JAIPUR METRO

1

2

JAIPUR METRO PHASE - I

Corridor- I

Corridor-II

Sitapura to Ambabadi(North – South)

Route Length (km.)

Elevated 18.004

UnderGround 5.095

Total 23.099

Number of Stations

Elevated 15

UnderGround 5

Total 20

Completion Cost (Rs. In crores)

Without Taxes & Escalation

3481

With Taxes & Escalation

4624

Ridership (PHPDT)

2014 11300

2021 18200

2031 27000

Mansarovar to BadiChaupar (East -

West)

9.439

2.628

12.067

8

3

11

2194

2907

10000

20200

34100

Total

21.03

7.88

28.91

21

8

29

5675

7531

21300

38400

61100

As per Revised DPRPHPDT- Peak Hour Peak Direction Trips3

INTRODUCTION

PHASE I

North-South(15.5 kilometers)

East-West (13.5 kilometers)

Totaling nearly 30 Kilometers, will be laid across the city atan estimated cost of Rs 8,000 crores.,

The East-West corridor will be from Ramganj to Mansarover,.

A nine-km elevated track connecting Chandpole toMansarover be the first to be completed

The North-South corridor will connect Sanganer to Panipech

4

NEED OF METRO SYSTEMPopulation growth rate of Jaipur is double the

average growth rate of other cities.

Significant reduction in environmental pollution.

Development of Delhi-Mumbai Industrial Corridor,

SEZ, International hub for Gem & Jewellery &

increasing tourist inflow will put additional burden

on transportation need.

5

ADVANTAGE OF METRO SYSTEM

Metro systems are superior to other modes because

they provide higher carrying capacity, faster,

smoother and safer travel, occupy less space, are

non-polluting and energy-efficient.

Causes no air pollution in the city.

Causes lesser noise level.

Reduces journey time by anything between 50%

and 75% depending on road conditions.6

READY MIX CONCRETEReady-mix concrete is a type of concrete is manufactured in

a factory or batching plant.

TRANSIT MIXTURE

The cylindrical portion is continuously rotating.

The rotation speed of cylindrical portion is 0-14 rpm.

7

TRANSIT MIXTURE 8

GRADE OF CONCRETE IN CONSTRUCTION

Piles - M 35

Pile cap - M 35

Piers – M 50

All precast element for station- M 45

Crash Barrier - M-35

Cantilever piers arm- M 55

9

BOOM PLACER

10

CONSTRUCTION STEPSPile Foundation

Pile Cap

Pier/Column

Pier Arm or Cross Arm

Track Level

11

CONSTRUCTION

12

PILE FOUNDATION STEPSETTING OUT

DRIVING OF TEMPORARY CASING

BORING

REINFORCEMENT CAGE LOWERING

FLUSHING OPERATION

CONCRETING

13

PILE FOUNDATION

14

PILLING MACHINE

15

PILE CAPA pile cap is a thick Concrete mat that rests on concrete

or timber piles that have been driven into soft or unstable ground to provide a suitable stable foundation.

16

PIERGrade of Concrete M- 50

The Diameter of Pier is 2000 mm from Ground level to Concourse level and from Concourse level it is 1600 mm.

17

PIER

18

CRASH BARRIER

It is constructed around the pier to avoid the direct impact on the pier in case of accident. The thickness of crash barrier is225mm and consist 25mm cover. The height of crash barrier is 165mm.The grade of concrete use in crash barrier construction is M-35.

19

DRAINAGE

The drainage pipe is used for drain the rain water fromtrack level.

The diameter of drainage pipe is 200mm.

For the drain of water a drain hole is also construct inthe crash barrier.

20

21

CANTILEVER PIER ARMA pier is consist 2 pier arms at Concourse level.

M -55 grade concrete is used.

The size of one arm is 10230 mm from center of the pier.

The depth of pier arm at near to the pier is 2250 mm and at end point is 1650 mm.

22

CANTILEVER PIER ARM

23

10230 mm

1650 mm

PRECAST GIRDERThey are precast at casting yard or on site.

The girders are placed on the corbel.

The sizes of girders are 350 mm X 1200 mm.

Grade of concrete is M-50.

24

PRECAST GIRDER

25

PRECAST SLABThe dimensions of precast slab are 165 mm X 1000 mm.

The concrete grade is M-35.

The slabs and girders are jointed each other by arc weldedconnection.

26

LAUNCHING OF PRECAST GIRDER

HYDRA DEMAG HC-400” is used to launching orErect the Precast Slabs and Precast Girders onPier Arms.

Firstly Hydra must be stand on hydraulic jack.

The capacity of this crane is about 150KN.

The Capacity of Hydra is Depend on its Boom Length.

27

HYDRA DEMAG HC-400

28

PROBLEM AT SITE

Allowing free flow of vehicular traffic on the already congested along with chosen alignment.

Paucity availability of Land.

Existence of charted and uncharted utilities.

Problems to pedestrian.

Problems to existing residents.

Environmental Impact including noise and vibration etc. 29

SAFETYSafety is very important thing for any kind of

construction.

The safety is for workers as well as for public also.

The safety belts, helmets and Safety shoe is used,without these things, the entry to the site isprohibited.

30

SAFETY HELMETS & SHOES

31

DMRC

ENGINEERELECTRICIAN

SAFETY LABOUR

SHOES BELTS

CONCLUSION

Such types of construction actually is very difficult.reduce the traffic volume, travelling time .

Summer Training is a golden opportunity for learning and self development and really experiencing the real scenario of the company environment. It helped me to increase my technical skills. It is also helped me to be with latest and new technologies.

32

Jaipur

Metro