Project Street Limits
• Montwood from McRae to Zanzibar– Windrock from Montwood to Eastwood Dam– Honolulu and Trinidad (200-300’ to
accommodate sanitary sewer adjustment)• Eastwood Dam• Replacement of Traffic Signal at Wedgewood
• Consists of street, drainage, parkway and accessibility improvements
– Water distribution lines and services replacement, (entire project)
– Sanitary sewer lines and services replacement, (Honolulu, Trinidad and at Windrock)
– Underground storm sewer system (11'x7' Concrete Box Culvert)
– Increase capacity to Eastwood Dam (PSB)
Scope of Work
– Concrete paved roadways with
standard curb and gutter– Concrete sidewalks and driveways– ADA compliant ramps and 8' sidewalks, plus
4' parkway with trees– New landscaping and irrigation along
parkway (4’), modifications to existing landscaping and irrigation at medians
Scope of Work
Landscaping Enhancement
• Proposed trees along parkways
• Raywood Ash• Lacebark Elm• Chinese Pistache
• Proposed trees and shrubs at medians:• Desert Museum Palo Verde• Golden Ball Lead Tree• Sweet Acacia
Funding Source:– 2010 COs $9,521,346.24– PSB $1,567,983.60– Total $11,089,329.84
CONTRACTOR:
Ultimate Concrete LLCEl Paso, TX
Contract Time: 698 Consecutive Calendar Days
Project Schedule
– Target start construction December 2012/January 2013
– Scheduled completion January 2015
– Anticipated Impacts
–Construction Time 24 months
–Access to properties will be maintained
–Various detours will be in place throughout the construction
–Temporary driveway and sidewalk closures
Project Schedule
–Scheduled water service shutdowns, 24 hour advance notice to be given, maximum of four hours long.
PHASE 1
PHASES 1, 2, 3 and 4 Phase 1 - 218 days
PHASE 2
PHASE 3
PHASE 4- water line
Phases 2, 3, 4 will be done concurrently with phase 1
Phase 2 (90 days)Phase 3 (50 days)Phase 4 (50 days)