Mid-City Exposition Light Rail Transit Project

Pre-Proposal ConferenceAugust 14, 2006

Phase 2 Engineering & Environmental Consultant Services (RFP#5-06)

Exposition Corridor Light Rail Transit Project

Mid-City Exposition Light Rail Transit Project

8.6 miles of Light Rail

1.3 miles Shared with Metro Blue Line

10 stations, 3 with Park and Ride Lots

42,000 Daily Riders in 2030

Completion – Summer 2010

Estimated Cost - $640 million

Phase 1 Description

Mid-City Exposition Light Rail Transit Project Phase 1 Alignment

Mid-City Exposition Light Rail Transit Project

• FTA Record of Decision received on February 27, 2006.

• Awarded the Project’s DB contract and issued NTP for Design to commence on March 30, 2006.

Phase 1 Status

Mid-City Exposition Light Rail Transit Project

Funding Plan

• Federal CMAQ - $15.6 million• Local Prop C 25% Funds - $24.9 million• City of LA - $35 million• State TCRP - $249.8 million• State STIP funds - $314.7 million

• Total - $640 million

Mid-City Exposition Light Rail Transit Project

Recent Activities• Approved MOU between Authority and Metro

• Held several Community meetings along the

corridor to provide status on the Project's design

and construction

• Co-Located Authority staff and Design Builder

(D/B) at 707 Wilshire Blvd. Project Office

• Commenced real estate activities

Mid-City Exposition Light Rail Transit Project

Ongoing Events

• Design Development and Final Design – March 2006 through June 2007.

• Official Groundbreaking - September 2006• Initial Construction – Flower Street improvements

and utility relocation started in August

• Major Construction Underway in February 2007

Mid-City Exposition Light Rail Transit Project Transit Parkway

Mid-City Exposition Light Rail Transit Project Typical Station

Mid-City Exposition Light Rail Transit Project Downtown LA Segment

Mid-City Exposition Light Rail Transit Project USC/Expo Park Segment

Undercrossing

Extends for 2,300 feet5-foot safety retaining wallOptional at-grade station near Trousdale Circle

Mid-City Exposition Light Rail Transit Project Optional Station

Optional Station at USC/Expo Park (Trousdale)

Mid-City Exposition Light Rail Transit Project La Brea Station

Mid-City Exposition Light Rail Transit Project La Cienega Station

Conceptual view of station(looking north on La Cienega)

Mid-City Exposition Light Rail Transit Project

National Blvd.

Jefferso

BallonaCreekSyd Kronenthal Park

Bikeway

LRT bridge structure

La CienegaPlace

Existing Sidewalk to Remain

Ballona Creek/Jefferson Bridge

Mid-City Exposition Light Rail Transit Project

National Blvd.

Was

hington

Blvd

.

Platform At Grade

Wes

ley

St.

Metro Right Of Way bikeway

Washington/National Interim Terminus Station

Mid-City Exposition Light Rail Transit Project

National Blvd

Helms Ave

Wesley St

Washington Blvd

Venice Blvd

I-10

Aerial Station Site

Future Venice/Robertson Station

Mid-City Exposition Light Rail Transit Project

Design Apr 2006 – Jun 2007

Utility Relocation Aug 2006 – Dec 2007

Major Construction Feb 2007 – Feb 2010

Startup and Testing Feb 2010 – May 2010

Revenue Service June 2010

Phase 1 Schedule

Mid-City Exposition Light Rail Transit Project

Culver CityCulver City

Santa MonicaSanta Monica

Phase 2 Extension

Mid-City Exposition Light Rail Transit Project

Phase 1 to Culver City - 8.6 miles

Phase 2 to Santa Monica- 6-7 miles*

Total 14.5-15.5 miles

*Route is one mile longer via Venice/Sepulveda alternative routing.

Phase 2 Length

Mid-City Exposition Light Rail Transit Project

ROW Acquisition 1990-1991

Initial Feasibility Studies 1992-1993

Major Investment Study 1999-2000

Draft EIS/EIR 2000-2001

Phase 2 Background

Mid-City Exposition Light Rail Transit Project

The Re-Evaluation/Major Investment Study (1999-2000) screened a large number of alternatives for the Mid-City/Westside Corridor. Alternatives along the Exposition Corridor included TSM (Rapid Bus), BRT and LRT predominantly following the abandoned Exposition railroad right-of-way.

Major Investment Study

Mid-City Exposition Light Rail Transit Project

• Evaluated LRT and BRT in Both Expo and Wilshire Corridors

• Metro Board Adopted a Locally Preferred Alternative (LPA) for Expo which Extended from Downtown LA to Culver City only

• Expo Segment from Culver City to Santa Monica was Deferred

DEIS/DEIR

Mid-City Exposition Light Rail Transit ProjectVenice/Sepulveda Alignment

Mid-City Exposition Light Rail Transit Project Venice/Sepulveda Alignment

Mid-City Exposition Light Rail Transit Project Venice/Sepulveda Alignment

Mid-City Exposition Light Rail Transit Project Venice/Sepulveda Alignment

Mid-City Exposition Light Rail Transit ProjectExpo ROW Alignment

Mid-City Exposition Light Rail Transit Project I-10 at National Crossing

Mid-City Exposition Light Rail Transit ProjectExpo ROW Near I-10/National

Mid-City Exposition Light Rail Transit ProjectExpo ROW Near I-10/National

Mid-City Exposition Light Rail Transit ProjectExpo ROW at I-10/National

Mid-City Exposition Light Rail Transit ProjectExpo ROW at I-10/Motor

Mid-City Exposition Light Rail Transit ProjectExpo ROW I-10 Undercrossing

Mid-City Exposition Light Rail Transit ProjectExpo ROW I-10 Undercrossing

Mid-City Exposition Light Rail Transit ProjectExpo ROW near Northvale Road

Mid-City Exposition Light Rail Transit ProjectExpo ROW near Northvale Road

Mid-City Exposition Light Rail Transit ProjectExpo ROW near Northvale Road

Mid-City Exposition Light Rail Transit ProjectExpo ROW near Overland Ave.

Mid-City Exposition Light Rail Transit Project Expo ROW near Westwood Blvd.

Mid-City Exposition Light Rail Transit ProjectExpo ROW near Westwood Blvd.

Mid-City Exposition Light Rail Transit ProjectExpo ROW at I-405

Mid-City Exposition Light Rail Transit Project Expo ROW at I-405

Mid-City Exposition Light Rail Transit ProjectExpo ROW in Santa Monica

Mid-City Exposition Light Rail Transit ProjectExpo ROW in Santa Monica

Mid-City Exposition Light Rail Transit ProjectExpo ROW in Santa Monica

Mid-City Exposition Light Rail Transit ProjectExpo ROW in Santa Monica

Mid-City Exposition Light Rail Transit ProjectExpo ROW in Santa Monica

Mid-City Exposition Light Rail Transit Project Expo ROW in Santa Monica

Mid-City Exposition Light Rail Transit ProjectExpo ROW in Santa Monica

Mid-City Exposition Light Rail Transit Project Phase 2 Status

Exposition Transit Corridor to Santa Monica is included in the Metro 2001 Long Range Transportation Plan and Draft 2006 LRTP

SB1384 (Kuehl) will clarify role of Construction Authority for Phase 2 Planning, Design and Construction

Mid-City Exposition Light Rail Transit Project

Planning NTP November 2006

EIS Record of Decision July 2009

Full Funding Grant Agreement Mid 2010

Final Design & Construction 2011 – 2014

Revenue Service 2015

Phase 2 Schedule

Mid-City Exposition Light Rail Transit Project

Stage 1 – AA/DEIS/DEIR

•Notice to Proceed……………………………….November 2, 2006•Public Scoping Meetings……………………………..January 2007 •FTA Review of Model Runs………………………………July 2007•Admin. AA/DEIS/DEIR to FTA………………..….September 2007•FTA Approval to Release AA/DEIS/DEIR……….December 2007•Start of Public Comment Period….………………….January 2008•Board Adoption of LPA………………………………….March 2008•Request to Enter PE………………………….…………March 2008

EIS/PE Schedule

Mid-City Exposition Light Rail Transit Project

Stage 2 – FEIS/FEIR and PE

•FTA Approval to Enter PE…………………….……….May 2008•New Starts Rating Submittal…………………..……….July 2008•Administrative FEIS/FEIR to FTA…………...…December 2008•FTA Approval to Release FEIS/FEIR……………….March 2009•Public Circulation Period Starts……….………..……..April 2009•Board Certification of FEIS/FEIR……………..……….May 2009•Record of Decision from FTA…………………..………July 2009•Request to Enter Final Design……….…………………July 2009

EIS/PE Schedule

Mid-City Exposition Light Rail Transit Project EIS/PE Schedule

Stage 3 – Support Services after Environmental Clearance (Optional)

•Full Funding Grant Agreement•Environmental Services During Construction•Design Services During Construction•Special Work Assignments•Schedule TBD

Mid-City Exposition Light Rail Transit Project Phase 2 Scope of Work

TASK 1.0 ADMINISTRATION & PROJECT MANAGEMENT

•Task 1.1 Integrated Project Office•Task 1.2 General Project Management•Task 1.3 Project Mgmt. Plan And Project Imp. Plan•Task 1.4 Progress Meetings•Task 1.5 Project Schedule & Tracking System•Task 1.6 Project Accounting•Task 1.7 Project Progress Reporting•Task 1.8 Coordination Meetings with Cities/Stakeholders•Task 1.9 Computerized Project Folder•Task 1.10 Quality Control Procedures•Task 1.11 Management of Deliverables, Copying and Printing

Mid-City Exposition Light Rail Transit Project Phase 2 Scope of Work

TASK 2.0 COMMUNITY PARTICIPATION

•Task 2.1 Public Participation Plan•Task 2.2 Public Presentations•Task 2.3 Project Newsletters•Task 2.4 Project Brochures, Fact Sheets, etc.•Task 2.5 Project Website Support•Task 2.6 Report on Public Involvement Activities

Mid-City Exposition Light Rail Transit Project Phase 2 Scope of Work

TASK 3.0 ALTERNATIVES DEFINITION

•Task 3.1 Notice of Preparation/Notice of Intent•Task 3.2 Research & Review of Previous Alternatives•Task 3.3 Update of Purpose & Need/Corridor Definition•Task 3.4 Project Scoping•Task 3.5 Alternatives Identification•Task 3.6 Initial Screening of Alternatives

Mid-City Exposition Light Rail Transit Project Phase 2 Scope of Work

TASK 4.0 AA/DEIS/DEIR ENGINEERING & URBAN DESIGN

•Task 4.1 Corridor Mapping•Task 4.2 Plan & Profile Drawings•Task 4.3 Station Plans & Typical Cross Sections•Task 4.4 Bikeway Design•Task 4.5 Urban Design & Engineering Constraints•Task 4.6 Cost Estimates•Task 4.7 Engineering Report

Mid-City Exposition Light Rail Transit Project Phase 2 Scope of Work

TASK 5.0 RIDERSHIP FORECASTING & PERFORMANCE INDICATORS•Task 5.1 Operating Plans•Task 5.2 Aggregate Ridership Forecasts•Task 5.3 Semi-Independent Forecasts•Task 5.4 Ridership Estimates/Performance Measures•Task 5.5 Analyze Model Uncertainties•Task 5.6 Operating Cost Estimates•Task 5.7 New Starts Templates•Task 5.8 Conduct SUMMIT Analysis•Task 5.9 Transmit Model Simulation Data•Task 5.10 Model Documentation Reports•Task 5.11 Data Preservation

Mid-City Exposition Light Rail Transit Project Phase 2 Scope of Work

TASK 6.0 COMPARATIVE ANALYSIS OF ALTERNATIVES

•Task 6.1 Engineering Feasibility Analysis•Task 6.2 Environmental Feasibility Analysis•Task 6.3 Funding/Fiscal Analysis•Task 6.4 Ridership Forecasts & Performance Measures•Task 6.5 Comparative Evaluation & Summary

Mid-City Exposition Light Rail Transit Project Phase 2 Scope of Work

TASK 7.0 AA/DEIS/DEIR

•Task 7.1 Environmental Analysis•Task 7.2 Environmental Documentation•Task 7.3 FTA Comment & Review•Task 7.4 Public Comment Period/Public Hearings•Task 7.5 LPA Recommendation Report•Task 7.6 DEIS/DEIR Special Analysis Sections

Mid-City Exposition Light Rail Transit Project Phase 2 Scope of Work

Task 8.0 FTA & METRO COORDINATION

•Task 8.1 FTA/Metro Coordination•Task 8.2 New Starts Submittals•Task 8.3 FTA Request to Enter PE•Task 8.4 Work Plan for Before & After Study•Task 8.5 Bus and Rail Fleet Management Plans•Task 8.7 Real Estate Acquisition Plan•Task 8.8 Support for Record of Decision•Task 8.9 FTA Request to Enter Final Design

Mid-City Exposition Light Rail Transit Project Phase 2 Scope of Work

TASK 10.0 FINAL EIS/EIR

•Task 10.1 Review of DEIS/DEIR Comments•Task 10.2 Refinement of Locally Preferred Alternative•Task 10.3 Responses to DEIS/DEIR Comments•Task 10.4 Administrative FEIS/FEIR•Task 10.5 FEIS/FEIR Circulation and Approvals•Task 10.6 Administrative Record

Mid-City Exposition Light Rail Transit Project Phase 2 Scope of Work

TASK 9.0 PRELIMINARY ENGINEERING

•Task 9.1 Preliminary Basis of Design Report•Task 9.2 Geotechnical Studies•Task 9.3 Hazardous Materials Investigation & Analysis

(Phase 1 and 2 Site Assessments)•Task 9.4 Drainage/Hydraulics•Task 9.5 Trackwork•Task 9.6 Retaining Walls and Soundwalls•Task 9.7 Street Improvements•Task 9.8 Bridges•Task 9.9 Tunnels/Trenches•Task 9.10 Utilities

Mid-City Exposition Light Rail Transit Project Phase 2 Scope of Work

•Task 9.11 Right of Way•Task 9.12 Traction Power Load Flow Analysis, Substation

Locations and Overhead Contact System•Task 9.13 Signaling/Communications•Task 9.14 Traffic Handling and Construction Staging•Task 9.15 Plan & Profile and Typical Section Drawings•Task 9.16 Station Plans•Task 9.17 Special Provisions•Task 9.18 Cost Estimates•Task 9.19 Safety & Security•Task 9.20 Project Risk Analysis and Procurement Planning•Task 9.21 Caltrans Project Initiation Report•Task 9.22 Value Engineering/Peer Review•Task 9.23 Agency Permits & Approvals•Task 9.24 Preliminary Engineering Report

Mid-City Exposition Light Rail Transit Project Phase 2 Scope of Work

TASK 11.0 SUPPORT SERVICES AFTER ENVIRONMENTAL CLEARANCE(Optional Task)

•Task 11.1 Full Funding Grant Agreement•Task 11.2 Environmental Services During Construction•Task 11.3 Design Services During Construction•Task 11.4 Special Work Assignments