Navigating a MOTEMS Audit - State Lands Commission · Navigating a MOTEMS Audit Ted Trenkwalder,...

Post on 28-Jul-2018

217 views 0 download

transcript

Navigating a Navigating a MOTEMS MOTEMS AuditAudit

Ted Trenkwalder, P.E., S.E.

Structural Engineer

Ben C. Gerwick, Inc.September  10, 2008

Presentation OutlineIntroduction

Ben C. Gerwick, IncAudits Completed for Four High Risk TerminalsFirst two Audits Submitted and Reviewed by CSLC

The Audit ProcessLessons LearnedSummaryQuestions

The Audit ProcessSurveys, Surveys, SurveysOperational Capacity and Demand AnalysesSeismic Capacity and Demand AnalysesChecklists, Missing Information, and Deficiency TablesExecutive Summary and Audit Submittal

The Audit ProcessSurveys, Surveys, Surveys,…

Data Collection and ReviewAbove and Below Water InvestigationsGeotechnical InvestigationsHydrographic and Topographic SurveyMaterial Testing 

The Audit ProcessData Collection and Review

Existing As‐Built DrawingsExisting As‐Built SpecificationsExisting Condition Survey(s)Existing Geotechnical InformationExisting Hydrographic or Topographic InformationExisting Vessel Information and General ArrangementsExisting Terminal Operations Manual(s) Available Information from Public Records

The Audit ProcessAbove and Below Water Inspections

PE Divers and Level of InspectionsCoordinate Inspections and Critical MembersCompile Inspection Results and Assign Ratings Condition Survey Report (s)

The Audit ProcessGeotechnical Investigations

Borings and CPTs Available borings may not meet MOTEMS 100‐ft requirementMap both transverse and longitudinal soil profilesConsider potential repairs and upgrades to facilities

Seismic Analyses and Hazard AnalysesSite Specific Response SpectraSoil Liquefaction and lateral stabilityP‐y and T‐z requirementsAbutments

The Audit ProcessOperational Capacity and Demand Analyses

Operational Dead and Live LoadsBerthing Mooring

Winds and CurrentsPassing Vessel Effects

Fender SystemsMooring Hardware

The Audit ProcessSeismic Capacity and Demand Analyses

SeismicDead Load and Equipment Inertial and Kinematic Loads

The Audit ProcessChecklists, Missing Information, and Deficiency Tables

CSLC Draft Audit Manual ChecklistsMissing Information Deficiency Tables

The Audit ProcessExecutive Summary and Audit Submittal

Structural Summaries and CARsComponent Summaries and RAPsPath Forward

Addresses deficiencies and scheduled repairs

Audit Submittal Two (2) Copies and CDs to CSLC

7 to 11 Volumes (4‐in binders)1,200 to 3,000 pages 250 ‐ 750 MB of information 

Lessons LearnedPlanning and Scheduling Immediate Mitigation May be RequiredTesting is knowledgeMOTEMS ModificationsCommunication

Lessons LearnedPlanning and Scheduling

Recommend 12 months from inspection to submittal

Lessons LearnedPlanning and Scheduling (Continued)

Start Condition Surveys earlyCurrents, tides, and weather will affect inspection schedulesShip schedules will interrupt inspection schedules

Lessons LearnedPlanning and Scheduling (Continued)

Start Geotechnical field investigations early also

Site Specific Spectra and soil parameters required for analysesPotential Liquefaction and Lateral Spreading may direct mitigationmeasures

Lessons LearnedPlanning and Scheduling (Continued)

Compile Draft Checklists & DeficienciesDevelop repair design plan to eliminate operational deficienciesPlan CSLC walk down after surveys and deficiency direction

Review Path Forward with Corporate Local MOTs require input and approval from CorporateCSLC will hold MOTs to Repair Plan Schedules

Lessons LearnedMitigations may be required

Audits are performed on circa 1950 terminals with some improvements

Lessons LearnedMitigations may be required (Continued)

Expect Operational Deficiencies in Older Structures

Damaged Spring Fender Assembly

Relocated Mooring Hook

Lessons LearnedMitigations may be required (Continued)

Events Happen

Lessons LearnedTesting is knowledge

Existing Fender Assembly

Pipeway Repair Connection

Lessons LearnedMOTEMS Audit Modifications

Executive Summary Table ModificationsAbove and Below Water CARsFollow‐Up Action Items

Lessons LearnedMOTEMS Audit Modifications (Continued)

Deficiency Table ModificationsSeparate columns for Deficiency and Suggested MitigationAdded Date Completed column

Lessons LearnedMOTEMS Audit Modifications

Condition Surveys vs. Assessments

A CAR is a Condition Assessment RatingA Condition Survey refers to loss of section

Underwater vs. Above waterMOTEMS states +3‐ft MLLW for underwater survey.  Above water above +3‐ft MLLW

Lessons LearnedCommunication

Need a Project Champion at the TerminalCoordination between MOT, Audit Team, and CSLC

Include CSLC in schedule and walk throughInform CSLC of known deficiencies and directions

Request Clarification from SLC, if needed. 

SummaryAudit Process includes surveys, analyses, and checklists, deficiency tables, summary, and submittal.Recommend 12 months to complete AuditExpect mitigation requirements for older facilitiesTesting may help for marginal capacitiesMOT needs a Project Manager with good communication skills

Navigating a Navigating a MOTEMS MOTEMS AuditAudit

Ted Trenkwalder, P.E., S.E.

Structural Engineer

Ben C. Gerwick, Inc.