Pre-Contract Risk Managementan ACE guide
Pre-Contract Risk Management - An ACE guide
Association for Consultancy and EngineeringAlliance House 12 Caxton Street London SW1H 0QLT: 020 7222 6557F: 020 7990 9202consult@acenet.co.ukwww.acenet.co.uk
02
ContentsIntroductionPre-Contract Assessment ProcessStage I – IdentifyStage II – EvaluateStage III – MitigateStage IV - TransferAppendix
344788
© Association for Consultancy and Engineering No part of this report may be copied either in whole or in part without the permission in writing of the Association for Consultancy and Engineering.
Pre-Contract Risk Management - An ACE guide 03
The need for risk assessmentWhatever altruistic motives consultants may have, one of the primary objectives of operating a business is to generate profit, which enables business to reward proprietors and employees appropriately. Generating profit is a function of good management and minimising risk is one way of contributing towards making a profit.
Increases in premiums and excesses payable in respect of professional indemnity (PI) insurance have always received a considerable amount of publicity. Such increases are caused by factors such as the performance of the stock market, the attractiveness of PI insurance to insurers, and the industry’s and individual firms’ claims experience. Whilst the first two factors may be more difficult to address, the claims issue can be addressed through the implementation of more effective risk management systems. Furthermore, even where PI insurance is available, there are undoubtedly exclusions to such policies which need to be taken into account when taking on work.
The results of an ACE insurance/risk management survey showed that only 46% of responders have formalised risk management and quality assurance systems in place. A large majority (92%) do not have a full time risk manager who has no other job function.
Risk management practices should form an integral part of a consultant’s quality management system procedure for project appointment contract control. Good risk management requires senior management involvement and control as work progresses; it also requires increased project staff awareness and participation at project reviews.
It is for this reason that ACE has prepared a number of guides relating to project risk management. This first document relates to the pre-contractual stage of the project life cycle.
Introduction The followings headings and questions are intended to prompt the reader to consider the risks involved when considering whether to bid for or take on a new project. This list is not exhaustive and there may be other risks particular to your project that will need to be considered. When all risks are identified they can then be evaluated and a strategy put in place to either mitigate or transfer those risks.
It is essential to keep in mind that risk management is not a one-off exercise but a constant management process which needs to be repeated as often as the needs of a particular project require. Risk management does not cease until all disputes have been resolved and the files finally closed.
Where to go for further informationACE member companies who have further questions about contract terms and conditions can contact ACE on 020 7222 6557.
Pre-Contract Risk Management - An ACE guide
Should you look to win this contract?One of the first things that should be considered when invited to submit a tender is to consider pre-contractual issues and to decide whether you should even bid for a particular project. This decision can only be made once an assessment has been made of all the circumstances of the case.
The following process is generally used for the process of risk management, namely:
• Identify the risk• Evaluate the risk• Mitigate the risk by:
• Declining it• Accepting it (and costing for it)• Reducing it
• Transfer the risk
The process should be kept under constant review and revisited at pre-determined trigger points, e.g.:
• Expression of interest• Tender/bid stage• Contract issue stage• Design stage• Construction stage• Commissioning stage• Post project review, i.e. lessons learnt
The first step, when invited to bid for a particular project, is to consider the risks that may be associated with the project. This can be done by, for instance, asking the following non-exhaustive questions:
Consider the Contractual Parties
Do you know your client?
• Is this a new client? If they are an existing client, how good is your relationship?
• Are they prompt payers?• What is their interest in the project?• Is your client the contractor? If so, are they likely to
have adequate contingencies in the tender or are they known for lowest price bidding?
• What is their financial status? Are they financially sound?
• What financial information is available? Is it significantly out of date? If so, has the client provided a satisfactory reason for that?
• Is the client contracting through a special purpose vehicle (SPV) set up for this project alone?
• Do they have experience on this type of project?• Are they competent?• Will they understand their statutory duties?• Are there any cultural differences?• Is the nominated client a legal entity? If not, find
out who the correct contracting party is going to be. Ask the above questions in respect of that entity.
Is your client the ultimate client? If not, who is the ultimate client?
• Is it a private company?• Is it a public body?• Have you worked with them before?• What research have you done on them?• Where are they based?• Could they affect your reputation adversely?• How tight is their budget?
Pre-Contract Assessment Process
Stage I – Identify
04
Pre-Contract Risk Management - An ACE guide
Do you know who else will be involved in the project?
• Will you be acting as a sub-consultant to another project team member?
• Will you be jointly and severally liable?• Do you know the PI arrangements of the other
parties?• Have you worked with them before?• Are there back-to-back contractual obligations?• Are there likely to be any software compatibility
issues within the project team?
Service Scope and Location
What are you being asked to do?
• Does this fit your business plan?• What are the objectives?• Is the brief/scope clear and complete?• Are the services required particularly risky or
unusual in nature? Would this affect your ability to complete the project successfully?
• Do any of the requirements amount to a fitness for purpose obligation as a matter of fact? If so, have you discussed the implications with your PI insurance brokers?
• What is the scope and complexity of the work? Is the complexity likely to grow or shrink?
• Is the location easily accessible?• Are there any environmental issues to consider
– pollution, etc?• Can you provide the services?• Can they be delivered on time?• Will you need to appoint specialist sub-
consultants? • Are there any regulatory issues, e.g. health and
safety, etc?
Have you done it before?
• Is this a new territory?• If yes, have you checked the territorial limits of
your PI policy?• If not, do you have sufficient similar experience to
give you confidence?• Are those with experience still with you or still
available?• Are you familiar with local legislation, taxes,
custom and practice?• What are the contractual requirements?• Does the project involve new technology?
Staffing Requirements
Do you have the resources and the competence?
• Does it require 24/7 support?• Will your resources be available in the right
timescale?• Will you have built in redundancy if a key source
goes missing? • Are you overly reliant on a specific individual?• Do you need to sub-contract?• Do you have a project manager?
Other Commercial Issues
Are the rewards worth the risk?
• Have you understood the risks?• What is the value of the contract to you?• If it is a loss leader, will it produce long term profit?• Can it affect your reputation negatively?• Have you considered changes in the economy/
market?• Is this state of the art/new technology?• What is the likely impact on cash flow?
Do you know the procurement route?
• Is the procurement/contract on the same basis from the ultimate client?
• How are the risks allocated further down the supply chain?
Who is the competition?
• How will you compete: through your fee or service?
• Can you realistically compete?• Have you completed a SWOT analysis?• Is your assessment of the competition truly
impartial?
Why are you doing this?
• Is it high profile?• Do you understand the business?• Are there reputation risks?• Is it a learning opportunity?
05
Pre-Contract Risk Management - An ACE guide
Will you be paid enough?
• Are there any obstacles to payment that are outside your control?
• Will you remain cash positive or, alternatively, will the cash profile be acceptable?
• Are you aware of your tax liabilities?• Will your price be squeezed in future negotiations?• Is your level of profit adequate against inflation and
currency fluctuations?
What are your contractual obligations?
• Have you seen the proposed agreement?• If the proposed agreement is unreasonable, have
you accounted for the fact that legal advice may be required in your fees?
• Is there a ‘reasonable skill and care’ duty?• Are you being requested to indemnify and/or hold
the client harmless from particular losses?• Is there a fitness for purpose, liquidated damages,
or other penalty clause?• Is any kind of guarantee required?• Are collateral warranties required?• Are you being asked to concede copyright?• How is the team to be structured – JV/
consortium?• Does your PI policy meet the requirements of the
contract? • Will you be novated? If so, who will you be
novated to? For example, does the client generally use experienced contractors?
• Have you seen the proposed novation agreement?
What is your financial liability
• What is your financial limit of liability under the contract?
• Does your PI policy cover your financial liability under the contract?
Having identified the risks, you are in a position to evaluate their significance to your business. In financial terms, what represents a high risk to you?
Risk exposure
What is the maximum exposure to a loss arising from the risks identified?
• In financial terms?• In reputation terms? • In interruption risks? • Liquidated damages?• Fines and penalties?
Likelihood of risk occurrence
What is the probability of risk?
• High (for example, 80 – 100% probable)• Medium (for example 20 – 80% probable)• Low (for example 0 – 20% probable)
What is the impact to your business?
What might the impact of the risk be? This will relate to the scale of the project in relation to your total workload.
• High (for example, 80 – 100% probable)• Medium (for example 20 – 80% probable)• Low (for example 0 – 20% probable)
An example pro forma risk register is shown in the Appendix. This can be used independently to identify and manage your risks. An example of how the risk register can be used is also shown in the Appendix. The risk register should be a ‘live’ document and reviewed on a regular basis to track and update identified risks. High Probability/High Impact risks should be actively managed or avoided.
Stage II – Evaluate
08
Pre-Contract Risk Management - An ACE guide
Stage III - MitigateAt this stage, you should consider whether or not it is possible to reduce or control the identified risks. Can the risks be reduced? If so, draw up an action plan.
Can the risks be controlled contractually?
• Are there liability caps?• Is there a net contribution clause?• Can the contract be made subject to reasonable
skill and care?• Are you being requested to indemnify and/or hold
the client harmless from particular losses?• Are you in a position to propose, or insist on,
amendments to the contract?• Should the risks or the project be declined?
Stage IV - TransferTransferring all or part of the risk can reduce the possible impact on your business to an acceptable level. This can be done:
• Through the contract • By outsourcing/sub-contracting• Through your insurance
07
Pre-Contract Risk Management - An ACE guide08
GA
TE
WA
Y/O
PP
OR
TU
NIT
Y S
TAG
E
PR
OJE
CT
NA
ME
Sub
mit
expr
essi
on o
f int
eres
tYe
s or
no
PR
OJE
CT
RE
FER
EN
CE
Sub
mit
pre-
qual
ifica
tion
Yes
or n
o
OP
PO
RT
UN
ITY
/BID
MA
NA
GE
RS
ubm
it bi
dYe
s or
no
DA
TE
Acc
ept a
ppoi
ntm
ent
Yes
or n
o
Risk ID
Description of Risk
Probability )High/Medium/Low(
Impact)High/Medium/Low(
INITIAL RISK SCORE
Risk Owner
Target Score
Risk Allocation (avoidance, reduction, transfer)
CONTROL MEASURE or ACTION REQUIRED
Target Date
Review Date
Risk Status (open or closed)
1 2 3 4 5 6 7 8 9 10RIS
K ID
EN
TIF
ICA
TIO
NR
ISK
AS
SE
SS
ME
NT
RIS
K R
ES
PO
NS
ER
ISK
MO
NIT
OR
ING
Sco
ring
wou
ld d
epen
d on
the
natu
re o
f the
con
trac
t. Fo
r in
stan
ce, u
nlim
ited
assi
gnm
ents
on
colla
tera
l w
arra
ntie
s m
ay b
e co
nsid
ered
hig
her
than
a ‘2
’ for
so
me
cont
ract
s. F
urth
erm
ore,
poo
r sc
ope
defin
ition
m
ay a
lso
be c
onsi
dere
d hi
gher
than
a ‘2
’.
Key
:H
igh
prob
abilit
y or
impa
ct3
Ris
k R
atin
g:R
edR
isk
scor
e is
6 to
9
Med
ium
pro
babi
ity o
r im
pact
2
Am
ber
Ris
k sc
ore
is 3
to 5
Low
pro
babi
lity
or im
pact
1
Gre
enR
isk
scor
e is
1 o
r 2
App
endi
x: B
lank
Pro
For
ma
Ris
k R
egis
ter
Pre-Contract Risk Management - An ACE guide 09
RISK PROBABILITY
HIGH MEDIUM LOW
Score 3 2 1
RISK HIGH 3 Red (9) Red (6) Amber (3)
IMPACT MEDIUM 2 Red (6) Amber (4) Green (2)
LOW 1 Amber (3) Green (2) Green (1)
Notes:1. The risk scores and classification can be amended to suit each contract.
Appendix: Example Risk Matrix
Pre-Contract Risk Management - An ACE guide
Risk ID
Description of Risk
Probability High/Medium/Low
Impact High/Medium/Low
INITIAL RISK SCORE
Risk Owner
Target Score
Risk Allocation (avoidance, reduction, transfer)
CONTROL MEASURE or ACTION REQUIRED
Target Date
Review Date
Risk Status (open or closed)
1C
laus
e 2.
2 re
qui
res
the
pro
visi
on o
f a
colla
tera
l war
rant
y w
ith u
nlim
ited
as
sign
men
ts
MM
4S
P2
Red
uctio
nQ
ualif
y b
id a
nd li
mit
assi
gnm
ents
to
one
6/1/
2008
6/1/
2008
Clo
sed
2U
nlim
ited
PI l
imit
req
uire
d b
y co
ntra
ct
doc
s
MH
6D
P4
Avo
idQ
ualif
y b
id a
nd a
dd
ca
p t
o P
I lia
bili
ty7/
1/20
088/
1/20
09O
pen
3P
oor
scop
e d
efin
ition
in c
ontr
act
doc
s re
gard
ing
the
des
ign
of b
asem
ent
wor
ks
MH
6H
P2
Tran
sfer
Tran
sfer
des
ign
risk
to g
roun
d w
orks
su
b c
onsu
ltant
. R
evis
e sc
ope
of
app
oint
men
t. C
heck
P
I cov
er.
7/1/
2008
8/1/
2009
Op
en
4 5 6 7 8 9 10
GA
TE
WA
Y/O
PP
OR
TU
NIT
Y S
TAG
E
PR
OJE
CT
NA
ME
XX
Sub
mit
expr
essi
on o
f int
eres
tYe
s or
no
PR
OJE
CT
RE
FER
EN
CE
333-
333
Sub
mit
pre-
qual
ifica
tion
Yes
or n
o
OP
PO
RT
UN
ITY
/BID
MA
NA
GE
RS
PS
ubm
it bi
dYe
s or
no
PR
OC
UR
EM
EN
T S
TAG
EP
req
ualif
icat
ion
Acc
ept a
ppoi
ntm
ent
Yes
or n
o
Key
:H
igh
prob
abilit
y or
impa
ct3
Ris
k R
atin
g:R
edR
isk
scor
e is
6 to
9
Med
ium
pro
babi
ity o
r im
pact
2
Am
ber
Ris
k sc
ore
is 3
to 5
Low
pro
babi
lity
or im
pact
1
Gre
enR
isk
scor
e is
1 o
r 2
App
endi
x: E
xam
ple
Ris
k R
egis
ter
10
RIS
K ID
EN
TIF
ICA
TIO
NR
ISK
AS
SE
SS
ME
NT
RIS
K R
ES
PO
NS
ER
ISK
MO
NIT
OR
ING
Pre-Contract Risk Management - An ACE guide
AcknowledgementsThis guide was produced by ACE with support from ACE’s Legal and Liability Group.
11
20
Association for Consultancy and EngineeringAlliance House 12 Caxton Street London SW1H 0QLT: 020 7222 6557F: 020 7990 9202consult@acenet.co.ukwww.acenet.co.uk