NEPTUNE power subsystem

Post on 20-Jan-2016

77 views 0 download

description

NEPTUNE power subsystem. Progress and Plans April 2003 Harold Kirkham. Presentation outline. Progress review Converter Mission Assurance Delivery system Documentation Plans. DC-DC Converter. DC-DC Converter. LOAD. DC-DC Converter. DC-DC Converter. Progress: Converter. - PowerPoint PPT Presentation

transcript

Neptune Power Overview- 1 All rights reserved © 2003, Neptune

NEPTUNE power subsystem

Progress and Plans

April 2003

Harold Kirkham

Neptune Power Overview- 2 All rights reserved © 2003, Neptune

Presentation outline

• Progress review– Converter– Mission Assurance – Delivery system– Documentation

• Plans

Neptune Power Overview- 3 All rights reserved © 2003, Neptune

Neptune Power Overview- 4 All rights reserved © 2003, Neptune

Neptune Power Overview- 5 All rights reserved © 2003, Neptune

Progress: Converter• All operating principles demonstrated

– Efficiency and Voltage Regulation are excellent– Current is evenly shared by parallel stages– Voltage is evenly divided by series stages

DC-DCConverter

DC-DCConverter

DC-DCConverter

DC-DCConverter

LOAD

Neptune Power Overview- 6 All rights reserved © 2003, Neptune

Progress: Converter Efficiency

0.82

0.84

0.86

0.88

0.9

0.92

0.94

0 100 200 300 400 500 600 700 800 900

Output Power (W)

450 V

500 V

600 V

700 V

800 V

Neptune Power Overview- 7 All rights reserved © 2003, Neptune

Progress: Converter Regulation

-0.050%

-0.040%

-0.030%

-0.020%

-0.010%

0.000%

0.010%

0.020%

0.030%

0 100 200 300 400 500 600 700 800 900-0.050%

-0.040%

-0.030%

-0.020%

-0.010%

0.000%

0.010%

0.020%

0.030%

0 100 200 300 400 500 600 700 800 900

Output Power (W)

450 V

500 V

600 V

700 V

800 V

Neptune Power Overview- 8 All rights reserved © 2003, Neptune

Mission Assurance

• Four aspects:– Converter– Node Distribution System– Delivery System– Communications

Neptune Power Overview- 9 All rights reserved © 2003, Neptune

Mission Assurance: Converter

• Converter stack MTBF estimated: 40 years– Assume worst-case: failure takes out stack– Assume cold-standby redundancy– Assume 30 year NEPTUNE lifetime– Observatory may need a few replacements

• Assume substring failure is not fatal– Converter power de-rated by 17%– Observatory may never need a replacement

• The Message is: Don’t worry – BE HAPPY!

Neptune Power Overview- 10 All rights reserved © 2003, Neptune

Mission Assurance: Node Distribution

• Distribution system power at 400 and 48 V– Assume 400-V source is solidly available– Assume 48-V COTS converters– Assume COTS switches– This is so simple, we have deferred the design

• BOTE cost estimates done by JPL & UW– JPL cost: $2,000,000– UW cost: $250,000

Neptune Power Overview- 11 All rights reserved © 2003, Neptune

Mission Assurance: Node Distribution

• JPL assumes– Hardware handled by

certified people only– Complete paper trail for

all activities– Extensive testing, with

tests traceable back– Environment complies

with ESD and contamination rules

– All handling requires multiple personnel

• UW assumes– Hardware handled as

needed– Marginal paper trail

– Some testing

Neptune Power Overview- 12 All rights reserved © 2003, Neptune

Mission Assurance: Node Distribution

• The difference between these numbers is one of culture

• The two cost estimates are equally valid• Neither is “right” or “wrong”

• The product of the work is different, however• You pay for what you get• Is there a middle ground?

Neptune Power Overview- 13 All rights reserved © 2003, Neptune

Mission Assurance: Delivery System

• Triggered by concern over converter reliability, we have devised a “Version 2”

• The original motivation may not be valid, but the new design brings major benefits

• The biggest benefit of Version 2 is that node failures (power supply or comm failure) do not affect the backbone

• This segregation of function leads to better observatory availability

Neptune Power Overview- 14 All rights reserved © 2003, Neptune

How does Version 2 work?

Neptune Power Overview- 15 All rights reserved © 2003, Neptune

Component availability

• Zeners, qualified to 2A, preliminary study done for 10A upgrade• Capacitors, qualified• Latching relay, similar to qualified, limited re-qualification needed• Resistors, similar to part in qualification• Bridge, qualified• Controller, space qualified part may be suitable, limited development,

or control by analog electronics (qualified)

Neptune Power Overview- 16 All rights reserved © 2003, Neptune

Version 2 power sub-system Pros and Cons

• High reliability

– Parts are qualified or low development cost

– Low component count – Low power consumption– Switching only at low power

• Segregated functionality

– Better observatory availability

• Can use single conductor cable, BU to Node

– Cost savings

• BU requires a ground• Controllability reduced

– Switches cannot be remotely operated

Neptune Power Overview- 17 All rights reserved © 2003, Neptune

Progress: Documentation

ConfigurationManagement

Plan

ConfigurationManagement

Plan

ProjectDocumentation Plan

RequirementsDocument

DeploymentVessel ICD

OperationsConcept Doc

SystemDescriptionDocuments

VerificationPlan ICD

Test Plan

Reportsand

Minutes

Power ProjectHistory

PMACS

Protection

Converter

NEPTUNE level Power Subsystem level

Neptune Power Overview- 18 All rights reserved © 2003, Neptune

Progress: Documentation

• All key documents started and on web site– Concept of Operations (Rev 5)– Test Plan (Initial) – Converter (3 files)– PMACS (17 files)– Assorted trade-offs– CoDR docs (37 files)

• Total number of files ~400