OPMA 5364Project Management
Part 5
Project Scheduling
Part 5 - Project Scheduling 2
Topic Outline: Project Scheduling
• Identifying relationships among activities• Project network diagrams• Identifying critical paths and critical activities• Determining activity slack times• Gantt charts• Project scheduling exercise• Microsoft Project example• Other precedence relationships• Management of project schedules
Part 5 - Project Scheduling 3
Identifying Activity Relationships
In addition to estimating activity time duration and cost, relationships among activities must also be identified
Relationships:• What task immediately precedes this task?• What task immediately follows this task?• What tasks can be done concurrently?
These are referred to as precedence relationships
The main relationship for scheduling is ‘what task immediately precedes the current task,’ which is referred to as the immediate predecessor task
Part 5 - Project Scheduling 4
Project Network Diagrams
• Network diagrams show the precedence relationships among activities
• It’s easier to understand these relationships graphically
• Network diagrams help to understand the flow of work in a project
• Network diagrams are a useful tool for project planning and control, as well as for scheduling
• One (perhaps exaggerated) claim is that the network represents ¾ of the planning process
Part 5 - Project Scheduling 5
2 Versions of Network Diagrams
Activity-on-Arrow (AOA) networks– also called Arrow Diagramming Method (ADM)– simpler for projects with many dependencies– emphasizes events; milestones can be easily flagged– sometimes requires dummy activities
Activity-on-Node (AON) networks– also called Precedence Diagramming Method (PDM)– easier to draw for simple projects– emphasizes activities– no dummy activities
Part 5 - Project Scheduling 6
Activities vs. Events
• Activity – a chunk of work that is part of the project; an activity may be broken down into multiple subactivities
• Event – a significant point in time during the project, such as a milestone event; an event could be the time at which an activity is completed or the time at which related concurrent activities have all completed
• Dummy Activity – an artificial activity with zero time duration that only shows a precedence relationship among activities
Part 5 - Project Scheduling 7
Activity-on-Arrow (AOA) Networks
bc
d
e
fg
Activity Predecessormnrs
__
m, nn
m r
n s
k
j
k
j
j
k
or
Dashed lines are called dummy activities
Part 5 - Project Scheduling 8
1 2Excavate
& pour footings
Pour foundation
Install drains
Project Network for House Construction
(AOA network)
3
6
7
4
8
9
5
10
11
12
16
1813
1715
14
Install roughelectrical & plumbing
Pourbasement
floorInstall
cooling &heating
Erectframe & roof
Laybrickwork
Laystormdrains
Installdrywall
Layflooring
Installfinished
plumbing
Installkitchen
equipmentPaint
Finishroof
Installroof
drainage
Finishgrading
Finishfloors
Pourwalks;
Landscape
Finishelectrical
work
Finishcarpeting
Part 5 - Project Scheduling 9
Project Network Example
Task Pred. Dur. Task Pred. Dur.
a -- 4 g c,d 1
b -- 3 h e 4
c a 3 i f 5
d a 2 j e,g 6
e b 6 k h,i 1
f b 4
Draw AOA and AON networks
Part 5 - Project Scheduling 10
Activity-on-Arrow (AOA or ADM) Network(Initial Network)
Part 5 - Project Scheduling 11
Activity-on-Arrow (AOA or ADM) Network(Final Network)
a
b
d
c
gj
k
i
h
f
e
Part 5 - Project Scheduling 12
Activity-on-Node (AON or PDM) Network
Part 5 - Project Scheduling 13
A project has the following activities and precedence relationships:
Predecessor Predecessor
Activity Activities Activity Activitiesa -- f c,eb a g bc a h b,dd a i b,de b j f,g,h
Draw AOA and AON networks
Project Network Example
Part 5 - Project Scheduling 14
Activity on Arrow(Initial Network)
Part 5 - Project Scheduling 15
Activity on Arrow(Final Network)
a
b
c
d
e
f
g
hi
j
Part 5 - Project Scheduling 16
Activity on Node
Part 5 - Project Scheduling 17
Critical Pathpath – any route along the network from start to
finish
Critical Path – path with the longest total duration
This is the shortest time in which the project can be completed.
Critical Activity – an activity on the critical path
*If a critical activity is delayed, the entire project will be delayed. Close attention must be given to critical activities to prevent project delay. There may be more than one critical path.
Part 5 - Project Scheduling 18
Critical Path
Brute force approach to finding critical path:
1. identify all possible paths from start to finish
2. sum up durations for each path
3. largest total indicates critical path
(This approach is inefficient, but is instructive)
Part 5 - Project Scheduling 19
1
2 6
4 7
53
b = 2
d = 4
g = 9
h = 9
f = 8c = 5
a = 6
k = 6
j = 7
i = 4
e = 3
Part 5 - Project Scheduling 20
Slack Times
• EST—Earliest Start Time– Largest EFT of all predecessors
• EFT—Earliest Finish Time– EST + duration for this task
• LFT—Latest Finish Time– Smallest LST of following tasks
• LST—Latest Start Time– LFT – duration for this task
• Slack—LFT – EFT or LST – EST
Part 5 - Project Scheduling 21
Computing Slack Times
Task = duration
slack = xxxx
EST EFT
LST LFT
Part 5 - Project Scheduling 22
Slack Times Example
Task Pred. Dur. Task Pred. Dur.
a -- 4 g c,d 1
b -- 3 h e 4
c a 3 i f 5
d a 2 j e,g 6
e b 6 k h,i 1
f b 4
For each task, compute ES, EF, LF, LS, Slack
Part 5 - Project Scheduling 23
Start Finish
a=4slack=
b=3slack=
c=3slack=
d=2slack=
e=6slack=
f=4slack=
g=1slack=
h=4slack=
i=5slack=
j=6slack=
k=1slack=
Task=durslack=xxx
EST EFT
LFTLST
Part 5 - Project Scheduling 24
Gantt Charts
• The main purpose of a Gantt chart is to display the schedule of activities
• They are easy to understand• They are flexible in that you can also show other
information on the chart, such as resources required, who is responsible, critical activities, percent complete, etc.
• All project management software packages will create Gantt charts
Part 5 - Project Scheduling 25
Gantt ChartActivity
a
b
c
d
e
f
g
h
i
Time (weeks)
Part 5 - Project Scheduling 26
Project Scheduling Exercise
DynaTech Equipment Corp. case• Divide into small groups• Read case (5 minutes)• Assignment: (40 minutes)
– List the immediate predecessors and WBS number for each activity
– Draw project network diagram (lowest level)– Draw Gantt chart– Determine project completion time
Part 5 - Project Scheduling 27
Microsoft Project Example
Part 5 - Project Scheduling 28
Microsoft Project Example
Part 5 - Project Scheduling 29
Microsoft Project Example
Part 5 - Project Scheduling 30
Other Precedence Relationships
• The typical precedence relationship between two activities is that when the first activity has finished, then the second activity can start. In this case the first activity is called the immediate predecessor of the second activity.
• This is referred to as a Finish-to-Start linkage.• Other precedence relationships, or linkages, are
also possible.• Lead and lag times are also possible.
Part 5 - Project Scheduling 31
Other Precedence Relationships
Finish-to-StartLinkage (FS)
Start-to-StartLinkage (SS)
Finish-to-FinishLinkage (FF)
Start-to-FinishLinkage (SF)
Activity 1
Activity 2
Activity 1
Activity 2
Activity 1
Activity 2
Activity 1
Activity 2
Lead and Lag Times
Lead (-) and Lag (+) times are expressed as part of the immediate predecessor notation. So 1FS+3 listed for the immediate predecessor of Activity 2 means that Activity 1 is the predecessor with a Finish-to-Start linkage and a 3-day lag time after Activity 1 finishes before Activity 2 can start.
1FS-3 means that Activity 2 can start 3 days before Activity 1 finishes.
1FF+3; 1SF-5; 1SS+4
Part 5 - Project Scheduling 32
Management of Project Schedules
• Meeting project deadlines is often the most important goal in project management
• Careful scheduling of project activities is critical to meeting the project due date
• Effective project managers should have a good understanding of the issues involved in activity scheduling
Part 5 - Project Scheduling 33
Ineffective Scheduling
Notice: