Levy Nuclear Plant Overview of Water Issues Presented by Jamie Hunter to the FDEP – Central...

Post on 18-Jan-2016

215 views 0 download

Tags:

transcript

Levy Nuclear PlantOverview of Water Issues

Presented by Jamie Hunter

to the

FDEP – Central District’s

13th Annual Power Generation Conference

Lake Buena Vista, FLJuly 2009

Progress Energy Florida Service Area

Counties shown in green are wholly or partially served by PEF

Levy Nuclear Plant Site Location

Levy Aerial

Levy Site Layout(Expanded View)

Levy Aerial View (Looking West)

Artist Conceptual View

AP1000 Standard Plant Configuration

Major State/Local Permits & Approvals

Levy Co. Land Use/ Zoning/ Comp. Plan Obtained Required Approvals in Sept. 2008

Florida PSC Need Determination Affirmative Determination issued August 2008

Florida Power Plant Site Certification Expect Siting Board Approval in August 2009

Major Federal Permits & Approvals

FDEP PSD Air Construction Permit Obtained Final Permit in February 2008

FDEP NPDES Water Permit Expect Final Permit in Late 2009

Army Corps of Engineers 404/10 Permit Expect Final Permit in Late 2010

NRC Combined Operating License Expect Final License in Late 2011

Levy Nuclear Plant – Air Emissions

Particulate Drift from Cooling Towers

Emergency Diesel Generators/Pumps

Avoided CO2 Emissions – Over 14 Million Tons per Year vs. Coal Over 6 Million Tons per Year vs. Natural Gas

CO2 Emission Factors – Various Fuels

Nuclear Life-Cycle CO2 Emissions

Annual Air Emissions Comparison

Cooling Water Needs/Supply

Low Profile Closed-Cycle Cooling Towers will be Used – Reduces Cooling Water needs by ~95%

Over 99% of the Project’s Water Needs are for Steam Condenser Cooling Requirements

Cooling Tower Makeup Water Needs are ~122 MGD

Source:

Cross Florida Barge Canal

CT Blowdown of ~82 MGD

Discharge Location:

Crystal River Energy Complex

CFBC at Inglis Lock – Looking West

CFBC at Inglis Lock – Looking East

Cross Florida Barge Canal (Looking West)

Intake

Levy Cooling Water Intake at CFBC

Levy Make-Up Pipeline Route

Levy Blowdown Pipeline Route

Crystal River Site Discharge Canal

Freshwater Needs/Source

Project Requires Freshwater for: Process Boiler Water/Steam Makeup

Process Equipment Cooling System

Potable Water for Drinking/Sanitary

Fire Suppression Systems

Freshwater Quantity Needed is 1.58 MGD

Freshwater Source is Groundwater from Floridan Aquifer via Onsite Wells

Groundwater Well Locations/Drawdown

Groundwater Wells/ Wetland Overlay

Wetland Impacts/Mitigation

Project Property Contains a Significant Amount of Wetlands

Project Site Design/Layout Planned to Avoid/Minimize Wetland Impacts

Total Project Impacts (Plant/Transmission) Currently >400 UMAM Credits

Much of the Mitigation Proposed to occur Onsite, with additional Offsite as Needed

Wetlands Total/ Wetlands Impacted

Water Summary

>95% Reduction in Overall Water Needs with the Use of Cooling Towers

>99% of Project Water Needs Met by Use of Salt Water for Steam Condenser

Cooling

Minimal Aquifer and Wetland Impacts from Groundwater Withdrawals

Wetland Impacts Minimized and Unavoidable Impacts Fully Mitigated

An Update of What’s Behind the News