MLPL/NEPRA/05/16 5th August, 2016

The Registrar National Electric Power Regulatory Authority

Subject: Application for a GENERATION License

I, Syed Mohsin Raza Naqvi, being the duly authorized representative of Maple Leaf Power Limited by virtue of Board Resolution dated 2'd June 2016, hereby apply to the National Electric Power Regulatory Authority for the grant of a Generation License to Maple Leaf Power Limited pursuant to section 15 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997.

I certify that the documents-in-support attached with this application are prepared and submitted in conformity with the provisions of the National Electric Power Regulatory Authority Licensing (Application and Modification Procedure) Regulations, 1999, and undertake to abide by the terms and provisions of the above-said regulations.

I further undertake and confirm that the information provided in the attached documents-in-support is true and correct to the best of my knowledge and belief. A pay order in the sum of Rupees 1,824 (One Thousand Eight Hundred and Twenty Four Rupees Only), being the differential nonrefundable license application fee calculated in accordance with Schedule II to the National Electric Power Regulatory Authority Licensing (Application and Modification Procedure) Regulations, 1999, is also attached herewith.

Signature

Maple Leaf Power Limited

42-Lawrence Road, Lahore, (Pakistan)

Tel: 92-042-36302261 & 36302262

Fax: 92-042-36368721

PROSEPECTUS

Maple Leaf Power Limited

Introduction:

Maple Leaf Power Limited (MLPL) is a wholly owned subsidiary of Maple Leaf Cement Factory

Limited (MLCF) having head office at 42 Lawrence Road Lahore. MLPL is setting up a 40 MW

Coal Fired Power Plant at Iskandarabad district Mianwali. Major equipment of the

aforementioned plant is being purchased from 'Sinoma Energy Conservations' which is a

Chinese organization with market presence in over 70 countries.

The total project cost is expected to be around 5.5 billion rupees. The plant is expected to

operate throughout the year owing to the ample coal supply from international as well as local

markets and steady electricity demand from end consumer i.e. Maple Leaf Cement Factory

Limited.

Salient Features of Coal Fired Power Plant:

Project Location Iskanderabad near daud khel dist. Mianwali

Rated Power Generation Capacity : 40 MW

Fuel Imported Coal

Proposed Covered Area 36,000 m2 approximately

Construction Period 17 months

Source of water 4 wells at 0.5 km distance from Indus River

Source of power Self-generated electricity from power plant

Air pollution abatement Installation of ESP, bag

house filters and desulfurizer Type of waste water Power Plant waste water

Waste water treatment Power plant waste water shall be recirculated

42-Lawrence Road,

Lahore, (Pakistan) Tel: 92-042-36302261

& 36302262 Fax: 92-042-36368721 Maple Leaf Power Limited

Solid waste management Ash recovered from power plant shall be used in

the cement factory

Proposed Investment:

The expected cost of the Coal Fired Power Plant is 5.5 billion rupees which is being financed by

the holding company

Social and Environmental Impact:

Social and environmental impacts relating to this project have been anticipated and the keys

impacts are as follows;

• Construction noise

■ Solid waste

■ Soil contamination

• Air pollution

■ Community and workers' safety

■ Employment conflicts

Since the project has been commenced on a reserved area and no human settlements exist

within 2 km of the selected site, construction related impact is not expected to extend to the

community.