Post on 14-May-2015
transcript
P.K.AgarwalDy. General Manager
Power Grid Corporation of India, Indiapk.agarwal@nrldc.org
Shift from"traditional way of thinking"
To"new way of thinking."
2SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA
Low speed data acquisition - once in 2 to 10 sec.
No information on happening within sub-second.
Steady state observability of the system.
X-ray quality visibility of the system.
3SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA
High speed data acquisition - 50 samples or more
per second.
Gets the pulse of the system.
Dynamic observability of the system.
MRI of the power system.
Wide area monitoring.
4SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA
From overview to detailed view.
From steady state to dynamic state.
From state estimation to state calculation.
From local view to system wide view.
From localized protection to system protection
From x-ray of the system to MRI of the system.
From supervision to health monitoring.
SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA5
More Data
Better Visualization.
Frequent updation of values.
Wide coverage area.
Panoramic inside view.
SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA6
Phasor measurement System and Phasor Measurement Unit (PMU).
Phasor was mathematically presented by Charles Proteus Steinmetz
in 1983.
PMU was invented in Virginia Tech University by Dr. Arun G. Phadke
and Dr. James S. Thorp in 1988.
First prototype was built by Virginia Tech in 1992.
Implementation started in 1995 at TVA and BPA.
Proved a highly useful tool in investigation of 1996 and 2003
blackouts.
SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA7
Source – wikipedia.org
Phasor Measurement System
Enhanced Visualization by Angular Measurement.
Time Synchronized & Time Aligned Measurement.
Wide Area Measurement System
8SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA
9SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA
10SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA
SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA11
SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA12
Plot of frequency value SCADA data during tripping of Rihand project (5 sec sample)
Portion of plot expanded with 40 mSec data
SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA13
14SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA
SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA15
Indicates relative strengths of system of buses.
Rapid increase in angle warns for system event
(generation or transmission loss).
Captures pulse of the system.
Provides a signature of system state.
16SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA
17SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA
SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA18
SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA19
20SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA
SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA21
SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA22
23SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA
Time aligning of phasor data done at control center in PDC.
Each packet from PMU has second of century stamp.
PDC assemble same time stamp data and produces packets for further use.
SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA24
Allows us to see dynamics not visible in traditional SCADA measurement.
Enables accurate event analysis by precise comparison.
SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA25
SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA26
27SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA
Like traffic cameras on transmission highways.
Visualize traffic density as well as pattern.
Improve situational awareness.
Provide early warning of subtlest beginning of
dynamic interaction.
Provides root cause analysis of the events.
SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA28
PMUs synchronised with GPS.
Inputs taken from existing CT/PTs.
Fast communication channels like FO.
Phasor data concentrator.
Data management and services software.
29SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA
WAMS Architecture
30SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA
31SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA
SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA32
SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA33
PMU Locations Under the NR Pilot Project
• HVDC Vidhyachal BTB – In the major
thermal generation complex
• 400 kV Kanpur- Transmission Pooling
Station
• 400 kV Dadri- Load Center
• 400 kV Moga- Hydro Pooling Station
1. PDC
2. Data Historian
3. LAN equipments
4. Operator Console.
34SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA
35SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA
Components:-
1. Global Positioning System2. Phasor Measuerment Unit.
SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA36
Present
◦ Forensics
◦ Supplemental Information
◦ Learning
◦ Wide-Area Visibility
◦ Model validation.
37SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA
Near Future◦ Early Warning & Suggested Actions
◦ State Estimator Robustness
◦ Automated Event Reports and Event Playback
Longer Term◦ Backup to SCADA
◦ Smart Grid
◦ Special Protection
SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA38
39SCADA ASIA SUMMIT 2010 - Paradigm Shift in Power System SCADA