The largest construction & real estate conglomerate Company Profile

No.23 in 2018

Rating “A”

Global Contractor

No.1 in 2018

3

SOLUTIONS

IBS ( Industrialized Building System)

Innovation of Equipment

Construction Management

New Building Materials

Smart Construction

CHALLENGES

Higher Requirement of Green Construction

Complexity and Difficulty of Construction

Shorter Construction Duration

Shortage of Labor

Cost Control

1 IBS ( Industrialized Building System )

5

1. IBS

Design based on BIM

6

1.IBS

Precast concrete components

7

1. IBS

Prefabrication of steel structure

8

1. IBS

Modularization of components

2 Smart Construction

10

Digital Manufacture

Virtual Construction

Intelligent Monitoring

2. Smart Construction

11

Digital Processing Technology

2. Smart Construction

BIM CNC Machine Transportation Installation

Based on BIM

Import the model directly

into CNC machine to start

the manufactory.

Precise and efficient

12

Virtual Construction Technology

Based on BIM

Virtual construction

process

Easy to understand

2.Smart Construction

13

传感器 无线传输数据采集 云平台 监控终端Sensor DAQ

Wireless

Transmission

Cloud

Platforms

Monitoring

Terminal 传感器 无线传输数据采集 云平台 监控终端

Intelligent Monitoring – Foundation Pit Monitoring System

2. Smart Construction

14 Global Navigation Satellite System

2. Smart Construction

Intelligent Monitoring – Verticality Monitor

15

Smart

Site

Attendance Recording, Working Tracking,

Face Reorganization, Digital NCR Control

……

On-site Management

BIM 5D

Cost statistics

……

Business Management

VR Safety Accident Experience

VR Construction MOS Training

……

Construction Training

Daily Progress Record,

Weekly Schedule Model

Schedule Lag Analysis

……

Schedule Management

Material Transfer Tracking

Material Construction Record

……

Material Management

Air quality monitoring

Noise monitoring

……

Green Construction

2. Smart Construction

16 Display personnel location information in real time

On-Site Management

2. Smart Construction

Attendance Record with face recognition system

Real-time labor distribution diagram 2 Open a new NCR

3 NCR Closing Process Tracking

1 Identify deffects

4 Output the data for saving

1 2

4 3

NCR

Control

Mobile APP

Start an NCR

NCR Statics and

Data Output

Transfer to Person in

Charge

Close the NCR

with Evidence

17

Build

Model

Generate Drawings

Produce Paste QR

code Transfer Tracking

Install Tracking

Visual Display

2. Smart Construction

Tracking material transfer process.

Automatically record the installation completion time

Check the construction schedule with real completion time.

Material Tracking

18

Safety Management – Virtual Reality Technology

VR Safety Training

Emergency rescue skills

Risk-free experience

Gaming-style, more

attractive

2. Smart Construction

19

System working principle

diagram

Site environment

monitoring screen

View real-time

environment data On-site spray facility

2. Smart Construction

Air quality monitoring

Noise monitoring

Automated control

Real-time Data transfer

Environmental Protection

Temperature monitoring

Wind monitoring

3 New Building Materials

21

3. Building materials innovation

Self-healing concrete

Self-repairing and

regeneration

use microfiber

22

3. Building materials innovation

Polycarbonate panel

Low energy consumption

Improved impact resistance

23

3. Building materials innovation

Self-luminous cement

Translucent wood Anti-seismic reinforcement

4 Innovation of Equipment

25

4. Construction machinery innovation

Working Platform

High Bearing Capacity

Integrate Platform

Modular

26

27

Key Technology:

Rail power supply

Switching system

Centralized dispatch control

4. Construction machinery innovation

Vertical Transportation – Multi-Cage Hoist

28

4. Construction machinery innovation

save climbing time

Save space on

working platform

Save cost

Vertical Transportation – Rotary Tower Crane

29

4. Construction machinery innovation

Vertical Escape Device – Magnetic Sliding Pole

5 Construction Management

31

Core Wall

Concrete Slab

Steel Frame

Metal Deck

Fireproofing Facade

5. Construction Management – Compact Overlapping Management

32

Mat Foundation ( - L6 )

Start 2016-4-2

Ground Floor

Core Wall ( L92 )

27 days

10 weeks

17 months

Crown 2018-06-30

5 months

5. Construction Management – Compact Overlapping Management

33

5. Construction Management – Compact Overlapping Management

Building 500 ≥ height ≥ 400 Core Topping Out Completion

Signature Tower 26 months 3 years

Average Durations for 17 Others 40 months 6 years