Trail Route and Phasing Examples of Similar Trails Key Facts and Current Status Next Steps
City Hall
Port Orange Gym
FPL Magnolia Substation site
Phase 1Future Phases
Nova Road
I-95
Common across the Country
Recognized by National Assc. of Homebuilders as #1 amenity
Common adjacent to homes
Location: FPL transmission corridor
Length: 6,000 feet (1.14 miles)
Width: 12’ paved lane with 2’ shoulders, 16’ total
Separation: 150’+ distance from homes
Material: Asphalt with stabilized base, gravel shoulders
Cost: $568,000 total. 25% City share = $142,000
Furnishings: Lighting, signage, benches, trash receptacles at each end
Uses: Pedestrians and non-motorized vehicles only Hours: Daylight only, like other City parks Security: Patrolled by PD
Source: Trail Design Guidelines, Portland Parks & Recreation Dept., 2009
2003 Project submitted to MPO for funding
2006 Feasibility study completed
2009 Project adopted in Port Orange CIP
2010 LAP Agreement considered by City Council
On-going discussions with FPL
Presentation to Countryside HOA (4-19-10)
Discussions with School District as alternative
Working to address privacy, security, and liability concerns
2010 Appraise property along
easement corridor Secure easements for public
access Select design consultant Survey trail corridor Begin design
2011 Complete design Obtain bids for construction Begin construction
2012 Complete construction Grand Opening