Project Factsheet – Renovation Works of Lok Fu Shopping Centre Phase 1, Wang Tau Hom

Page 1 of 2 Renovation Works of Lok Fu Shopping Centre Phase 1, Wang Tau Hom

Project: Renovation Works of Lok Fu Shopping Centre Phase 1, Wang Tau Hom

Original Contract Sum: HK$26 million

Contract Start Date: June 2007

Contract Completion Date: April 2008

Client: The Link Management Limited

Project Factsheet – Renovation Works of Lok Fu Shopping Centre Phase 1, Wang Tau Hom

Page 2 of 2 Renovation Works of Lok Fu Shopping Centre Phase 1, Wang Tau Hom

Description:

Overall renovation of 3 storeys shopping centre. The works includes alternation of shop layout; construction of new staircases;

replacement of escalators; interior fitting-out works; installation and diversion of building services; installation of cladding system for

covered walkway as well as exterior landscaping works.