Post on 12-Jun-2020
transcript
OVERVIEW
INTRODUCTION
PROJECT DESCRIPTION
PROJECT STATUS
LEGAL AND ORGANIZATIONAL DEVELOPMENT
PROSPECTS
CONCLUSIONS
Reduces investment for power reserves by 3.5 billion US $ (2008- 2028) for the same reliability.
Economic analysis of the interconnection indicated a cost / benefit ration 1.77 (all six countries )
The two common strategies: build capacities independently or interconnect individual systems.
Considerable investment is required to build new generating capacities .
Supply has to increase to match the anticipated demand.
Power Demand in GCC Countries is anticipated to increase from 32 GW in 2003 to 94 GW in 2028.r1
Slide 3
r1 I believe it is much more than this figure, only Saudi Arabia is 32,000 MW.rnassar, 10/10/2007
Provide means for energy trading
Provide emergency support to any system during black out situations
Improve the overall system reliability
Lower operating costs by using most economic generation unit in the interconnected system
Share spinning reserves to cover emergency operating conditions
Reduce generating capacity required in each system due to ability to share power reservesr4
Slide 4
r4 I believe it is much more than this figure, only Saudi Arabia is 32,000 MW.rnassar, 10/10/2007
Phase I (%) Phases I &III (%)
Kuwait 33.8 26.7
Saudi Arabia (ERB) 40.0 31.6
Bahrain 11.4 9.0
Qatar 14.8 11.7
UAE 15.4
Oman 5.6
TOTAL 100.0 100.0
r3
SAUDI ARABIASEC – ERB
HDVCBACK-TO-BACK
KUWAITAL ZOUR 400 kV
BAHRAIN
QATARDOHA SOUTH SUPER 400 kV
OMANOMAN NORTHERN GRID
UAESHUWAIHAT
400 kV
EMIRATE NATIONAL GRID
1200 MW
1200 MW600 MW
750 MW
400 MW
900 MW
GHUNAN 400 kV
AL FADHILI 400 kV
310 km
90 km
100 km290 km
150 km
52 km
SALWA 400 kV
112 km
JASRA 400 kV
AL WASEET 220 kVAL OUHAH 220 kV
Contract Price
Substations $221,983,888
HVDC BtB Conv. $205,896,785
Transmission Lines $280,400,717
Cables $343,122,125
Control Center $27,637,220
Consultancy $16,283,146
TOTAL $ 1,095,323,881
Contract No. Contract Actual Percentage (%)
112-A1 Al-Zour S/S 74.33112-A6 Al-Jasra S/S 66.16112-A7 Doha South S/S 81.08112-A2 Al-Fadhili S/S 93.42112-A4 Ghunan & R.A.Q. S/S 41.74112-A5 Salwa S/S 74.4113-A3 Al-Fadhili B2B 51.84114-B1 Al-Zour / Al-Fadhili T/L 41.06114-B4 Salwa / Doha South T/L 50.98114-B2 Al-Fadhili / Ghunan T/L 81.62114-B3 R.A.Q. / Ghunan / Salwa T/L 28.14115-B5 Land & Submarine Cable 10.66116-C Control Systems 64.09
Overall Progress 41.34
GCC MinisterialCommittee
GCCIABoard of Directors
GCCIA - CEO
General Agreement
PETA
Transmission& Metering Codes
E & W MinisterialCommittee Level
General Assembly& Board Level
GCC Utilities Level
Articles / Bylaws
PlanningCommittee
OperatingCommittee
Regulatory AdvisoryCommittee
Agreement between the
Trading parties setting out the
technical provisions which the Authority, the TSO Parties and the Procurement
Parties will observe when operating and
using the Interconnector .
Agreement between the
Trading parties setting out the
technical provisions which the Authority, the TSO Parties and the Procurement
Parties will observe when operating and
using the Interconnector .
Interconnector Transmission Code (ITC)
Agreement between the
Trading parties setting out
obligations in respect of installed
capacities and operating reserves as well as Terms
applicable to connection, use of
interconnector, and Trading.
Agreement between the
Trading parties setting out
obligations in respect of installed
capacities and operating reserves as well as Terms
applicable to connection, use of
interconnector, and Trading.
Power Exchange & Trading Agreement (PETA)
High level agreement
between the Member States setting out the
rules and regulations in respect of the
inteconnector as well as defining the Regulatory
Committee and the regulatory principles.
High level agreement
between the Member States setting out the
rules and regulations in respect of the
inteconnector as well as defining the Regulatory
Committee and the regulatory principles.
GeneralAgreement
(GA)
Provide a Wheeling Services to the power sectors in the GCC countries
Becomes a ‘Launch-Pad’ for Energy Trading
Provide access to the Electricity Market in the region and beyond
Utilize the OPGW fiber optic excess capacity
Authority may lease out fibers
Market is being
explored
The Interconnector Provides an opportunity for capitalizing in fiber optic excess capacity
The GCC Grid will be a fundamental step that can lead to a regional electricity market
The Interconnector’s legal and organisational frame work is in the process of being finalised
The work progress shows about 41 % accomplishment as on September 2007
The Interconnector’s connection points rated equivalent to the loss of 50% of the largest power plant for each country
The Interconnector will provide economic benefits and support in emergency situations