Ministry of Environment ProtectionMinistry of Environment Protectionand Natural Resources of Georgiaand Natural Resources of Georgia
Risk communication on pipeline safety in Georgia
Revaz Enukidze
Head of Department of International relations and conventions
WORKSHOP ON PREVENTION OF ACCIDENTS OF GAS TRANSMISSIONS PIPELINE
8-9 March 2006
Hague
EAST-WEST ENERGY CORRIDOR
In 1904, the famous Nobel brothers built a pipeline running from Baku to the Georgian Black Sea coast.
Georgia
Ministry of Environment ProtectionMinistry of Environment Protectionand Natural Resources of Georgiaand Natural Resources of Georgia
KAZAKHSTAN
RUSSIA
AZERBAIJAN
GEORGIA
TURKMENISTAN
Oil Fields
ARMENIA
Oil
Gas
60 mln. t/y 31 bln. m3/y
100 mln. t/y
31 bln. m3/y
10 mln. t/y 110 bln. m3/y
ESTIMATES OF OIL AND GAS PRODUCTION IN THE CASPIAN REGION BY THE YEAR 2010 (“Possible production” as estimated by EIA)
Turkey
GEORGIA
Russia
ArmeniaAZERBAIJAN
SupsaSupsa
BakuBaku
50 mln t/y 50 mln t/y
30 BCM30 BCM
BTC
SCP
CeyhanCeyhan
Erzurum Erzurum
TbilisiTbilisi
Implementation of the Baku-Tbilisi-Ceyhan Main Export Pipeline and the Baku-Tbilisi-Erzurum South Caucasus Pipeline System projects lays a foundation to a full-scale development of the East-West Energy Corridor.
7 mln. t/yWREP
EAST-WEST ENERGY CORRIDOR
Ministry of Environment ProtectionMinistry of Environment Protectionand Natural Resources of Georgiaand Natural Resources of Georgia
ENVIRONMENTAL AND TECHNICAL STANDARDS AND PRACTICES APPLIED IN THE COURSE OF THE IMPLEMENTATION OF THE BTC AND THE SCP PROJECTS
• Netherlands Standards (for the BTC Project)
• Austrian Standards (for the BTC Project)
• ISO, API, ANSI, ASTM, BSI etc.
• EU Standards and Practices
• UK Standards (for the SCP Project)
• World Bank Environmental Standards and Practices
Ministry of Environment ProtectionMinistry of Environment Protectionand Natural Resources of Georgiaand Natural Resources of Georgia
ENVIRONMENTAL ASPECTS OF BTC AND SCP CONSTRUCTION
Georgia has approved the Environmental Impact Georgia has approved the Environmental Impact Assessment (EIA) and the Project Design Documents for the Assessment (EIA) and the Project Design Documents for the BTC and SCP Projects, with certain conditions. BTC and SCP Projects, with certain conditions.
Among others, these conditions call for special solutions Among others, these conditions call for special solutions with respect to environmentally sensitive areas in the with respect to environmentally sensitive areas in the Borjomi and Tsalka districts.Borjomi and Tsalka districts.
Conditionally has been approved also Oil Spill Response Conditionally has been approved also Oil Spill Response Plan for BTC Pipeline. Emergency Response Plan for SCP Plan for BTC Pipeline. Emergency Response Plan for SCP Pipeline has to be approved before the operation phase.Pipeline has to be approved before the operation phase.
Ministry of Environment ProtectionMinistry of Environment Protectionand Natural Resources of Georgiaand Natural Resources of Georgia
River Mtkvari crossing
0.5 km0.5 km0.5 km0.5 km
Ktsia Tabatskuri
1.5 km1.5 km1.5 km1.5 km
Kodiana pass
3 km3 km3 km3 km
Sections of SCP and BTC pipelines laded simultaneously.
Ministry of Environment ProtectionMinistry of Environment Protectionand Natural Resources of Georgiaand Natural Resources of Georgia
Additional studies for landslide-prone areas have been finalized and construction in this area was performed according to the site-specific design concepts.
Fulfillment of Environmental Permit Conditions
Ministry of Environment ProtectionMinistry of Environment Protectionand Natural Resources of Georgiaand Natural Resources of Georgia
Methodology for calculating scouring depth and set-backs at river-crossings have been agreed upon. Detailed designs for certain river crossings have been approved.
Fulfillment of Environmental Permit Conditions
Ministry of Environment ProtectionMinistry of Environment Protectionand Natural Resources of Georgiaand Natural Resources of Georgia
Specific mitigation measures for the sensitive segments of the Borjomi and Tsalka pipeline sections are being finalized.
Fulfillment of Environmental Permit Conditions
Ministry of Environment ProtectionMinistry of Environment Protectionand Natural Resources of Georgiaand Natural Resources of Georgia
• A fiber optic or similar sensor system will be installed to detect earth movements, illegal excavation, or third party intrusion.
• A marker tape will be utilized with electronic alarm to detect breakage/interference.
70cm
BTC Pipeline
Fiber optic cable Detection Diameter
TSALKA Area BORJOMI Area
BTC Pipeline
2m
Detection DiameterFiber optic cable
Ministry of Environment ProtectionMinistry of Environment Protectionand Natural Resources of Georgiaand Natural Resources of Georgia
CATHODIC PROTECTION DEVISE
Cathodic protection system
Cathodic protection posts is installed to protect the pipeline against corrosion.
INTERNAL MONITORING OF THE PIPELINE
Pig launchers and receivers is installed at several points of the pipeline.
Fulfillment of Environmental Permit Conditions
Ministry of Environment ProtectionMinistry of Environment Protectionand Natural Resources of Georgiaand Natural Resources of Georgia
Drain-down Tank
Security Base
Head of Special State Protection Head of Special State Protection Service (SSPS) of Georgia Service (SSPS) of Georgia
Minister of State Security of GeorgiaMinister of State Security of Georgia
Head of State Intelligence Service Head of State Intelligence Service of Georgiaof Georgia
Minister of Interior Affairs of GeorgiaMinister of Interior Affairs of Georgia
Minister of Defense of GeorgiaMinister of Defense of Georgia
Head of State Border Protection Head of State Border Protection Department of GeorgiaDepartment of Georgia
President of Georgian International President of Georgian International Oil Corporation (GIOC)Oil Corporation (GIOC)
Minister of Environment of GeorgiaMinister of Environment of Georgia
Minister of Finance of GeorgiaMinister of Finance of Georgia
Head of Regional Policy and Head of Regional Policy and Administration Service of the State Administration Service of the State Chancelary of GeorgiaChancelary of Georgia
Heads of other relevant state Heads of other relevant state agenciesagencies
SECURITY ISSUES OF THE EAST-WEST ENERGY CORRIDOR
National Security Council of GeorgiaNational Security Council of Georgia
Standing Interagency CommissionStanding Interagency Commission
Deputy Chairman (SSPS)Deputy Chairman (SSPS)
Chairman of the Standing Interagency CommissionChairman of the Standing Interagency Commission
Deputy Chairman (GIOC)Deputy Chairman (GIOC)
Ministry of Environment ProtectionMinistry of Environment Protectionand Natural Resources of Georgiaand Natural Resources of Georgia
Special camp for security Special camp for security personnel will be deployed personnel will be deployed along the East-West Energy along the East-West Energy Corridor to patrol the pipelines Corridor to patrol the pipelines on a permanent basis.on a permanent basis.
This will allow for timely and proper response to all potential threats from terrorist attacks.
SECURITY ISSUES OF THE EAST-WEST ENERGY CORRIDOR
LEGEND
Gas-main
Branch
Interconnection facilities
SCP
Georgia will receive significant amounts of natural gas from the SCP.Georgia will receive significant amounts of natural gas from the SCP.
First CDM project on gas pipeline will be implemented in Georgia.First CDM project on gas pipeline will be implemented in Georgia.
Ensuring Georgia’s Energy Security Ensuring Georgia’s Energy Security
Ministry of Environment ProtectionMinistry of Environment Protectionand Natural Resources of Georgiaand Natural Resources of Georgia