7/25/2019 OceanStor S5600T&S5800T&S6800T Storage System V100R005 Quick Installation Guide (SAN Volume) 04
1/18
Overview
1
Issue: 04
Date: 2014-10-30
This document guides you through a time-saving process for installing a storage system. For more information, see
the OceanStor S5600T&S5800T&S6800T Storage System V100R005 Installation Guide.
a
Copyright Huawei Technologies Co., Ltd. 2014All rights reserved.
Introduction to the OceanStor T Series
Before You Start
OceanStor S5600T&S5800T&S6800TStorage SystemV100R005Quick Installation Guide (SAN Volume)
HUAWEI OceanStor T series storage systems are innovative mid-range and high-end offerings that are ready to
meet your current and future storage requirements. They are designed to provide medium- and large-scale
enterprises with improved storage performance, efficiency, security, scalability, and manageability.
Where to get helpb
Feedbackc
You can obtain the product documentation from the documentation CD-ROM delivered with the product or from
http://enterprise.huawei.com. You can also register for a Huawei support account at this website to browse and
download valuable information and sign up for product updates.
Your feedback is important to us. If you have any comments about this document, please submit them to us on
the Huawei Enterprise website.
7/25/2019 OceanStor S5600T&S5800T&S6800T Storage System V100R005 Quick Installation Guide (SAN Volume) 04
2/18
Installation Process
Safety Information
Do not operate devices or handle cables on a stormy day.
To avoid eye injuries, do not look into the optical outlets without eye protection.
Arrange for at least three persons to carry and install a fully configured enclosure to avoidpersonal injury or device damage.
Do not wear an ESD wrist strap during power-on to avoid electric shocks.
Scenario 1 Wearing an ESD wrist strap whose
ground terminal is a plugScenario 2 Wearing an ESD wrist strap whose
ground terminal is a metal clip
Initializing the Storage System
Checking installation tools
Checking circuit breakers
Checking components
Planning device installation positions
Removing filler panels
Determining device installationpositions using installation templates
Installing adjustable guide rails
Installing the controller enclosureand disk enclosures into the cabinet
Installing the cable tray
A generic viewof cable connections
Connecting ground cables
Connecting enclosures
Connecting the storage systemto an application server
Connecting to the maintenanceterminal
Connecting power cables
Checking device installation
Checking cable connections
Switching on externalpower supplies
Pressing the power buttonon either controller
Checking status indicatorson the enclosures
Installing front panels
Installation Preparations
Installing Devices
Connecting Cables
Powering On the
Storage System
Checking
Hardware Installation
(Optional) Installing Host Software
Installing filler panels
2
CAUTION
7/25/2019 OceanStor S5600T&S5800T&S6800T Storage System V100R005 Quick Installation Guide (SAN Volume) 04
3/18
Checking installation tools
c Checking components
Checking circuit breakers
Adjustable guide railsFloating nut and M6
screw
Multi-mode optical
fiber cable
Mini SAS cable
Network cable
Front panel of a 2 U
controller enclosure
ba
Installation template
(for 2 U devices)
Ground cable
Controller enclosure(4 U)Front panel of a 4 U
controller enclosure
Disk enclosure (2 U)
Disk enclosure (4 U)
1 Installation Preparations
The following installation tools are required:
Phillips screwdriver (M3 to M6)
Flat-head screwdriver (M3 to M6)
Diagonal pliers
Floating nut mounting bar
A storage system power failure may cause devices
connected to the same circuit breaker to power off
unexpectedly. Therefore, ensure that the storage systempower supplies have functioning circuit breakers with the
following amps:
AC power: 16 A
DC power: 32 A
For information about the full list of required components, see the Packing List. The bag containing the
Packing Listis attached to the surface of the box.
Installation template
(for 4 U devices)
Cable tray (2 U)
3
NOTICE
7/25/2019 OceanStor S5600T&S5800T&S6800T Storage System V100R005 Quick Installation Guide (SAN Volume) 04
4/18
Recommended installation positions
2a Planning device installation posi tions
Total required cabinet space = 4 U + 2 U x (Number of 2 U disk enclosures) + 4 U x (Number of 4 U disk
enclosures)
Note: The height of the storage system is measured by the unit of U. 1 U equals 44.5 mm (1.75 inches).
Tips
Install the controller
enclosure in the middle of an
empty 42 U cabinet, namely
between the 17 U mark and
the 22 U mark.
Be certain to next install
other devices below the
controller to prevent the
cabinet from becoming
top heavy.
2b Removing fil ler panels
2 Installing Devices
Controller enclosure (4 U)
Disk enclosure (4 U)
Disk enclosure (4 U)
Disk enclosure (4 U)
Disk enclosure (4 U)
4
7/25/2019 OceanStor S5600T&S5800T&S6800T Storage System V100R005 Quick Installation Guide (SAN Volume) 04
5/18
Determining device installation posit ions using installation templatesc
Scenario 2
Installation position of a 4 U device
Scenario 1
Installation position of a 2 U device
Low base of the guide rail
On the mounting bars, use a marker to mark the holes where screws will be installed to secure the
controller and disk enclosures.
Installation positions of 2 U device fixing screws
Installation positions of guide rail fixing screws
Low base of the guide rail
Installation positions of 4 U device fixing screws
Installation positions of guide rail fixing screws
Installation positions of floating nuts
5
NOTE
7/25/2019 OceanStor S5600T&S5800T&S6800T Storage System V100R005 Quick Installation Guide (SAN Volume) 04
6/18
Installing adjustable guide railsd
Scenario 2
Attaching adjustable guide rails for a 4 U device
Scenario 1
Attaching adjustable guide rails for a 2 U device
Front
Rear
Front
Rear
The adjustable guide rails are 600 mm (23.62 in.) to 900 mm (35.43 in.) long. They are designed to fit into
cabinets with depth ranging from 800 mm (31.50 in.) to 1100 mm (43.34 in.).
The adjustable guide rails are preconfigured with positioning pins applicable to square holes only. For
round holes, replace the positioning pins.
Two paired adjustable guide rails must be positioned exactly parallel to one another.
6
7/25/2019 OceanStor S5600T&S5800T&S6800T Storage System V100R005 Quick Installation Guide (SAN Volume) 04
7/18
2e Installing the controller enclosure and disk enclosures into the cabinet
To avoid device damage, do not stack any components but install them onto guide rails.
Install a disk enclosure onto the adjustable guide rails using the same method as installing the
controller enclosure.
2f
Installing the cable tray
NOTE
For a cabinet of 1 m (39.4 inches) deep or deeper, if the controller enclosure rear is more than 70 mm (2.758
inches) away from the rear columns or if the rear columns are more than 150 mm (5.91 inches) away from
the rear cabinet door, the cable tray must be installed on the rear columns of the cabinet.
For a cabinet of 1 m (39.4 inches) deep or deeper, if the controller enclosure rear is 70 mm (2.758 inches) orless away from the rear columns or if the rear columns are 150 mm (5.91 inches) or less away from the rear
cabinet door, the cable tray must be installed on the controller enclosure.
For a cabinet of 800 mm (31.50 inches) deep, the cable tray must be installed on the controller enclosure.
Scenario 1 Installing the cable tray onto the rear columns
Front
Rear
7
NOTICE
7/25/2019 OceanStor S5600T&S5800T&S6800T Storage System V100R005 Quick Installation Guide (SAN Volume) 04
8/18
2g Installing filler panels
Scenario 2
Installing the cable tray onto the controller
8
7/25/2019 OceanStor S5600T&S5800T&S6800T Storage System V100R005 Quick Installation Guide (SAN Volume) 04
9/18
3a
A generic view of cable connections
3b Connecting ground cables
3 Connecting Cables
Maintenanceterminal
Applicationserver
Diskenclosure
Controllerenclosure
Groundcable
Externalpower
Externalpower
9
7/25/2019 OceanStor S5600T&S5800T&S6800T Storage System V100R005 Quick Installation Guide (SAN Volume) 04
10/18
Slot B0 Slot A0
3c Connecting enclosures
Controller
enclosure
Expansionmodule A
Disk
enclosure 1
Disk
enclosure 2
Disk
Enclosure 3
Disk
Enclosure 4
Expansionmodule B
Port P0 on controller A (B) must be connected to port PRI on expansion module A (B) on the configuration
disk enclosure (the one with coffer disks).
All the EXP ports on the storage system connect only to the PRI ports. For a storage system with two or more disk enclosures, set up multiple loops based on the number of
expansion ports on the controller enclosure, and evenly allocate those disk enclosures to the loops. Connect disk enclosures except the configuration disk enclosure in one loop over two separate links for
optimal network reliability.
10
7/25/2019 OceanStor S5600T&S5800T&S6800T Storage System V100R005 Quick Installation Guide (SAN Volume) 04
11/18
3d
Connecting the storage system to an application server
Scenario 1 Directly connecting host ports to the application server
Application
server
Application
server
Controller
enclosure
Controller
enclosure
The controller enclosure can connect to application servers through 1 Gbit/s iSCSI, 10 Gbit/s TOE, 10 Gbit/s
FCoE, and 8 Gbit/s FC host ports.
iSCSI cable connection
Optical fiber cable connection
11
7/25/2019 OceanStor S5600T&S5800T&S6800T Storage System V100R005 Quick Installation Guide (SAN Volume) 04
12/18
Scenario 2 Connecting host ports to the application server through switches iSCSI cable connection
Optical fiber cable connection
Application
server
Ethernet
switch
Ethernet
switch
Controller
enclosure
Application
server
Controller
enclosure
Fibre Channel
switch
Fibre Channel
switch
12
7/25/2019 OceanStor S5600T&S5800T&S6800T Storage System V100R005 Quick Installation Guide (SAN Volume) 04
13/18
3e
Connecting to the maintenance terminal
3f Connecting power cables
Scenario 1 Connecting an AC power cable
Complete view of the AC power cables
After connecting a serial port on the storage system to the maintenance terminal through a serial cable,
you can then manage and maintain the storage system from the maintenance terminal.
During initial configuration, set an IP address for the management network port through the serial port.
Maintenance
terminal
Controller
enclosure
Disk
enclosure
Controller
enclosure
External
power
AC devices can connect only to AC power supplies, and DC devices can connect only to DC power supplies.
To ensure a high availability of the storage system and avoid unexpected power failures, connect the storage
system to two routes of power supplies on either side or both sides.
External
power
13
NOTICE
7/25/2019 OceanStor S5600T&S5800T&S6800T Storage System V100R005 Quick Installation Guide (SAN Volume) 04
14/18
Scenario 2 Connecting a DC power cable
Complete view of the DC power cables
When you connect DC power cables, ensure that the black cable leading from the anode of the DC power
source connects to the RTN (+) terminal and that the blue cable leading from the cathode of the DC power
source connects to the NEG (-) terminal.
Disk
enclosure
Controller
enclosure
DC PDU
14
7/25/2019 OceanStor S5600T&S5800T&S6800T Storage System V100R005 Quick Installation Guide (SAN Volume) 04
15/18
Checking cable connections
4a Checking device installation
4b
Check Item Normal Abnormal
Ground cable
Optical fiber cable
Mini SAS cable
Network cable
Serial cable
The cable is fully inserted and secured. The cable is loose or disconnected.
AC power cable
The AC power cables for each
controller enclosure or disk enclosure
are connected to two separate power
supplies for redundancy.
The AC power cables are secured
with plastic buckles.
The AC power cables for each
controller enclosure or disk enclosure
are connected to the same power
supply.
The AC power cables are not secured
with plastic buckles.
DC power cable
The OT terminal of the black cable
connects to the RTN (+) terminal and
the OT terminal of the blue cable
connects to the NEG (-) terminal.
The OT terminal of the blue cable
connects to the RTN (+) terminal and the
OT terminal of the black cable connects to
the NEG (-) terminal.
4 Checking Hardware Installation
Check Item Normal Abnormal
Controller enclosure The device sits stably on the guide
rails without displacement.
Screws are properly secured.
The device slants or cannot be detected.
Screws are loose or have fallen off.Disk enclosure
The power-on process takes three to five minutes. The system is completely powered on until the power
indicator of controller enclosure does not blink continually.
To avoid electric shocks, do not wear an ESD wrist strap when the storage system is powering on.
Do not adjust mini SAS cable connections between enclosures after power-on. Otherwise the storage
system may become abnormal.
5 Powering On the Storage System
Follow the correct power-on sequence of the storage system: switch on external power supplies press
the power button on either controller module switch on the Ethernet or Fibre Channel switch switch
on the application servers.
Follow the correct power-off sequence of the storage system: stop host services press and hold the
power button on either controller module until the system is completely powered off (five seconds)
disconnect the controller enclosure and the disk enclosures from their power supplies.
5a
Switching on external power supplies
Switch on external power supplies in the following sequence:
disk enclosures controller enclosure switches (for a SAN) application server.
15
7/25/2019 OceanStor S5600T&S5800T&S6800T Storage System V100R005 Quick Installation Guide (SAN Volume) 04
16/18
5b
Pressing the power button on either controller
5c
Checking status indicators on the enclosures
After you have powered on a disk enclosure or the controller enclosure, check that all disks are
working correctly (no alarm/location indicator is steady red).
Power indicator of the diskenclosure: steady green
Alarm indicator of thedisk enclosure: off
Alarm/Location indicatorof the disk enclosure: off
Power indicator of the controllerenclosure: steady green
Disk alarm/locationindicator: steady green
Controller enclosure
Disk enclosure
For details and rectification suggestions on the indicators, refer to the OceanStor
S2200T&S2600T&S5500T&S5600T&S5800T&S6800T Storage System V100R005 Quick Maintenance Guide.
Controller enclosure
Scenario 1 Turn on the switches of the power
distribution boxScenario 2 Turn on the switch of the PDU
Front
Front
Rear
Rear
16
NOTICE
7/25/2019 OceanStor S5600T&S5800T&S6800T Storage System V100R005 Quick Installation Guide (SAN Volume) 04
17/18
Scenario 2 Installing the front panel for a 4 U device
Scenario 1 Installing the front panel for a 2 U device
5d
Installing front panels
17
7/25/2019 OceanStor S5600T&S5800T&S6800T Storage System V100R005 Quick Installation Guide (SAN Volume) 04
18/18
18
Install the following host software programs on the application server:
1. Initiator, an optional program for iSCSI host ports. For details about installing the Initiator program, refer to
the OceanStor S5600T&S5800T&S6800T Storage System V100R005 Installation Guide.
2. UltraPath, a multipathing program. For details about installing the UltraPath, refer to the OceanStor
UltraPath for Windows User Guide, OceanStor UltraPath for Linux User Guide, or OceanStor UltraPath for
AIX User Guide.
3. UltraAPM, another optional program. For details about installing the UltraAPM, refer to the OceanStor
UltraAPM User Guide.
Obtain the documentation for the UltraAPM and UltraPath from the delivery-attached CD-ROM.
7 (Optional) Installing Host Software
Contacting Huawei Technical Support
For details about initializing the storage system, refer to the OceanStor S5600T&S5800T&S6800T
Storage System V100R005 Installation Guide.
The default user name and password of the storage system are adminandAdmin@storage
respectively. You are advised to change the default login password immediately after you have logged in to
the storage system for the first time and periodically change your login password in the future.
This reduces the password leakage risks.
6 Initializing the Storage System
After you have powered on the storage system, complete the following initialization steps:
1. Change the IP address of the management network port using the command-line interface (CLI). Before
doing this, connect the serial port on the controller enclosure to the maintenance terminal.
2. Install the ISM on the maintenance terminal.
3. On the ISM, follow the Initial Configuration wizard to change the administrator's password, configure ratefor Fibre Channel host ports, configure IP addresses and route information for iSCSI host ports, and
import license files. If you do not perform the initial configuration as prompted, follow-up configuration
and use of services will be affected.
Huawei customer service center
Address: Huawei Industrial Base, Bantian, Longgang, Shenzhen 518129, People's Republic of China
Website: http://enterprise.huawei.com
Local Huawei technical support personnel
Obtain contact information for local Huawei offices at http://support.huawei.com/enterprise/.
Huawei storage product info rmation self-service platform
http://enterprise.huawei.com/topic/Self_service_2013_en/knowledge.html