
Legal Inspection
Architect Engineer
Tender Batch 04Omega
OW
NER
FIDIC Engineer
IMPL
EMEN
TATI
ON
Tender Batch 03Vinci Ferrovial Razel
Tender Batch 05. 06. 07Ferrovial
FIDIC Engineer
250 staff
270 staff -> 800 200 staff -> 800 50 staff -> 200
Industry information day 21.05.2015
PROCUREMENT STATUS
6
Industry information day 21.05.2015
7
1 B€ of construction contracts on-goingTB
07C
ooling Towers -15 M
€
TB03 & TB04 Tokamak Complex & Assembly Hall• TB03 : 300M€• TB04 : 500M€TB02 Long Lead – Mechanical Handling: 32M€
TB05 Magnet Power Conversion & Reactive Power Control buildings - 25 M€
TB06
H
igh
Volta
ge E
lect
rical
Equ
ipm
ent -
38
M€
Industry information day 21.05.2015
8
Remaining procurement packages
TB12
N
B b
uild
ings
• TB16: Site infrastructures• TB11: Completion works
TB09 & TB10 Hot Cell complex
TB13 Emergency Power Supplies
Industry information day 21.05.2015
SCHEDULE
10
Industry information day 21.05.2015
11
Buildings Ready for Equipment (RFE dates)
Earliest RFE (B61, Q4 2016) latest RFE (Hot Cell Facilities, Q1 2022)
RFE 1A, Apr 2017
RFE 1B, Feb 2018
RFE 1C, Jul 2019
Industry information day 21.05.2015
WORKSITE STATUS
12
Industry information day 21.05.2015 13
CURRENT STATUS OF ITER worksite
Industry information day 21.05.2015
14
Reminder: TB 03 – Civil worksScope of Supply: 295M€
Tokamak Complex (buildings 11, 14 & 74) Assembly Hall (13), Cleaning Facility (17), RF Heating (15) Cryoplant Compressor (51-52), Resistors (75), Site Services (61),
Control Building (71)
Works duration
Number of workers
2014 to 2019
~ 800
11
13
71
61
14
74
17
75
15
51
52
Industry information day 21.05.2015
15
TB03 – Work progress•Concrete pouring of the walls on the first level (B2) of the Tokamak
B14 – Tritium Building :
- Walls execution is progressing.
- The reinforcement for the last external wall is already in place.
Industry information day 21.05.2015
16
TB03 – Work progress
Pouring of the pillars of the Diagnostic Building (B74) completed
Reinforcement work for the bio-shield ongoing Reinforcement of columns started. First external wall ready to be poured
Industry information day 21.05.2015
17
TB03 – Work progress•Mock-up
Industry information day 21.05.2015
18
TB03 – Work progress•Assembly building
Objective: Ready for crane rails installation : 20 October 2015
The steel frame of the Assembly Hall building is starting to take shape with the fourth level sections of the massive columns being erected in the east facade and west facade has started the erection of the 2nd level.
Preparatory works for the assembly of the roof on the floor are ongoing.
The roof will be lifted in one piece once assembled.
Industry information day 21.05.2015
19
TB03 – Work progress•B61 – Sites services Building
Objective: Building Water tight: 16 October 2015
Backfilling on going Earthwork foundation pilling until June Slab : Summer 2015 Steel structure : Until October
Industry information day 21.05.2015
TB04 – Tokamak Complex / HVAC – 3D views Design progress
Industry information day 21.05.2015
WORKSITE STATUS IN 2017
21
Industry information day 21.05.2015
22
Worksite status in 2017
Industry information day 21.05.2015
Thank you for your attention
23