Mechanical Lined Pipe - Installation by Reel-Lay Wacek … asia 2011 presentation subsea… ·...

Post on 18-Jul-2018

224 views 2 download

transcript

Mechanical Lined Pipe - Installation by Reel-Lay

Wacek LipskiWacek LipskiDiscipline Manager

The New Subsea7

Description of BuBiR

Mechanical Lined Pipe

Overview of Reel Lay Installation method

Development programme

Agenda

Development programme

Installation methodology

Current StatusCurrent Status

2Page 10.01.11

O bOur new beginning

A combination of Acergy and Subsea 7, two very strong subsea companies that have come together to create a subsea companies, that have come together to create a global leader in seabed-to-surface engineering, construction and services.

10.01.11 3Page

S b h d f lSubsea 7 Methods of Pipelay

S-layS-lay

Reeling

J-lay

10.01.11 4Page

CDTM

S b & ddl l C b lSubsea 7 –Asia & Middle East Pipelay Capability

S-lay & J-lay of pipelines in Asia & Middle East is through our Joint Venture Company SapuraAcergy and the Sapura 3000:Joint Venture Company, SapuraAcergy and the Sapura 3000:

– 240 Tonnes S-lay– 400 Tonnes J-lay– First deep water project in Malaysia (S-lay) – Murphy Kikeh– Work ongoing on second deep water project (S-lay and J-

lay) Shell Gumusut Kakaplay), Shell Gumusut Kakap

10.01.11 5Page

Driver

BuBiR

Mechanical Lined Pipe is a BuBi Mechanical Lined Pipe is a cost effective solution where CRA materials are required

Proven track record for S-lay, J-lay and CDTM

Extending the applicability to Extending the applicability to Reeling will have a positive impact on the economic viability of some ff h d l t j toffshore development projects

10.01.11 6Page

Driver

Item No.Production Material

Pipeline DetailsLinepipe price

OD WT

1 22Cr 10" 14.3mm 1.75

2 13Cr 10" 12.7mm 1.5

3 Lined 316L 10" 12.7mm + 3mm liner 1.0

4 Lined 825 10" 12 7mm + 3mm liner 2.254 Lined 825 10 12.7mm + 3mm liner 2.25

5 Clad 316L 10" 11.8mm + 3mm clad 2.25

3 56 Clad 825 10" 11.8mm + 3mm clad 3.5

Material price comparison based on 20 miles length.

10.01.11 7Page

f R h l dDescription of BuBiR Mechanical Lined Pipe

• Carbon Steel outer pipe with a Corrosion with a Corrosion Resistant Alloy liner

• Assembled by Hydraulic process

Carbon Steel Outer PipeCarbon Steel Outer Pipe

Cladding(Alloy 625 typ )

50mmNom 3mm liner

(Alloy 625 typ.)

10.01.11 8Page

f R h l dDescription of BuBiR Mechanical Lined Pipe

Material options

Carbon Steel Rp 0.2 [MPa] Rm [MPa]API X52 360 460API X60 415 520API X65 450 535API X70 485 570

Cladding Rp 0.2 [MPa] Rm [MPa]

Example of material options

2.4858 / 825 240 500 - 7002.4856 / 625 276 690 - 8901.4539 / 904L 220 520 - 7201.4404 / 316L 220 520 - 6701.4404 / 316L 220 520 670

10.01.11 9Page

Description of Mechanical Lined PipeDescription of Mechanical Lined Pipe

• Pipe Sizes and wall thickness options.

10.01.11 10Page

Construction Process for BuBi PipeR

Construction Process for BuBi Pipe

10.01.11 11Page

blAssembly Process

0 10 1

Hydraulic expansion press (Schäferpresse)

32

10.01.11 12Page

Hydraulic expansion press (Schäferpresse)

l llReel Lay Installation

Port Isobel Spool Base – Gulf of Mexico

10.01.11 14Page

lDevelopment Programme

Objective:

Demonstrate that installation by Reel Lay will not wrinkle the pipe or have an unacceptable impact on the mechanical or corrosion resistance properties required for its intended corrosion resistance properties required for its intended service.

Phase 1

Test a – Simulated reeling trials of pipes without internal pressure.

Test b – Simulated reeling trials of pipes with internal pressure

10i Di X65 t i 15 09 + 3 All 825 li

10.01.11 15Page

10ins.Dia, X65 outer pipe15.09 + 3mm Alloy 825 liner

lTest a – No internal pressure

FE Analysis - wrinkle prediction performed on pipe with no internal pressure internal pressure.

10.01.11 16Page

lDevelopment Programme

Simulated reeling test rig.Bend Radius 7.5 mtrs.

10.01.11 17Page

Herriot Watt University Scotland.

lTest a – No Internal Pressure

Wrinkles recorded in line with FE Analysis.y

10.01.11 18Page

b h lTest b – With internal pressure

FE Analysis - wrinkle prediction performed on pipe with i l internal pressure

10.01.11 19Page

No wrinkles measured

h l h 2Further Development – Phase 2

• Testing of different pipe sizes & liner materials

• Demonstration for low fatigue applications

• Enhanced FEA

10.01.11 20Page

f d ff & l lTesting of different pipe sizes & liner materials

Phase 2

2010 Scope ( completed)

Simulated Reeling trials with internal pressure

8 ins dia. X65,Alloy 625 & 316l (no girth weld)

Depressurisation Test

Fatigue Testing – Strip & Full scale

DNV Qualification – DNV RP – A203

10.01.11 21Page

f d ff & l lTesting of different pipe sizes & liner materials

Depressurisation Test

10.01.11 22Page

h d

BUBI PIPE STAGES SHOWING MECHANICAL GRIP FROM 30 BAR PRESSURE DURING REELING

Enhanced FEArb

on s

teel

liner

Car

Li C iShot blasted carbon steel

Liner inserted

6mmgap

Liner expansion at

1200 bar

Coating at 240°C

~ 40µ gap

30 bar for

Reeling

10.01.11 23Page

Start Telescoped Hydroformed Coated Installation

Pipeline Inspection 2000 readings every 20mm along the pipePipeline Inspection – 2000 readings every 20mm along the pipe

Bore measurements taken to record any change during o/a process and provide inputs to FE model.

On Manufacture at ButtingOn Manufacture at Butting

Prior to simulated reeling

Following Simulated reeling

Post fatigue testing

10.01.11 24Page

Fatigue Testing Strip TestFatigue Testing – Strip Test

40M cycles and no failure at

60MPa on 2 post reeled sample. 60MPa on 2 post reeled sample.

10.01.11 25Page

ll S lFatigue Testing – Full Scale Resonance Test

Fatigue test was taken to a stress/no. of cycles as per the DNV 30.2 F1 Curve

Stress range, MPa Design life (F1), cycles Target life (F1), cycles180 85,740 293,424120 289,372 990,30760 2 314 975 7 922 45860 2,314,975 7,922,458

All samples showed no defects which could be attributed to the fatigue testing

NDE (AUT X d D P t t t ti ) d S ti i f d t fi i t it

10.01.11 26Page

NDE (AUT, X-ray and Dye Penetrant testing) and Sectioning was performed to confirm integrity of the clad weld to liner interface

TestingTesting

Dye- penetrant testing to check for defects on linerDye- penetrant testing to check for defects on liner

longitudinal, overlay and Girth welds.

X-ray of longitudinal, seam and girth welds.

Tensile test of both materials.

Charpy V notched impact tests at -30oC on the carbon steel

Hardness testing on X65 and the Alloy 625

Metallographic examination of the seal weld area

G48 Corrosion tests carried out at 50oC on Alloy 625 linerG48 Corrosion tests carried out at 50oC, on Alloy 625 liner

G28 Intergranular corrosion (Method A)

10.01.11 27Page

ll h d lInstallation Methodology

Key objective:

Maintaining internal pressure

during the stalk reeling onto

the vessel and installation.

10.01.11 28Page

Installation Methodology

PIG

MANIFOLD

Pig End Cap

END CAP

TIE IN SHED

10.01.11 29Page

Installation Methodology

PIG

MANIFOLD

END CAPEND CAP

TIE IN SHED

10.01.11 30Page

Installation Methodology

PIG

MANIFOLD

END CAPEND CAP

TIE IN SHED

10.01.11 31Page

Installation Methodology

PIG

MANIFOLD

END CAPEND CAP

TIE IN SHED

Key procedures:Straightening TrialsOffshore tie – ins

10.01.11 32Page

Offshore tie insOffshore Emergency Abandonment

hHigh Friction Pig Tests

The tests performed to date demonstrated

that the high friction pig could be pumped

into position and located accurately to the

desired position in the pipeline.

Leak proof at 4 bar differential pressure Leak proof at 4 bar differential pressure –

(tested over 12 hrs).

Consistent launch, running & reversal

pressures recorded.p

10.01.11 33Page

S fSafety

Risk assessment performed using the Shell software FRED (Fire, Release, E l i d Di i ) Explosion and Dispersion).

All l ithi 10 f th l ith d k l l t h i ht h ld

10.01.11 34Page

All personnel within 10m of the reel, either deck level or at height, should wear normal suitable eye protection and safety clothing.

Q l fDnV Qualification

10.01.11 35Page

l S 20Development Scope 2011

Reeling Trials on 12 ins. X65 with Alloy 625 liner.

Reeling Trials on 8ins X65 with 316l linerReeling Trials on 8ins. X65 with 316l liner

Full Scale fatigue testing on 8ins. X65 with Alloy 625 liner.Full Scale fatigue testing on 8ins. X65 with Alloy 625 liner.

Reeling Trials on 12 ins. X80 with Alloy 625 liner.

10.01.11 36Page

S l G á d lPre Salt - Guará and Lula

Submerged Buoy

70+ km of BuBi Mechanical Lined Pipe to be installed in approx. 2100 mtrs. Water depth

10.01.11 37Page

C lConclusions

• Tests to date demonstrate no Tests to date demonstrate no wrinkling occurs when reeling is performed with internal pressurepressure.

• Installation of mechanical • Installation of mechanical lined pipe by Reel Lay is achievable, safe and will offer significant economic significant economic advantages.

• DNV QualifiedQ

• First project awarded

10.01.11 38Page

p j