MSD 1 P12453 Detailed Design Review Markus Holzenkamp Robin Leili Cody Anderson 5/17/2015 Detailed...

Post on 17-Dec-2015

215 views 1 download

Tags:

transcript

MSD 1 P12453Detailed Design Review

Markus HolzenkampRobin Leili

Cody Anderson

04/18/23

Detailed Design Review

1

Agenda• Introduction (1 min)• Project Background (2 min)• Customer Needs (2 min)• Revised Engineering Specs (5 min)• Risk Management (5 min)• RITDAQ (40 min)

– Analog– Thermocouples

• Bill of Materials (10 min) – Complete– Cost Overview

• LabView VI Interface (10 min)• Test Plan (10 min)• Questions

04/18/23

Detailed Design Review

2

Team MembersTEAM:Project Manager: Markus Holzenkamp (ME)Project Engineers: Cody Anderson (ME)

Robin Leili-Marrazzo (ME)

CUSTOMER:Dr. Jason Kolodziej, ME Department, RITDr. Edward Hensel, ME Department, RIT

SUPPORT:Project Guide: Bill Nowak (Xerox)Faculty Champion: Dr. Kolodziej (RIT)Sponsors: Scott Delmotte (D-R)

James Sorokes (D-R) Britt Dinsdale (D-R)

04/18/23

Detailed Design Review

3

Customer NeedsPriority Need

1 Learn RITDAQ capabilities and propose and implement improvements in code to generate p-v diagrams, time and frequency plots

1 Propose and install possible additional sensors to measure stage pressures, stage temperature, bearing temperature

2 Install Envision System

3 Select, install, and integrate encoder

99 Develop future undergrad/grad labs

04/18/23

Detailed Design Review

4

Project Scope• Understand the current state of the compressor– Current sensors, DAQ capabilities– Operation characteristics of reciprocating compressors

• Install and run ENVISION Condition monitoring system to be donated by Dresser-Rand

• Increase the current DAQ capabilities

• End Goal: Design, develop, and install effective health monitoring capabilities

04/18/23

Detailed Design Review

5

Sample Engineering Specs (Updated)

Specification Unit of Measure

Marginal Value

Ideal Value

Actual Value

Encoder Resolution pulses per rev 1 1440 720 (x4)

crankshaft / encodershaft ratio 10 1 1

Encoder Lifetime cycles 100000 1000000 TBD

Voltage required by sensors V 120 24 8-30

Sensor Cost $ 1000 0 <300

Sensor Output V 0-5 0-5

Sample Rate of the RITDAQ Hz 0 <370kHz TBD

Total number of analog sensors # 0 <16 13

Total number of thermocouples # 0 <16 12

Pipe thread size ½”- ¾” NPT

1/8” – ¾” NPT

04/18/23

Detailed Design Review

6

Concept Selection04/18/23

Detailed Design Review

7

Risk Assessment04/18/23

Detailed Design Review

8

Risk Assessment04/18/23

Detailed Design Review

9

RITDAQChannel layout and sensor attachments

04/18/23

Detailed Design Review

10

DAQ Channel Layout (Analog)04/18/23

Detailed Design Review

11

DAQ Channel Layout (Analog)04/18/23

Detailed Design Review

12

Flow meter

How?•Insert in flex-hose section

Why?•Easy to modify layout•Cost efficient

Materials Needed:-hose clamps (x2)-Adapter (x2)

04/18/23

Detailed Design Review

13

Tank Pressure04/18/23

Detailed Design Review

14

Tank Pressure

How?•Use Rosemount Alphaline 1151•Mounted on compressor base•Connected with pressure tubing

Why?•Already have sensor•Easy to place T-Piece before analog gage

Materials Needed:-T-Piece-Adapter-Thermocouple fitting

04/18/23

Detailed Design Review

15

dP across orifice tank

How?•Use Rosemount sensor •Mount in basement with tank

Why?•No room constraints•Out of the way

Materials Needed:-Hardware-Adapter (x2)-Elbow

04/18/23

Detailed Design Review

16

Photocraft HS20 Encoder

How?•Use included mounting bracket to attach to oil pump housing

Why?•No modifications to existing structure

Materials needed:- 7/16-14 Bolt 3in long- 7/16-14 nuts

04/18/23

Detailed Design Review

17

DAQ Channel Layout (Thermocouples)04/18/23

Detailed Design Review

18

DAQ Channel Layout (Thermocouples)04/18/23

Detailed Design Review

19

Inlet Coolant TemperatureHow?•Attach T-Piece between flex hose and steel flange

Why?•No modifications to existing structure•Inlet coolant is at room temperature, heat loss is negligible along steel pipeMaterials Needed:-T-Piece-Hose Clamp-Adapter for Thermocouple-Thermocouple fitting

04/18/23

Detailed Design Review

20

Cylinder Coolant Layout04/18/23

Detailed Design Review

21

Head Outlet Coolant Temperature04/18/23

Detailed Design Review

22

Head Outlet Coolant Temperature

How?•Attach fitting to plugged hole and insert thermocouple directed at top outlet

Why?•No modification of existing structure•Measures right at the outlet Materials Needed:-Thermocouple fitting-Adapter

04/18/23

Detailed Design Review

23

Center Outlet Coolant Temperature

How?•Attach fitting with thermocouple to plugged hole adjacent to outlet

Why?•No modification to existing structure•No losses

Materials Needed:-Adapter-Thermocouple fitting

04/18/23

Detailed Design Review

24

Tail Coolant Out Temperature04/18/23

Detailed Design Review

25

Tail Outlet Coolant Temperature

How?•Drill and tap hole in pipe. (4mm wall thickness)

Why?•Close to outlet •No mixing with other coolant flowsMaterials Needed:- Thermocouple fitting

04/18/23

Detailed Design Review

26

Tail Coolant Out Temperature

• Test strength of threading schedule 80 pipe.

04/18/23

Detailed Design Review

27

Combined Outlet Coolant Temperature

How?•Drill and tap hole in bottom of flow sight

Why?•Close after all 3 coolant outlets combine•Sufficient wall thickness to secure enough threads for fittingMaterials Needed:- Fitting for Thermocouple

04/18/23

Detailed Design Review

28

Combined Outlet Coolant Temperature

04/18/23

Detailed Design Review

29

Measuring the temperature of the cooling pipes at various locations

Coolant Temperature Before and After Chiller

How?•Insert T-Piece between flex hose and Chiller inlet

Why?•Easy to add piping at this place

Materials Needed:-T-Piece (x2)-Adapter (x2)-Thermocouple fitting (x2)

04/18/23

Detailed Design Review

30

Crankcase Oil Temperature

How?•Attach fitting with thermocouple in plugged hole in crankcase

Why?•No modification of existing structure

Materials Needed:-Adapter-Thermocouple fitting

04/18/23

Detailed Design Review

31

Crankshaft Bearing Temperature04/18/23

Detailed Design Review

32

Crankshaft Bearing Temperature

How?•Drill into crankcase until just before bearing journal•Insert thermocouple to measure temperature of crankcase at that point•Assistance from Dresser-Rand

Why?•Does not alter bearing function•Will show trends of bearing temperature accuratelyMaterials Needed:- Thermocouple fitting (x2)

04/18/23

Detailed Design Review

33

Bill of Materials 04/18/23

Detailed Design Review

34

Cost Breakdown

BUDGET $3000Sensors $1089Wiring $88

Hardware $243TOTAL COST $1420

04/18/23

Detailed Design Review

35

LabView Interface

Goals:•Clearly display compressor data•Time domain and Frequency domain•P-v diagram for forward stroke and backstroke

04/18/23

Detailed Design Review

36

04/18/23

Detailed Design Review

37

PRELIMINARY TEST PLANS

04/18/23

Detailed Design Review

38

Sensor Tests

Means of testing sensor functionality•SigLab•Existing USB DAQ•RIT DAQ

04/18/23

Detailed Design Review

39

RIT DAQ

Cross referencing sensor outputs with existing DAQs and Signal Analyzers•Use USB DAQ to validate signals•Use SigLab to validate signals•Reference expected values to ensure proper sensor readings

04/18/23

Detailed Design Review

40

Envision System

Utilize the functionality of the RIT DAQ •Use the functioning RIT DAQ to ensure the Envision System is displaying proper outputs•RIT DAQ will already be cross referenced with alternative Signal Processors and validated

04/18/23

Detailed Design Review

41

Preliminary MSD II Schedule04/18/23

Detailed Design Review

42

Questions?04/18/23

Detailed Design Review

43