A City of Edmonton graphic outlining predicted traffic delays associated with the opening of the new Metro LRT Line to NAIT.

transcript

KINGSWAY

105 STREET

106 STREET

104 STREET

Attachment 1: Duration of Traffic Impacts

105 AVENUE

106 AVENUE

107 AVENUE

111 AVENUE

PRINCESS ELIZABETH AVENUE

4 MINUTES (Traffic Signals Red)

4 MINUTES (Traffic Signals Red)

2 MINUTES (Traffic Signals Red)

2 MINUTES (Traffic Signals Red)

2 MINUTES (Traffic Signals Red)

12 to 16 minute wait time at peak hours. 3 to 4 signal cycles.

12 to 16 minute wait time at peak hours. 3 to 4 signal cycles.

2 to 4 minute wait time at peak hours. 1 to 2 signal cycles.

2 to 4 minute wait time at peak hours. 1 to 2 signal cycles.

2 to 4 minute wait time at peak hours. 1 to 2 signal cycles.