Objectives
By the end of this lesson, you will be able to:
● Define Project Management
● Describe Microsoft® Project 2013 editions
● State the features of Microsoft® Project 2013
● Use Project Options in Microsoft® Project 2013
Copyright © 2012-2014, Simplilearn, All rights reserved. 3
The objective of any project is to create a product, obtain a desired result, or deliver a service.
Introduction
Elements of a Project
Scope
Work
Cost Time
Copyright © 2012-2014, Simplilearn, All rights reserved. 4
Project Management
Project management refers to the application of knowledge and methods to execute projects successfully.
Initiating Planning
Executing Closing
Project Management
Initiating Planning
Executing Closing
Copyright © 2012-2014, Simplilearn, All rights reserved. 5
Microsoft® Project 2013
Microsoft® Project 2013 is an application that enables you to plan and manage projects effectively.
Copyright © 2012-2014, Simplilearn, All rights reserved. 6
Microsoft® Project 2013 Editions
Microsoft® Project 2013 is available in two editions.
Microsoft® Project 2013 Editions
• Create and modify project
plans
• Plan and organize tasks
• Generate reports
• Monitor project costs
• Connect to Project Web App
• View the tasks to resources in
Team Planner View
Microsoft® Project Professional Microsoft® Project Standard
Copyright © 2012-2014, Simplilearn, All rights reserved. 7
Features of Microsoft® Project 2013
Microsoft® Project 2013 can be used to create plans with the level of detail that is appropriate for a project.
It gives the Project Manager the flexibility to edit or add information, any time during the course of the project. Flexibility
Each component of a project is broken down into a Work Breakdown Structure (WBS) or tasks. Work Breakdown
Structure
The Project Manager can set up a project calendar that includes the number of working days, public holidays, and other non-working days.
Project Calendar
It helps manage resources and their associated costs effectively by dividing resources as Material, Work, and Cost resources.
Manage Resources
The Project Manager can control tasks manually or schedule them automatically. Organizing project tasks includes linking tasks that are related.
Control Tasks
It has pre-installed reports which can be customized to generate burndown reports any time, to monitor the health of the project.
Pre-installed Reports
Copyright © 2012-2014, Simplilearn, All rights reserved. 8
Calendar Types
Microsoft® Project 2013 offers four calendar types.
Types of Calendars
Base
Project
Task
Resource
Copyright © 2012-2014, Simplilearn, All rights reserved. 9
Base Calendar
Base calendar is the template, on which the three Project calendars are built: Standard, Night shift, and 24 Hours.
Type of base calendar Timings Days per week
Standard 9 am to 5 pm 5 days per week
Night shift 11 pm to 5 am 5 days per week
24 Hours 24 hours per day 7 days per week
Copyright © 2012-2014, Simplilearn, All rights reserved. 10
Project Options
Project Options are available in the backstage view of Microsoft® Project 2013 interface.
You can customize the User Interface, Project view, and Start-up options in this screen. You can also personalize your project file here.
General
You can customize the calendar type and currency options in this screen. This screen highlights the list of checkboxes to choose preferred elements for the project.
Display
Microsoft® Project 2013 uses ribbon for easier access, as used in other Microsoft® products. You can add or remove the commands and tabs that you prefer on your Project window.
Customize Ribbon
Microsoft® Project 2013 provides a quick access toolbar for easy navigation, similar to the previous versions. You can add or remove tools that you constantly use while working on the project.
Quick Access Toolbar
Copyright © 2012-2014, Simplilearn, All rights reserved. 11
Copyright © 2012-2014, Simplilearn, All rights reserved. 12
Knowledge Check 1
What are the parameters that need to be defined while planning a project?
Select the answer.
a. Scope, work, time, and cost
b. Scope, resource, time, and cost
c. Scope, work, calendar, and cost
d. Scope, work, start/finish date, and schedule
Copyright © 2012-2014, Simplilearn, All rights reserved. 13
Knowledge Check 1
Answer: a. Scope, work, time, cost
a. Scope, work, time, and cost
b. Scope, resource, time, and cost
c. Scope, work, calendar, and cost
d. Scope, work, start/finish date, and schedule
Explanation: A Project Manager needs to define the scope, work, time, and cost while planning a project.
What are the parameters that need to be defined while planning a project?
Select the answer.
Copyright © 2012-2014, Simplilearn, All rights reserved. 14
Knowledge Check 2
Which of the following is the Team Planner used for?
Select the answer.
a. To modify tasks in project
b. To Identify potential problems in project
c. To share project updates online
d. To breakdown a project into work breakdown structure
Copyright © 2012-2014, Simplilearn, All rights reserved. 15
Knowledge Check 2
Answer: b. To Identify potential problems in project
Explanation: Team Planner helps the Project Manager to identify potential problems, before they can impact the project schedule.
Which of the following is the Team Planner used for?
Select the answer.
a. To modify tasks in project
b. To Identify potential problems in project
c. To share project updates online
d. To breakdown a project into work breakdown structure
Copyright © 2012-2014, Simplilearn, All rights reserved. 16
Knowledge Check 3
Initiating, Planning, Executing, Monitoring and Controlling, and Closing are the phases of which of the following?
Select the answer.
a. Project Planning
b. Project Management
c. Microsoft® Project
d. Project Interface
Copyright © 2012-2014, Simplilearn, All rights reserved. 17
Knowledge Check 3
Answer: b. Project Management
Explanation: Initiating, Planning, Executing, Monitoring and Controlling, and Closing are the phases of Project Management.
Initiating, Planning, Executing, Monitoring and Controlling, and Closing are the phases of which of the following?
Select the answer.
a. Project Planning
b. Project Management
c. Microsoft® Project
d. Project Interface
Copyright © 2012-2014, Simplilearn, All rights reserved. 18
Knowledge Check 4
Which of the following is a feature available only in Microsoft® Project Professional edition?
Select the answer.
a. Team Planner View
b. Base Calendar
c. Project Options
d. Project Interface
Copyright © 2012-2014, Simplilearn, All rights reserved. 19
Knowledge Check 4
Answer: a. Team Planner View
Explanation: Microsoft® Project Professional edition includes enhanced tools, such as the Team Planner View. This feature is not available in Microsoft® Standard edition.
Which of the following is a feature available only in Microsoft® Project Professional edition?
Select the answer.
a. Team Planner View
b. Base Calendar
c. Project Options
d. Project Interface
Copyright © 2012-2014, Simplilearn, All rights reserved. 20
Knowledge Check 5
Which of the following options allow you to customize the calendar type and currency options in Microsoft® Project 2013? Select the answer.
a. Display
b. Customize Ribbon
c. General
d. Quick Access Toolbar
Copyright © 2012-2014, Simplilearn, All rights reserved. 21
Knowledge Check 5
Answer: a. Display
Explanation: You can customize the calendar type and currency options in Microsoft® Project 2013, using the Display option.
Which of the following options allow you to customize the calendar type and currency options in Microsoft® Project 2013?
Select the answer.
a. Display
b. Customize Ribbon
c. General
d. Quick Access Toolbar
Copyright © 2012-2014, Simplilearn, All rights reserved. 22
Summary
Let us summarize the topics covered in this lesson:
● Project management involves balancing the scope, time, and cost constraints in
order to meet the overall objectives of the project.
● Microsoft® Project can be used to create plans with the level of detail that is
appropriate for a project.
● Microsoft® Project 2013 offers four calendar types. Base calendar is the template
of all calendars.
● The basic settings of a project can be managed using Project Options in
Microsoft® Project 2013.
Copyright © 2012-2014, Simplilearn, All rights reserved. 23